JPH0739741B2 - Elevating frame stand - Google Patents
Elevating frame standInfo
- Publication number
- JPH0739741B2 JPH0739741B2 JP8612386A JP8612386A JPH0739741B2 JP H0739741 B2 JPH0739741 B2 JP H0739741B2 JP 8612386 A JP8612386 A JP 8612386A JP 8612386 A JP8612386 A JP 8612386A JP H0739741 B2 JPH0739741 B2 JP H0739741B2
- Authority
- JP
- Japan
- Prior art keywords
- formwork
- frame
- push
- stand
- elevating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、地上1階に配置したプラントにおいて、1階
分の建物をロボット等の機械を用いて集中的に生産し、
1階分の躯体工事完了後に階高分だけ上方にプッシュア
ップすることを繰り返すことによって建物全体を生産す
るプッシュアップ工法に使用される型枠昇降架台に関す
る。DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention is a plant arranged on the first floor above the ground, which intensively produces a building on the first floor using a machine such as a robot.
The present invention relates to a formwork elevating platform used in a push-up construction method for producing an entire building by repeatedly pushing up by a height corresponding to the height of a building after the construction of the first floor is completed.
一般に、中高層のコンクリート建物を建築する場合、最
上階まで柱を建て、梁、ブレースを取り付けてから各階
の型枠の組立て、配筋、コンクリート打設、型枠の解
体、壁部材取り付け等が行われているが、近年、中高層
のコンクリート建築生産において、自動化施行の試みが
幾つかなされている。例えば、体育館等の大きな屋根を
地上で組み立てた後、油圧ジャッキによりプッシュアッ
プする方法や、最初に最上階までの柱を構築した後、地
上レベルでスラブを生産し、これを最上階に取付けたウ
ィンチで順次引き上げてゆく方法、さらに、地上レベル
で複数のプレハブのブロックを結合して、これを油圧ジ
ャッキ等により階高分プッシュアップし、再び地上レベ
ルで複数のプレハブのブロックを結合して、順次プッシ
ュアップして中高層のコンクリート建物を生産してゆく
方法等が知られている。Generally, when constructing a middle-high-rise concrete building, pillars are built up to the top floor, beams and braces are attached, and then formwork assembly on each floor, reinforcement, concrete placement, formwork disassembly, wall member installation, etc. are performed. However, in recent years, several attempts have been made to implement automation in the production of medium- and high-rise concrete buildings. For example, after assembling a large roof such as a gymnasium on the ground and pushing up with a hydraulic jack, or after first constructing the pillars up to the top floor, producing slabs on the ground level and attaching this to the top floor. A method of pulling up sequentially with a winch, further, combining a plurality of prefabricated blocks at the ground level, pushing this up by the floor height with a hydraulic jack etc., and again combining a plurality of prefabricated blocks at the ground level, It is known to push up one by one to produce middle- and high-rise concrete buildings.
また、地上レベルで1階分の建物を集中的に生産し、1
階分の躯体工事完了後に階高分だけ上方にプッシュアッ
プすることを繰り返すことによって建物全体を生産する
という考え方自体は、研究論文等で紹介されている。In addition, by intensively producing buildings on the first floor at the ground level,
The concept itself of producing the entire building by repeatedly pushing up by the height of the floor after the completion of the building work for the floor is introduced in research papers.
しかしながら、このような従来の工法では、機械を用い
てシステム的に建物を生産し、建築における自動化率を
向上させ、労働生産性の向上を図ることは困難であっ
た。However, with such a conventional construction method, it is difficult to systematically produce a building by using a machine, improve the automation rate in the construction, and improve labor productivity.
また、体育館等の大きな屋根を地上で組み立てた後、プ
ッシュアップする方法においては、プッシュアップは1
回だけであり、繰り返し性がなく多層階の建築生産に適
用させることに不可能である。また、最初に最上階まで
の柱を構築した後、地上レベルでスラブを生産し、これ
を最上階に取付けたウィンチで順次引き上げてゆく方法
においては、重量物を柱のみで支持しなければならず、
地震に対する構造的強度が弱いと言う問題を有してい
る。さらに、地上レベルで複数のプレハブのブロックを
結合して順次プッシュアップして中高層のコンクリート
建物を生産する方法においては、プレハブ自体が当初か
ら柱、構造壁、スラブ等を備えているので、現場での中
高層のコンクリート建築生産にこれを適用することは困
難である。また、地上レベルで1階分の建物を集中的に
生産し、上方にプッシュアップすることを繰り返すこと
によって建物全体を生産するという考え方においては、
抽象的な開示にとどまり、既に出来上がっている建物が
空間的制約を与えるなかで、柱生産、構造壁生産、スラ
ブ生産或いはプッシュアップ方法等の具体的な技術的課
題およびその解決策が何ら示されていない。Also, in the method of pushing up after assembling a large roof such as a gymnasium on the ground, the push up is 1
It is only one time, and it is impossible to apply it to multi-story building production without repeatability. Also, in the method of first constructing the pillars up to the top floor, then producing slabs at the ground level and sequentially lifting them with winches attached to the top floor, heavy objects must be supported only by the pillars. No
It has a problem of weak structural strength against earthquakes. Furthermore, in the method of connecting a plurality of prefabricated blocks at the ground level and sequentially pushing up to produce a high-rise concrete building, the prefab itself has columns, structural walls, slabs, etc. from the beginning, so on-site It is difficult to apply this to the production of medium- and high-rise concrete building. In addition, in the idea that the entire building is produced by intensively producing the first floor building at the ground level and repeatedly pushing up,
It is only abstract disclosure, and concrete technical issues such as pillar production, structural wall production, slab production, or push-up method and their solutions are shown, while already completed buildings give spatial constraints. Not not.
