Jig for building the skeleton of a buildingInfo
- Publication number
- JPH0745779B2 JPH0745779B2 JP27034886A JP27034886A JPH0745779B2 JP H0745779 B2 JPH0745779 B2 JP H0745779B2 JP 27034886 A JP27034886 A JP 27034886A JP 27034886 A JP27034886 A JP 27034886A JP H0745779 B2 JPH0745779 B2 JP H0745779B2
- Authority
- JP
- Japan
- Prior art keywords
- floor
- jig
- pillar
- work
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000009415 formwork Methods 0.000 claims description 10
- 239000011178 precast concrete Substances 0.000 claims description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 description 16
- 239000004567 concrete Substances 0.000 description 12
- 238000009434 installation Methods 0.000 description 5
- 238000000034 method Methods 0.000 description 5
- 230000015572 biosynthetic process Effects 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 238000005755 formation reaction Methods 0.000 description 3
- 238000011065 in-situ storage Methods 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000005266 casting Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】 (産業上の利用分野) 本発明は、建築物の躯体構築用治具に関し、さらに詳し
くは上階の作業床等を下階の床等の現場打ちコンクリー
トの打設前にあらかじめ確保しておくことにより、躯体
構築施工の合理化短縮化を図ったものである。Description: TECHNICAL FIELD The present invention relates to a jig for constructing a skeleton of a building, and more specifically, for placing a work floor or the like on the upper floor on the floor of a lower floor or the like. It is intended to rationalize and shorten the construction of the skeleton by securing it beforehand.
(従来の技術) 一般に建設構造物の構築に際しては、揚重機作業、鉄筋
配筋、型枠建込、コンクリート打設等の各工程を可及的
に効率良く行うことが建設工期を短縮化する上で重要と
なる。(Prior Art) Generally, in constructing a construction structure, it is possible to shorten the construction period by carrying out each process such as lifting machine work, reinforcing bar arrangement, form laying, concrete placing, etc. as efficiently as possible. Will be important above.
しかして、従来の現場打ちコンクリート作業では、第5
図に示すようにある特定のN階の壁、柱、梁等の構造躯
体と、N+1階の床とを同時に打設するのが一般的であ
る。In conventional cast-in-place concrete work,
As shown in the figure, it is general that a specific structural body such as a wall, a pillar or a beam on the Nth floor and a floor on the N + 1th floor are simultaneously cast.
(発明が解決しようとする問題点) ところが、現場打ちコンクリートについては、打設後所
定の強度を発現するまではその部分について次の作業を
進めることができないため、上記例では、N+1階の床
コンクリート打設後直ちに該床を作業床として利用して
該N+1階の壁、柱、梁の鉄筋組、型枠組等の作業を行
なうことが不可能であり、工期短縮化の上で最大の障害
になっていた。(Problems to be solved by the invention) However, as for the cast-in-place concrete, the next work cannot be carried out for that portion until the predetermined strength is exhibited after the casting, so in the above example, the floor on the N + 1 floor Immediately after placing concrete, it is not possible to use the floor as a work floor to perform work on the N + 1 floor walls, columns, beams, reinforcing bars, formwork, etc., which is the biggest obstacle to shortening the construction period. It was.
そこで、床をPC板(プレキェストコンクリート板)にて
成形して、現場では所定位置に揚重載架するだけで直ち
に作業床として利用しようとする工法が提案されてい
る。Therefore, a construction method has been proposed in which the floor is molded from a PC board (pre-cast concrete board), and it is used as a work floor immediately by simply hoisting it at a predetermined position on the site.
この場合、現場作業の省力化をさらに図るために、床の
他に柱や梁をもPC柱、PC梁としてあらかじめ工場等で製
作し、現場では相互の接合部の接合のみを行なう工法も
提案されているが、かかる工法では、PC床、PC柱及びPC
梁が相当の重量となるためクレーン等の揚重機械を用い
て所定の設置位置に仮載置するとともに、相互の位置の
寸法誤差等を修正する必要がある。In this case, in order to further save on-site work, we propose a method in which not only floors but also columns and beams are prefabricated as PC columns and PC beams in factories, etc., and only the joints between them are joined on site. However, in this construction method, PC floor, PC pillar and PC
Since the beam becomes a considerable weight, it is necessary to temporarily mount it at a predetermined installation position using a lifting machine such as a crane and correct dimensional errors between the positions.