本発明は上記問題点を解決しようとするもので、とくに
プッシュアップ工法に採用される具体的な型枠昇降架台
を提供すること目的とし、以て、人手による作業を極力
不要にし、建築の生産性を向上することを目的とする。The present invention is intended to solve the above problems, and particularly aims to provide a concrete form frame elevating / lowering platform adopted in the push-up method, thereby making manual work as unnecessary as possible and producing a building. The purpose is to improve the sex.
〔問題点を解決するための手段〕 そのために本発明の型枠昇降架台は、4角のコーナー部
に切欠部を有する型枠架台と、該型枠架台に配設され型
枠架台をプッシュアップ装置に沿って昇降させる昇降機
構と、前記切欠部を塞ぐための補助型枠と、型枠架台に
配設され前記補助型枠をスライドさせるための補助型枠
スライド機構とを備えることを特徴とするもので、さら
には、4角のコーナー部に切欠部を有する型枠架台と、
該型枠架台に配設され型枠架台をプッシュアップ装置に
沿って昇降させる昇降機構と、前記切欠部を塞ぐための
補助型枠と、型枠架台に配設され前記補助型枠をスライ
ドさせるための補助型枠スライド機構と、型枠架台の裏
面にバイブレータを配設したことを特徴とするものであ
る。[Means for Solving Problems] For that purpose, the formwork lifting / lowering stand of the present invention has a formwork stand having notches at four corners, and a pushup of the formwork stand arranged on the formwork stand. An elevation mechanism for elevating and lowering along the device, an auxiliary formwork for closing the notch, and an auxiliary formwork slide mechanism arranged on the formwork stand for sliding the auxiliary formwork, In addition, a frame mount having notches at the four corners,
An elevating mechanism which is disposed on the frame frame and moves the frame frame up and down along a push-up device, an auxiliary frame for closing the notch, and an auxiliary frame which is disposed on the frame frame and slides the auxiliary frame. It is characterized in that an auxiliary form slide mechanism for this purpose and a vibrator are arranged on the back surface of the form frame stand.
型枠昇降架台に装備された昇降用モータによりピニオン
が駆動し、該ピニオンがプッシュアップ装置のフレーム
に形成されたラックギヤと噛み合いながら、型枠架台を
上昇させる。この作業で型枠の大部分が形成されるが、
プッシュアップ装置の上面や梁との隙間が型枠のダメと
して取残される。このダメを埋めるために、型枠昇降架
台に内蔵された補助型枠スライド機構を作動させ、補助
型枠を油圧シリンダで押し出す。A pinion is driven by an elevating motor provided in the mold frame, and the mold frame is raised while the pinion meshes with a rack gear formed on the frame of the push-up device. Most of the formwork is formed by this work,
A gap between the upper surface of the push-up device and the beam is left as a useless frame. In order to fill this failure, the auxiliary form slide mechanism incorporated in the form elevating platform is operated and the auxiliary form is pushed out by the hydraulic cylinder.
先ず、本発明が適用されるプッシュアップ工法に使用さ
れるプラントについて概略説明する。First, a plant used in the push-up method to which the present invention is applied will be briefly described.
第3図は、プッシュアップ工法に使用されるプラント構
成を示す図である。図中、10は最上階、11は上階、12は
下階、13はプッシュアップ装置、14は柱搬送ロボット、
15は柱、16は軌道、17は壁部材搬送ロボット、18は壁部
材取付ロボット、19は梁、20はブレース、21は型枠昇降
架台、22は配筋ロボット、23はコンクリート打設・均ら
しロボットである。FIG. 3 is a diagram showing a plant configuration used in the push-up method. In the figure, 10 is the top floor, 11 is the upper floor, 12 is the lower floor, 13 is a push-up device, 14 is a pillar transfer robot,
15 is a pillar, 16 is a track, 17 is a wall member transfer robot, 18 is a wall member mounting robot, 19 is a beam, 20 is a brace, 21 is a formwork elevating platform, 22 is a bar arrangement robot, and 23 is concrete placing and leveling. It is a rush robot.
このプッシュアップ工法は、最上階生産、基準階生産お
よび最下階生産の3つの大きなシステムにより構成さ
れ、このうち基本となるシステムは、繰り返し性のある
基準階生産システムである。この基準階生産システム
は、大別して柱生産システム、構造壁生産システム、ス
ラブ生産システムおよびプッシュアップシステムの4つ
のサブシステムからなり、柱生産システムには柱搬送ロ
ボット14が、構造壁生産システムには壁部材搬送ロボッ
ト17および壁部材取付ロボット18が、スラブ生産システ
ムには型枠昇降架台21、配筋ロボット22、コンクリート
打設・均らしロボット23が、プッシュアップシステムに
はプッシュアップ装置13が使用される。そして、このプ
ラントでの生産作業は、作業高さによって上階と下階に
分けられて、柱生産は下階で行われ、床生産および構造
壁生産は上階で行われる。This push-up method is composed of three major systems: top floor production, standard floor production and bottom floor production, of which the basic system is a repeatable standard floor production system. This standard floor production system is roughly divided into four sub-systems: a column production system, a structural wall production system, a slab production system, and a push-up system. The column production system includes a column transfer robot 14, and the structural wall production system includes a sub-system. The wall member transfer robot 17 and the wall member mounting robot 18 are used for the slab production system, the formwork lifting platform 21, the bar arrangement robot 22, the concrete placing and leveling robot 23, and the pushup system 13 is the pushup device 13. To be done. The production work in this plant is divided into an upper floor and a lower floor according to the working height, pillar production is performed in the lower floor, and floor production and structural wall production are performed in the upper floor.
また、最上階生産および最下階生産の両システムには、
基準階生産システムと異なる点、例えば、最上階生産シ
ステムでは、柱の長さ、ペントハウスの生産があり、最
下階生産システムでは、地上躯体と地下躯体の接合など
がある。これらの異なる点を基準階生産システムの例外
事項としてとらえ、最上階生産および最下階生産の両シ
ステムの構成を基準階生産システムと同様にしている。
そして、ロボットや制御技術を導入することにより自動
化率を高める建築生産システムを可能にし、地上に設置
したプラントで1階部分の建物を集中的に生産し、これ
を階高分だけ上方にプッシュアップするというサイクル
を繰り返すことにより建物を生産するものである。In addition, both the top floor production system and the bottom floor production system,
Different from the standard floor production system, for example, in the top floor production system, there are pillar lengths and penthouse production, and in the bottom floor production system, there are joining of the above-ground structure and the underground structure. By taking these different points as an exception to the standard floor production system, the configurations of both the top floor production system and the bottom floor production system are made the same as the standard floor production system.
Then, by introducing robots and control technology, it enables a building production system that increases the automation rate, and centrally produces buildings on the first floor with a plant installed on the ground, and pushes this up by the height of the floor. The building is produced by repeating the cycle of doing.
次に、プッシュアップ工法の詳細について、第4図およ
び第5図(イ)ないし(ホ)に示す行程図で順を追って
説明する。Next, details of the push-up method will be described step by step with reference to the process diagrams shown in FIGS. 4 and 5 (a) to (e).
(A1)先ず、根切り、基礎、B1Fの躯体工事までは従来
通りの建築行程で行う。次に、プッシュアップ装置13、
型枠昇降架台21、建物外周の軌道16等で構成されるプラ
ントを設置し、このプラントを用いてペントハウスから
生産を開始する。(A2)型枠昇降架台21を上昇させ、柱
搬送ロボット14が柱15を搬送し、プッシュアップ装置13
の上方から柱15を落とし込んでプッシュアップ装置13に
渡す。(A3)型枠昇降架台21を下降させた後、壁部材搬
送ロボット17が軌道16を走行し、梁仕口30および梁19を
壁部材取付ロボット18まで搬送する。壁部材取付ロボッ
ト18は、壁部材搬送ロボット17上の梁仕口30を取り上
げ、柱15と梁仕口30とを溶接接合する。梁仕口30の接合
完了後、壁部材取付ロボット18は同様にして梁19の接合
を行う。(A4)型枠昇降架台21を上昇させた後、配筋ロ
ボット22が先組鉄筋31を型枠昇降架台21上に配設する。
(A5)コンクリート打設・均らしロボット23により型枠
昇降架台21上に生コンを分配し、コンクリートを均らし
養生を行う。(A6)養生完了後、型枠昇降架台21を下降
させ、次いでプッシュアップ装置13により、柱15を階高
分だけプッシュアップさせてペントハウス25の生産が完
了する。(A 1 ) First, the root cutting, foundation, and B1F frame work will be carried out in the conventional building process. Next, the push-up device 13,
A plant consisting of a formwork lift 21 and a track 16 around the building is installed, and production is started from the penthouse using this plant. (A 2 ) The form raising / lowering platform 21 is raised, and the column transfer robot 14 transfers the column 15 to the push-up device 13
The pillar 15 is dropped from above and passed to the push-up device 13. After lowering the (A 3) mold elevating frame 21, the wall member carrying robot 17 traveling on the track 16 transports the beam Joint 30 and beam 19 to the wall member mounted robot 18. The wall member mounting robot 18 picks up the beam joint 30 on the wall member transfer robot 17 and welds the column 15 and the beam joint 30 to each other. After the beam joint 30 is completely joined, the wall member mounting robot 18 similarly joins the beams 19. After raising the (A 4) mold elevating frame 21, Haisuji robot 22 is disposed on the mold elevating frame 21 ahead sets rebar 31.