しかしながら、微妙な位置調整はクレーン等の揚重機械
の操作では困難であり、最後は現場作業者の手作業に頼
る場合が多いが、前記の如く各部材とも相当の重量物で
あるため、一旦載置した後の調整作業は非常に困難であ
り、調整に長時間を要し、また誤差が大きい場合にはも
う一度揚重機械で吊り上げ、再度調整しなければならな
いという問題があった。However, delicate position adjustment is difficult with operation of a lifting machine such as a crane, and in the end, it often depends on the manual work of the site worker, but as described above, each member is a considerable heavy object, so once The adjustment work after mounting is very difficult, and it takes a long time for the adjustment, and when the error is large, there is a problem that the lifting machine must be lifted again and the adjustment must be performed again.
一方、柱、梁が現場打ちのRC構造(鉄筋コンクリート構
造)の場合、該柱、梁の配筋作業や、型枠組を構築現場
で行う場合には、高所での作業を伴なうため、足場を組
んで作業を行なう必要があり、安全面及び作業性の面で
問題があった。On the other hand, when the pillars and beams have an RC structure (reinforced concrete structure) that is cast in situ, when the reinforcement work of the pillars and beams and the formwork are performed at the construction site, work at high places is involved. It was necessary to work with scaffolding, which was a problem in terms of safety and workability.
そこで、本出願人は、特願昭61−137737号において、先
組鉄筋のなされた梁や柱に地上部分であらかじめ型枠を
も組付けた型枠付先組鉄筋構造体を提案し、上記問題の
解決を図った。Therefore, the present applicant proposed in Japanese Patent Application No. 61-137737 a pre-assembled rebar structure with a formwork, in which the formwork is also pre-assembled on the ground part to the beam or column where the pre-assembled rebar is made. I tried to solve the problem.
しかしながら、この場合でも床をPCに床板として、上記
した如く上階の作業床を早期に確保せんとした場合に
は、現場打ちコンクリート打設前の未完成構造躯体があ
る柱、梁の型枠付先組鉄筋構造体の上部に重量物である
PC床板を直接載架することは強度上不可能である。However, even in this case, if the floor is used as a floorboard for the PC and the work floor on the upper floor is not secured early as described above, the formwork of columns and beams with unfinished structural skeleton before cast-in-place concrete is placed. It is a heavy object on the upper part of the attached assembly rebar structure.
It is impossible to mount the PC floor board directly because of its strength.
そこで、まず下階の柱、梁のコンクリートを打設し、そ
の硬化を待ってからPC床板を設置するしかなく、工期が
長期化することとなり初期の目的に反する。Therefore, first of all, the concrete of the pillars and beams on the lower floor must be placed, and after the hardening of the concrete, the PC floorboard must be installed, which prolongs the construction period and defeats the initial purpose.
さらに、かかる柱、梁のコンクリートを先に打設する場
合には下の床面からの高所作業となり、足場組等が必要
になるため、より、作業が煩雑化、長期化するという問
題を有していた。Furthermore, when such concrete for pillars and beams is to be placed first, it will be work at a high place from the floor below, and scaffolding and the like will be necessary, which further complicates and lengthens the work. Had.
本発明はかかる従来の問題に鑑み、いずれの工法を採用
する場合であっても、構築現場での作業効率を格段に高
めうる、建築物の躯体構築用治具物を提供することを目
的とするものである。In view of such conventional problems, the present invention has an object to provide a jig for constructing a frame of a building, which can significantly improve the work efficiency at a construction site, regardless of which construction method is adopted. To do.
(問題点を解決するための手段) 上記目的を達成するため、本発明に係る建築物の躯体構
築用治具は、柱体の上下端部近傍を保持する少なくとも
一対の柱ガイド部と、前記柱体の上端位置で梁体の端部
を支持する梁台と、上階の床体を支持しうるスラブ台と
を一体に備えることを特徴とし、上階作業床の早期確
保、設置位置の調整作業の簡易化等を図っている。(Means for Solving Problems) In order to achieve the above object, a jig for building a structure of a building according to the present invention includes at least a pair of pillar guide portions that hold the vicinity of upper and lower end portions of the pillar body, and It is characterized by integrally including a beam stand that supports the end of the beam at the upper end position of the pillar body and a slab stand that can support the floor body of the upper floor, and secures the work floor of the upper floor early and sets the installation position. We are trying to simplify the adjustment work.