(A 5 ) Concrete pouring and leveling robot 23 distributes ready-mixed concrete on the formwork platform 21 to level and cure concrete. (A 6) after curing completion, lowering the mold elevating frame 21, and then by a push-up device 13, the pillars 15 by story height amount corresponding push up the production of penthouse 25 completed.
(B1)次に、最上階および屋上部の生産を開始する。屋
上部32側では型枠昇降架台21を上昇させ、柱搬送ロボッ
ト14が柱15を搬送し、プッシュアップ装置13の上方から
柱15を落とし込んでプッシュアップ装置13に渡す。一
方、ペントハウス25側ではプッシュアップ装置13の側方
から柱15を供給し、上下の柱を溶接する。(B2)屋上部
32側の型枠昇降架台21を下降させた後、壁部材搬送ロボ
ット17が軌道16を走行し、梁仕口30、ブレース33および
梁19を壁部材取付ロボット18まで搬送する。壁部材取付
ロボット18は、壁部材搬送ロボット17上の梁仕口30、ブ
レース20および梁19を取り上げ、柱15と梁仕口30、ブレ
ース20および梁19とを溶接接合する。(B3)型枠昇降架
台21を上昇させた後、配筋ロボット22が先組鉄筋31を型
枠昇降架台21上に配設する。(B4)コンクリート打設・
均らしロボット23により型枠昇降架台21上に生コンを分
配し、コンクリートを均らす。(B5)コンクリートの養
生を行っている間に、ペントハウス25の外壁35を取付け
る。(B6)養生完了後、型枠昇降架台21を下降させ、次
いでプッシュアップ装置13により、柱15を階高分だけプ
ッシュアップさせる。(B 1 ) Next, start production on the top floor and rooftop. On the rooftop 32 side, the form raising / lowering platform 21 is lifted, the pillar transport robot 14 carries the pillar 15, and the pillar 15 is dropped from above the push-up device 13 and passed to the push-up device 13. On the other hand, on the penthouse 25 side, the columns 15 are supplied from the side of the push-up device 13 and the upper and lower columns are welded. (B 2 ) Roof top
After lowering the frame elevating platform 21 on the 32 side, the wall member transfer robot 17 travels on the track 16 and transfers the beam joint 30, the brace 33 and the beam 19 to the wall member mounting robot 18. The wall member mounting robot 18 picks up the beam joint 30, the brace 20 and the beam 19 on the wall member transfer robot 17, and welds the column 15 to the beam joint 30, the brace 20 and the beam 19. (B 3 ) After raising the formwork elevating / lowering platform 21, the bar arrangement robot 22 arranges the pre-assembled reinforcing bars 31 on the formwork elevating / lowering platform 21. (B 4 ) Concrete pouring
The leveling robot 23 distributes the ready-mixed concrete on the formwork platform 21 to level the concrete. (B 5) while performing curing of the concrete, attaching the outer wall 35 of the penthouse 25. (B 6) after curing completion, lowering the mold elevating frame 21, and then by a push-up device 13, thereby pushing the pillar 15 only story height min up.
(C1)次に、基準階の生産を開始する。プッシュアップ
装置13の側方から柱15を供給し、上下の柱間を溶接す
る。(C2)壁部材搬送ロボット17が軌道16を走行し、梁
仕口30、ブレース20および梁19を壁部材取付ロボット18
まで搬送する。壁部材取付ロボット18は、壁部材搬送ロ
ボット17上の梁仕口30、ブレース33および梁19を取り上
げ、柱15と梁仕口30、ブレース20および梁19とを溶接接
合する。(C3)型枠昇降架台21を上昇させた後、配筋ロ
ボット22が先組鉄筋31を型枠昇降架台21上に配設する。
(C4)コンクリート打設・均らしロボット23により型枠
昇降架台21上に生コンを分配し、コンクリートを均ら
す。(C5)コンクリートの養生を行っている間に外壁35
を取付ける。(C6)養生完了後、型枠昇降架台21を下降
させ、次いでプッシュアップ装置13により、柱15を階高
分だけプッシュアップさせる。(C 1 ) Next, production of the standard floor is started. The pillar 15 is supplied from the side of the push-up device 13 and the upper and lower pillars are welded to each other. (C 2 ) The wall member transfer robot 17 travels on the track 16, and the beam member 30, the brace 20, and the beam 19 are attached to the wall member robot 18.
Transport to. The wall member mounting robot 18 picks up the beam joint 30, the brace 33 and the beam 19 on the wall member transfer robot 17, and welds the column 15 to the beam joint 30, the brace 20 and the beam 19. (C 3 ) After raising the formwork elevating platform 21, the bar arrangement robot 22 arranges the pre-assembled reinforcing bars 31 on the formwork elevating frame 21.
(C 4 ) Concrete pouring / leveling robot 23 distributes ready-mixed concrete on the formwork platform 21 to level the concrete. (C 5 ) Outer wall 35 while curing concrete
Install. (C 6 ) After the curing is completed, the formwork platform 21 is lowered, and then the pillar 15 is pushed up by the push-up device 13 by the height of the floor.
(D1)最後に、最下階の生産を開始する。プッシュアッ
プ装置13の側方から柱15を供給し、柱15と上部の柱およ
び下部の基礎体とを溶接する。(D2)プッシュアップ装
置13の上部を切断し撤去する。(D3)壁部材搬送ロボッ
ト17および壁部材取付ロボット18により、柱15と梁仕口
30、ブレース20および梁19とを溶接接合する。(D4)型
枠昇降架台21を上昇させた後、配筋ロボット22が先組鉄
筋31を型枠昇降架台21上に配設する。(D5)コンクリー
ト打設・均らしロボット23により型枠昇降架台21上に生
コンを分配し、コンクリートを均らす。(D6)コンクリ
ートの養生を行っている間に外壁35を取付ける。(D7)
プッシュアップ装置13、型枠昇降架台21、建物外周の軌
道16等で構成されるプラントを解体撤去する。(D8)1
階部分にブレース20を溶接接合する。(D9)1階部分の
内外装を行って建物が完成する。次に、第1図および第
2図により上記型枠昇降架台21について説明する。第1
図は本発明の型枠昇降架台の1実施例を示す平面図、第
2図は第1図の側面図である。(D 1 ) Finally, start the production of the bottom floor. The pillar 15 is supplied from the side of the push-up device 13 and the pillar 15 is welded to the upper pillar and the lower base body. (D 2 ) The upper part of the push-up device 13 is cut and removed. (D 3 ) The wall member transfer robot 17 and the wall member mounting robot 18 allow the pillar 15 and the beam joint
The 30, brace 20 and beam 19 are welded together. (D 4 ) After raising the formwork elevating / lowering platform 21, the bar arrangement robot 22 arranges the pre-assembled reinforcing bars 31 on the formwork elevating / lowering platform 21. (D 5 ) Concrete pouring / leveling robot 23 distributes ready-mixed concrete on the formwork lifting platform 21 to level the concrete. (D 6 ) Install outer wall 35 while curing concrete. (D 7 )
A plant including a push-up device 13, a formwork lifting platform 21, and a track 16 around the building is demolished and removed. (D 8 ) 1
Weld the braces 20 to the floor. (D 9 ) The interior and exterior of the first floor will be completed to complete the building. Next, the formwork elevating stand 21 will be described with reference to FIGS. 1 and 2. First
FIG. 1 is a plan view showing an embodiment of the frame raising / lowering stand of the present invention, and FIG. 2 is a side view of FIG.
型枠昇降架台21は、4本の柱15をプッシュアップさせる
ためのプッシュアップ装置13、13…で囲まれる空間に配
設され、4角のコーナー部に切欠部50が形成された型枠
架台51を有している。この型枠架台51のコーナー部の前
記切欠部50には、それぞれ2個の昇降用モータ52、52お
よび該モータ52により駆動されるピニオン(図示せず)
が設置されている。一方、プッシュアップ装置13のフレ
ーム53には前記ピニオンと噛み合うラックギヤ55が形成
されている。また、型枠架台51には、4台の補助型枠ス
ライド機構56が配設され、該補助型枠スライド機構56は
油圧シリンダ57により摺動自在な補助型枠59から構成さ
れている。さらに、型枠架台51の裏面にはコンクリート
を締固めるためのバイブレータ60が取付けられている。The formwork lifting / lowering base 21 is arranged in a space surrounded by push-up devices 13, 13 ... For pushing up the four pillars 15, and a formwork base having notches 50 at four corners. Has 51. Two notch motors 52 and 52 and pinions (not shown) driven by the motors 52 are respectively provided in the notches 50 at the corners of the frame base 51.
Is installed. On the other hand, a rack gear 55 that meshes with the pinion is formed on the frame 53 of the push-up device 13. Further, four auxiliary mold slide mechanisms 56 are arranged on the mold frame 51, and the auxiliary mold slide mechanism 56 is composed of an auxiliary mold 59 slidable by a hydraulic cylinder 57. Further, a vibrator 60 for compacting concrete is attached to the back surface of the formwork stand 51.