(実施例) 以下、本発明の好適な実施例を図面により説明する。(Examples) Hereinafter, preferred examples of the present invention will be described with reference to the drawings.
第1図及び第2図は本発明の一実施例を示す概念図であ
り、図中1は本実施例に係る躯体構築用治具である。1 and 2 are conceptual views showing an embodiment of the present invention, in which 1 is a skeleton building jig according to the present embodiment.
該躯体構築用治具1は、一対の柱ガイド部2と、梁台3
と、スラブ台4とからなる。The skeleton building jig 1 includes a pair of column guide portions 2 and a beam base 3
And a slab stand 4.
また、第2図において、5は柱体、6は梁体、7は床体
であり、柱体5及び梁体6は、本実施例では型枠付の先
組鉄筋構造体、即ち、RC構造用に先組配筋のなされた
柱、梁の単位揚重体に地上にてあらかじめ型枠が組付け
られたものとして構成されており、床体7はPC床板とし
て構成されている。Further, in FIG. 2, 5 is a column body, 6 is a beam body, and 7 is a floor body. In this embodiment, the column body 5 and the beam body 6 are pre-assembled rebar structures with formwork, that is, RC. It is configured as a formwork preassembled on the ground to a unit lifting body of columns and beams with pre-assembled reinforcement for structure, and the floor body 7 is configured as a PC floor board.
前記一対の柱ガイド部2は、柱体5の上下端部近傍を保
持しうるように、あらかじめ該主体5の型枠の外形寸法
に対応して4本の部材2aを枠状に組合わせてなり、該一
対の柱ガイド部2が柱体5の高さ寸法に合わせてその上
下端部近傍に位置するように配置してある。The pair of pillar guides 2 are formed by previously combining four members 2a in a frame shape so as to hold the vicinity of the upper and lower ends of the pillar 5 in correspondence with the outer dimensions of the mold of the main body 5. That is, the pair of pillar guide portions 2 are arranged so as to be positioned near the upper and lower end portions of the pillar body 5 in accordance with the height dimension of the pillar body 5.
なお、上の方の柱ガイド部2は本実施例では柱体5を配
置するとその上端部と丁度同一高さになるように設定さ
れている。In the present embodiment, the upper pillar guide portion 2 is set so that when the pillar body 5 is arranged, the pillar guide portion 2 is at the same height as the upper end portion thereof.
よって、構築現場において前記柱体5を上部の柱ガイド
部2の上方から嵌挿していけば、所定の柱設置位置に該
柱体5を仮固定することができる。Therefore, if the pillar body 5 is inserted from above the upper pillar guide portion 2 at the construction site, the pillar body 5 can be temporarily fixed at a predetermined pillar installation position.
前記梁台3は、本実施例では上部の前記柱ガイド部2と
同一水平面上で、該柱ガイド部2と一体に設けられてお
り、梁体6の端部を載置しうるだけの強度を有する杆体
からなり、柱ガイド部2の両側に各々設けられている。In the present embodiment, the beam base 3 is provided integrally with the pillar guide portion 2 on the same horizontal plane as the upper pillar guide portion 2, and is strong enough to mount the end portion of the beam body 6. And is provided on both sides of the column guide portion 2.
前記スラブ台4は、前記床体7を上端部に載置支持しう
るように構成された杆体からなり、本実施例では柱ガイ
ド部2及び梁台3を含む外形が矩形状の上下フレーム
8、8の対応する各隅角部が各々固定された4本のスラ
ブ台4が配設されている。The slab base 4 is composed of a rod configured so that the floor body 7 can be placed and supported on the upper end portion thereof, and in this embodiment, an upper and lower frame 8 having a rectangular outer shape including a column guide portion 2 and a beam base 3. , 8 are provided with four slab bases 4 to which respective corresponding corners are fixed.
なお、該スラブ台4は、本実施例では公知のいわゆる強
力サポートで構成されており、上下端に配設された支持
部4a及び載置部4bは本体4cに螺合されており、ねじ込み
位置を変化させることによりレベル調整が可能となって
いる。In addition, the slab base 4 is configured by a so-called strong support known in the present embodiment, and the support portion 4a and the mounting portion 4b arranged at the upper and lower ends are screwed to the main body 4c, and the screwing position is set. The level can be adjusted by changing.
次に、本実施例に係る躯体構築用治具1を用いて構造体
を構築する手順につき説明する。Next, a procedure for constructing a structure using the skeleton constructing jig 1 according to the present embodiment will be described.
まず、治具1を1層分の柱体5の個数に応じて、構築す
べき層のあらかじめ形成された床体71上に搬送し、各治
具1を各々所定設置位置に正確に位置決めして配設す
る。First, according to the number of pillars 5 for one layer, the jig 1 is transferred onto a preformed floor 71 of a layer to be constructed, and each jig 1 is accurately positioned at a predetermined installation position. It arranges.
しかる後に、あらかじめ地上で形成された型枠付先組鉄
筋構造体としての柱体5をクレーン等で揚重して上部の
柱ガイド部2から嵌挿し、下端が下部の柱ガイド部にも
嵌挿されさらに床体71に当接するまで下降させていく。Then, the pillar 5 as a pre-assembled rebar structure with formwork formed in advance on the ground is lifted by a crane or the like and inserted from the upper pillar guide portion 2, and the lower end is also fitted to the lower pillar guide portion. It is inserted and further lowered until it abuts on the floor 71.
これにより、柱体5は所定の設置位置に正確に仮固定さ
れたことになる。As a result, the pillar 5 is accurately and temporarily fixed at the predetermined installation position.
次に、同じく型枠付先組鉄筋構造体としての梁体6を同
様にして揚重し、各梁体6の端部を大体の位置決めをし
て梁台3上に載置する。Next, similarly, the beam bodies 6 as the pre-assembled rebar structure with formwork are similarly lifted, and the ends of each beam body 6 are roughly positioned and placed on the beam stand 3.
しかして、上部のフレーム8上に作業者が乗って手作業
にて正確な位置決めを行なう。Then, an operator rides on the upper frame 8 to perform accurate positioning by hand.
なお、この際、上部のフレーム8には作業用の台板9を
各隅角部等に取付けておくのが望ましい。At this time, it is desirable that the work base plate 9 be attached to each corner portion or the like of the upper frame 8.
梁体6の位置決めが終われば、次にPC板からなる床体7
を各スラブ台4上に載置して支持せしめる。When the positioning of the beam 6 is completed, the floor 7 made of PC board is next.
Is placed on each slab table 4 and supported.
この際、上部のフレーム8から各スラブ台4の上端まで
の距離Lをあらかじめ梁体6の梁成に等しく設定してお
くものとし、そうすれば梁体6の上端は床体7の下面に
接するだけで、該床体7の自重は受けないことになる。At this time, the distance L from the upper frame 8 to the upper end of each slab base 4 is set in advance to be equal to the beam formation of the beam body 6, so that the upper end of the beam body 6 is on the lower surface of the floor body 7. Only by touching, the floor 7 does not receive its own weight.
しかして、床体7の位置調整を行ない、さらに要すれ
ば、柱体5、梁体6及び床体7相互を位置ずれ等が生じ
ないように適宜手段により仮接合しておけばよい。Then, the position of the floor 7 may be adjusted, and if necessary, the pillar 5, the beam 6, and the floor 7 may be temporarily joined by appropriate means so as not to cause a positional deviation.
かかる構成からなる本実施例においては、躯体構築用治
具1を利用することにより、下階の柱、梁等がコンクリ
ート打設前であっても、床体7を設置すれば、該床体7
を直ちに上階の構築作業の際の作業床として利用し、該
上階の柱、梁等の構築準備に入れるため、RC構造では従
来不可能であった上階作業床の早期確保が可能となり、
作業効率が高まり、工期の大幅な短縮化が達成しうるも
のである。In the present embodiment having such a configuration, by using the skeleton building jig 1, even if the pillars, beams and the like on the lower floor are before the concrete is placed, if the floor 7 is installed, the floor 7
Is immediately used as a work floor for the construction work on the upper floor, and is put into the preparation for building the pillars, beams, etc. on the upper floor, which makes it possible to secure the work floor on the upper floor earlier, which was not possible with the RC structure. ,
The work efficiency can be improved and the construction period can be greatly shortened.