その動作について説明すると、プッシュアップ装置13に
より柱15のプッシュアップが完了すると、型枠昇降架台
21に装備された昇降用モータ52によりピニオンが駆動
し、該ピニオンがプッシュアップ装置13のフレーム53に
形成されたラックギヤ55と噛み合いながら、型枠架台51
を上昇させる。型枠架台51はセンサにより所定位置を検
出して自動的にスラブ形成位置に停止する。この作業で
型枠の大部分が形成されるが、プッシュアップ装置13の
上面や梁との隙間が型枠のダメ(切欠部50に相当)とし
て取残される。このダメを埋めるために、型枠昇降架台
21に内蔵された補助型枠スライド機構56を作動させ、補
助型枠59を油圧シリンダ57で押し出し、前記ダメを塞ぐ
ようにしている。この補助型枠59のスライドもセンサに
より自動的に制御される。The operation will be described. When the push-up device 13 completes the push-up of the column 15,
A pinion is driven by a lifting / lowering motor 52 mounted on the 21. The pinion engages with a rack gear 55 formed on a frame 53 of the push-up device 13 to form a frame stand 51.
Raise. The formwork stand 51 detects a predetermined position by a sensor and automatically stops at the slab formation position. Although most of the formwork is formed by this work, the gap between the upper surface of the push-up device 13 and the beam is left as a useless part of the formwork (corresponding to the notch 50). In order to fill this mess,
The auxiliary form slide mechanism 56 built in the 21 is operated, and the auxiliary form 59 is pushed out by the hydraulic cylinder 57 so as to close the useless part. The slide of the auxiliary mold 59 is also automatically controlled by the sensor.
次に、ビニールシートを型枠架台51上に敷設し、スラブ
配筋、コンクリートの打設を行った後、型枠架台51の裏
面に取付けたバイブレート60を作動させ、型枠昇降架台
21全体を振動させて型枠架台51上の生コンを締め固め
る。バイブレータ60はタイマーにより一定時間経過後、
自動的に停止される。Next, after laying a vinyl sheet on the formwork stand 51, placing slabs and placing concrete, activate the vibrate 60 attached to the back of the formwork stand 51 to move the formwork lift stand.
21 Vibrate the whole and consolidate the ready-mixed concrete on the formwork stand 51. The vibrator 60 is set by a timer after a certain period of time,
It will be stopped automatically.
コンクリートの養生が完了すると、型枠昇降架台21に内
蔵された補助型枠スライド機構56を作動させ、補助型枠
59を油圧シリンダ57により引戻し、型枠昇降架台21内に
格納する。その後、型枠昇降架台21を下階作業床のレベ
ルまで下降させ、次のスラブ生産のサイクルまで待機さ
せるものである。When the curing of the concrete is completed, the auxiliary form slide mechanism 56 built into the form lift platform 21 is activated to
59 is pulled back by the hydraulic cylinder 57 and stored in the frame elevating platform 21. After that, the formwork elevating platform 21 is lowered to the level of the lower floor work floor, and is kept waiting until the next slab production cycle.
なお、本発明は上記実施例に限定されるものではなく、
種々の変形が可能であることは勿論のことである。例え
ば、型枠昇降架台21に内蔵された補助型枠スライド機構
56は、油圧駆動にかぎらずモータ駆動でもよいし、型枠
昇降機構は油圧駆動によってもよい。The present invention is not limited to the above embodiment,
Of course, various modifications are possible. For example, the auxiliary formwork slide mechanism built in the formwork lift base 21.
56 is not limited to being hydraulically driven, and may be motor-driven, or the form raising / lowering mechanism may be hydraulically driven.
以上の説明から明らかなように、本発明によれば、下記
の効果が奏されるものである。As is apparent from the above description, the present invention has the following effects.
(イ)型枠の組立、解体が省略でき生産性の向上を図る
ことができる。(B) Assembly and disassembly of the mold can be omitted and productivity can be improved.
(ロ)型枠昇降架台を配筋作業、コンクリート打設作業
等のための床として使用することにより、機械化、自動
化率が高くなり安全性の向上を図ることが可能となる。(B) By using the formwork elevating platform as a floor for arranging work, concrete placing work, etc., it becomes possible to improve the safety by increasing the mechanization and automation rate.
(ハ)高所作業が減少し安全性が増大する。(C) Work at high places is reduced and safety is increased.
(ニ)足場を構築しないで外装仕上げを行うことが可能
となる。(D) It is possible to finish the exterior without constructing a scaffold.
第1図は本発明の型枠昇降架台の1実施例を示す平面
図、第2図は第1図の側面図、第3図はプッシュアップ
システムのプラント構成の1実施例を示す図、第4図は
プッシュアップ工法による行程を示す図である。 13……プッシュアップ装置、15……柱、21……型枠昇降
架台、50……切欠部、51……型枠架台、52……昇降用モ
ータ、53……フレーム、55……ラックギヤ、56……補助
型枠スライド機構、57……油圧シリンダ、59……補助型
枠、60……バイブレータ。FIG. 1 is a plan view showing one embodiment of a formwork lifting / lowering stand of the present invention, FIG. 2 is a side view of FIG. 1, and FIG. 3 is a view showing one embodiment of a push-up system plant configuration. FIG. 4 is a diagram showing a process by the push-up method. 13 …… Push-up device, 15 …… Pillar, 21 …… Form frame lifting frame, 50 …… Notched part, 51 …… Form frame frame, 52 …… Moving motor, 53 …… Frame, 55 …… Rack gear, 56 …… auxiliary form slide mechanism, 57 …… hydraulic cylinder, 59 …… auxiliary form, 60 …… vibrator.