しかして、前記下階の柱体5及び梁体6は、上階の床体
7を作業床として、該床体7上から現場打ちコンクリー
トの打設作業が可能であるため、従来のように下階床体
71上で別途に煩雑な足場組作業を行なう必要が全くなく
なる。Since the pillars 5 and the beams 6 on the lower floor can use the floor 7 on the upper floor as a working floor to perform the work of pouring concrete in-situ from the floor 7, it can be constructed as in the conventional case. Lower floor
There is no need to separately perform complicated scaffolding work on the 71.
また、治具1を複数層分に必要な個数だけあらかじめ用
意しておき、上記下階の柱体5及び梁体6のコンクリー
ト打設作業前に上階にも上記したと同様の方法で柱体
5、梁体6及び床体7を順次配設していき、これを繰返
すことにより、複数層分の仮構築作業を先に進めること
にすることもでき、この場合は柱体5及び梁体6のコン
クリート打設は完全に別個の工程として計画することが
でき、より合理的な施工計画により現場作業をより省力
化することが可能となる。In addition, the jigs 1 are prepared in advance in the required number for a plurality of layers, and before the concrete placing work of the pillars 5 and the beams 6 on the lower floor, the same method as described above is performed on the upper floor. By arranging the body 5, the beam 6 and the floor 7 in sequence and repeating this, it is possible to advance the temporary construction work for a plurality of layers. In this case, the pillar 5 and the beam The concrete pouring of the body 6 can be planned as a completely separate process, and a more rational construction plan makes it possible to save labor on site.
なお、この際、治具1は上階の躯体重量を安全に支持し
うるだけの強度を有するものとすることは言うまでもな
い。In this case, it goes without saying that the jig 1 has a strength sufficient to safely support the weight of the upper body.
また、治具1は分解組立可能な構成とすることにより、
下層部分の不要となった治具1を順次上層へと転用して
いくこともできる。In addition, the jig 1 is configured so that it can be disassembled and assembled,
The jig 1 that does not require the lower layer portion can be diverted to the upper layer one by one.
しかして、本発明は上記実施例の如くRC構造の建築物の
場合に特に顕著な効果を発揮しうるものであるが、これ
に限定されるものではなく、床体7に加え、柱体5、梁
体6もPC部材とした場合にも適用することができ、この
場合には治具1の存在により上部床PC板の荷重がPC梁に
加わることがないため、床PC板を載置後にPC梁の位置調
整をすることも可能となる。The present invention can exert a particularly remarkable effect in the case of a building having an RC structure as in the above embodiment, but the present invention is not limited to this, and in addition to the floor 7 the pillar 5 The beam 6 can also be applied to the case of using a PC member. In this case, since the load of the upper floor PC plate is not applied to the PC beam due to the presence of the jig 1, the floor PC plate is placed. It is also possible to adjust the position of the PC beam later.
また、SRC構造の場合にも本発明が適用しうるのは勿論
であり、この場合も上記RC構造の例に準じた作用効果を
奏しうる。Further, the present invention can be applied to the case of the SRC structure, of course, and in this case also, the operational effects according to the example of the RC structure can be obtained.
なお、上記実施例では、梁体6がすべて同一の梁成の例
を示したが、梁成の異なる大梁、小梁を同時に治具1に
載置しうるようにすることも可能であり、この場合は大
梁と小梁の各々の梁台3のレベルをあらかじめ異なる所
定高さ位置に設定しておけばよい。In addition, in the above-mentioned embodiment, the example in which the beam bodies 6 are all the same beam formation is shown, but it is also possible that large beams and small beams having different beam formations can be simultaneously placed on the jig 1. In this case, the level of each beam stand 3 of the large beam and the small beam may be set to different predetermined height positions in advance.