───────────────────────────────────────────────────── フロントページの続き (71)出願人 999999999 佐藤工業株式会社 富山県富山市桜木町1番11号 (71)出願人 999999999 清水建設株式会社 東京都中央区京橋2丁目16番1号 (71)出願人 999999999 大成建設株式会社 東京都新宿区西新宿1丁目25番1号 (71)出願人 999999999 株式会社竹中工務店 大阪府大阪市東区本町4丁目27番地 (71)出願人 999999999 戸田建設株式会社 東京都中央区京橋1丁目7番1号 (71)出願人 999999999 株式会社フジタ 東京都渋谷区千駄ヶ谷4丁目6番15号 (71)出願人 999999999 株式会社小松製作所 東京都港区赤坂2丁目3番6号 (71)出願人 999999999 日立造船株式会社 大阪府大阪市西区江戸堀1丁目6番14号 (72)発明者 長谷川 幸男 東京都新宿区大久保3−4−1 早稲田大 学システム科学研究所内 (72)発明者 井上 康夫 埼玉県川口市芝園町3丁目4―543 (72)発明者 新井 一彦 埼玉県浦和市仲町2−9−16 (72)発明者 松下 祐輔 東京都新宿区築地町16 ライオンズマンシ ヨン神楽坂第3―102号 (72)発明者 山下 伸二 神奈川県厚木市三田91−1 (72)発明者 奥山 信博 東京都世田谷区代田1−20−8 清水建設 寮 (72)発明者 坪田 章 東京都江東区南砂2−5−14 株式会社竹 中工務店技術研究所内 (72)発明者 森 正人 神奈川県横浜市港北区小机町246番地 (72)発明者 篠崎 徹 茨城県下妻市下木戸24 (72)発明者 吉武 亮二 東京都町田市能ヶ谷町1521−93 (72)発明者 武田 周 神奈川県平塚市万田18 小松製作所平塚寮 311号 (72)発明者 国塩 和良 大阪府大阪市西区江戸堀1丁目6番14号 日立造船株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (71) Applicant 999999999 Sato Industry Co., Ltd. 1-11 Sakuragicho, Toyama City, Toyama Prefecture (71) Applicant 999999999 Shimizu Corporation 2-16-1 Kyobashi, Chuo-ku, Tokyo (71) ) Applicant 999999999 Taisei Corporation 1-25-1 Nishishinjuku, Shinjuku-ku, Tokyo (71) Applicant 999999999 Takenaka Corporation Ltd. 4-27, Honmachi, Higashi-ku, Osaka-shi, Osaka (71) Applicant 999999999 Toda Construction Co., Ltd. Company 1-7-1, Kyobashi, Chuo-ku, Tokyo (71) Applicant 999999999 Fujita Co., Ltd. 4-6-15 Sendagaya, Shibuya-ku, Tokyo (71) Applicant 999999999 2-3 Akasaka, Minato-ku, Tokyo No. 6 (71) Applicant 999999999 Hitachi Zosen Corporation 1-6-14 Edobori, Nishi-ku, Osaka-shi, Osaka (72) Inventor Yukio Hasegawa Tokyo 3-4-1 Okubo, Shinjuku-ku, Research Institute for Systems Science, Waseda University (72) Inventor Yasuo Inoue 3-4-543 Shibaencho, Kawaguchi City, Saitama Prefecture (72) Kazuhiko Arai 2-9-16 Nakamachi, Urawa City, Saitama Prefecture (72) Yusuke Matsushita, 16 Tsukiji-cho, Shinjuku-ku, Tokyo No. 3-102, Lions Mansion Kagurazaka (72) Inventor Shinji Yamashita 91-1, Mita, Atsugi, Kanagawa Prefecture (72) Nobuhiro Okuyama, Shirota, Setagaya-ku, Tokyo 1-20-8 Shimizu Construction Dormitory (72) Inventor Akira Tsubota 2-5-14 Minamisuna, Koto-ku, Tokyo Inside the Research Institute of Takenaka Corporation (72) Masato Mori Makoto Mori, Kohoku-ku, Yokohama-shi, Kanagawa 246 (72) Inventor Toru Shinozaki 24 Shimogido, Shimotsuma-shi, Ibaraki (72) Inventor Ryoji Yoshitake 1521-93 Nogaya-cho, Machida-shi, Tokyo (72) Inventor Shu 18 Takeda, Hiratsuka-shi, Kanagawa Komatsu Manufacturing Hiratsuka Dormitory No. 311 (72) Inventor Kura Shio, 1-6-14 Edobori, Nishi-ku, Osaka City, Osaka Prefecture Hitachi Shipbuilding Co., Ltd.
Claims (4)
台と、該型枠架台に配設され型枠架台をプッシュアップ
装置に沿って昇降させる昇降機構と、前記切欠部を塞ぐ
ための補助型枠と、型枠架台に配設され前記補助型枠を
スライドさせるための補助型枠スライド機構とを備える
ことを特徴とする型枠昇降架台。1. A formwork stand having cutouts at four corners, an elevating mechanism arranged on the formwork stand for elevating and lowering the formwork stand along a push-up device, and for closing the cutouts. And an auxiliary form slide mechanism for sliding the auxiliary form, which is provided on the form frame stand.
ら構成されると共に、上記プッシュアップ装置にはラッ
クギヤが形成され、前記ピニオンとラックギヤにより型
枠架台を昇降させることを特徴とする特許請求の範囲第
1項記載の型枠昇降架台。2. The elevating mechanism comprises an elevating motor and a pinion, and a rack gear is formed in the push-up device, and the pinion and the rack gear elevate and lower the frame stand. Formwork elevating stand according to the first item of the range.
なること特徴とする特許請求の範囲第1項または第2項
記載の型枠昇降架台。3. The formwork elevating / lowering stand according to claim 1, wherein the auxiliary formwork slide mechanism comprises a hydraulic cylinder.
台と、該型枠架台に配設され型枠架台をプッシュアップ
装置に沿って昇降させる昇降機構と、前記切欠部を塞ぐ
ための補助型枠と、型枠架台に配設され前記補助型枠を
スライドさせるための補助型枠スライド機構と、型枠架
台の裏面にバイブレータを配設したことを特徴とする型
枠昇降架台。4. A formwork stand having cutouts at four corners, an elevating mechanism arranged on the formwork stand for raising and lowering the formwork stand along a push-up device, and for closing the cutouts. The auxiliary frame, the auxiliary frame slide mechanism that is provided on the frame frame and slides the auxiliary frame, and the vibrator on the back surface of the frame frame.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8612386A JPH0739741B2 (en) | 1986-04-16 | 1986-04-16 | Elevating frame stand |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8612386A JPH0739741B2 (en) | 1986-04-16 | 1986-04-16 | Elevating frame stand |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6322969A JPS6322969A (en) | 1988-01-30 |
| JPH0739741B2 true JPH0739741B2 (en) | 1995-05-01 |
Family
ID=13877925
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8612386A Expired - Lifetime JPH0739741B2 (en) | 1986-04-16 | 1986-04-16 | Elevating frame stand |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0739741B2 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101296814B1 (en) * | 2013-05-03 | 2013-08-14 | 대영건설 주식회사 | Upper pressing type support building method |
| KR101501959B1 (en) * | 2013-05-03 | 2015-03-12 | 대영건설 주식회사 | Upper pressing type support lifting apparatus |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7177431B2 (en) * | 2018-07-19 | 2022-11-24 | 株式会社大林組 | Lift-up device and tower-like structure construction method |
-
1986
- 1986-04-16 JP JP8612386A patent/JPH0739741B2/en not_active Expired - Lifetime
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101296814B1 (en) * | 2013-05-03 | 2013-08-14 | 대영건설 주식회사 | Upper pressing type support building method |
| KR101501959B1 (en) * | 2013-05-03 | 2015-03-12 | 대영건설 주식회사 | Upper pressing type support lifting apparatus |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6322969A (en) | 1988-01-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP2852724B1 (en) | High rise building elevation concept | |
| CN1028556C (en) | house building system | |
| JP3196043B2 (en) | Construction method of stairs and staircase, construction method of stairs, and stair members | |
| JPH0739741B2 (en) | Elevating frame stand | |
| JPH0483060A (en) | Building construction | |
| JPH0733689B2 (en) | Push-up method and apparatus | |
| JPH0733688B2 (en) | Push-up method | |
| JP2884397B2 (en) | Construction method of building structure and lifting device of building structure | |
| AU2003269072B2 (en) | In-situ construction of concrete building | |
| CN109680811B (en) | A prefabricated steel column node connection structure for assembled buildings and construction method thereof | |
| JPH10317661A (en) | An erect scaffold used to reinforce the perimeter of existing buildings | |
| JP2928002B2 (en) | Column formwork structure | |
| CN110820947B (en) | Modular floor construction process | |
| EP3495578B1 (en) | A method for realising a prefabricated wall for a colum and beam construction made of reinforced concrete, and a method for realising the construction | |
| JP2761526B2 (en) | How to build structures | |
| JPH0387439A (en) | construction method | |
| JP2717142B2 (en) | Construction method of suspended structure | |
| CN120844793A (en) | Method and system for printing multi-story buildings based on gantry concrete 3D printer | |
| JP2878571B2 (en) | Building construction method using construction equipment | |
| JPH05179694A (en) | Construction method of building | |
| JP2761527B2 (en) | How to build structures | |
| JPH03197734A (en) | Lift up method by replacement of scaffold body | |
| JPH0747890B2 (en) | Concrete placing piping system in push-up system | |
| JP2835880B2 (en) | High-rise building frame construction method | |
| JPH0417262B2 (en) |