また、スラブ台4は必ずしも1個の治具1に4本設ける
ものでなくともよく、例えば上部に所定の載置台が固定
された2本のスラブ台4で床板7を支持するようにして
もよく、さらに4本以上設けることもできる。Further, the slab bases 4 do not necessarily have to be provided in one jig 1 and, for example, the floor board 7 may be supported by the two slab bases 4 having a predetermined mounting base fixed to the upper part thereof. Of course, four or more can be provided.
また、上記実施例のように強力サポートを用いる以外に
も他の適宜部材を利用するこができ、レベル調整手段に
ついても同様である。Further, other than the strong support as in the above embodiment, other appropriate members can be used, and the same applies to the level adjusting means.
さらに、床板7は本実施例の如く完全なPC板でなくとも
よく、少なくとも上階の作業床として利用できるもので
あればいい。Further, the floor board 7 does not have to be a complete PC board as in the present embodiment, but may be any one that can be used as at least an upper floor work floor.
よって、本出願人が先に特願昭61−1377736にて開示し
た、例えば第3図及び第4図に示すような半PC床板10、
11、即ち、周辺部に少なくとも1個所以上の現場接合部
12が設けられ、他の周辺部及び中央部13には完成された
所定厚さの床部分が形成されたPC床板を用いてもよい。Therefore, the applicant has previously disclosed in Japanese Patent Application No. 61-1377736, for example, a half-PC floor board 10 as shown in FIGS. 3 and 4.
11, ie, at least one on-site joint in the periphery
It is also possible to use a PC floor board in which 12 is provided, and the other peripheral portion and the central portion 13 have a completed floor portion having a predetermined thickness.
さらに、治具1は上記実施例の如くフレーム8あるいは
スラブ台4のように線状の部材で構成するものに限定さ
れず、他の任意の面状部材等と組合わせたもの等とする
ことができるなど、本発明の要旨を逸脱しない範囲内で
種々の変形例が可能であることは言うまでもない。Further, the jig 1 is not limited to the one constituted by a linear member like the frame 8 or the slab base 4 as in the above-mentioned embodiment, but may be one combined with any other planar member or the like. Needless to say, various modifications are possible without departing from the scope of the present invention.
(発明の効果) 本発明は上述した如く構成されており、本発明に係る躯
体構築用治具を用いることにり、いずれの構造方式の建
築物においても上階作業床の早期確保、設置位置の調整
作業の簡易化等が可能となり、さらに現場作業の合理
化、効率化を図り、安全性を高めることができる極めて
有用なものである。(Effects of the Invention) The present invention is configured as described above, and by using the structure building jig according to the present invention, the upper floor work floor can be secured and installed at an early stage in any structure type building. It is extremely useful because it can simplify the adjustment work, etc., can further rationalize and improve the work efficiency in the field, and can enhance the safety.
第1図は本発明に係る躯体構築用治具の構成を示す概略
斜視図、第2図は該治具にを用いた構築作業例を示す説
明図、第3図及び第4図は各々本発明に係る床体の他の
実施例を示す概略斜視図、第5図は従来例を示す説明図
である。 1…躯体構築用治具、2…柱ガイド、3…梁台、4…ス
ラブ台、5…柱体、6…梁体、7…床体、8…フレー
ム、9…台板、10、11…PC床板。FIG. 1 is a schematic perspective view showing the structure of a skeleton building jig according to the present invention, FIG. 2 is an explanatory view showing an example of construction work using the jig, and FIGS. FIG. 5 is a schematic perspective view showing another embodiment of the floor according to the present invention, and FIG. 5 is an explanatory view showing a conventional example. DESCRIPTION OF SYMBOLS 1 ... Jig for building a frame, 2 ... Pillar guide, 3 ... Beam stand, 4 ... Slab stand, 5 ... Pillar, 6 ... Beam body, 7 ... Floor body, 8 ... Frame, 9 ... Base plate, 10, 11 ... PC floorboard.
Claims (4)
一対の柱ガイド部と、前記柱体の上端位置で梁体の端部
を支持する梁台と、上階の床体を支持しうるスラブ台と
を一体に備えてなることを特徴とする建築物の躯体構築
用治具。1. A pair of pillar guides for holding the vicinity of the upper and lower ends of a pillar, a beam stand for supporting the end of the beam at the upper end of the pillar, and a floor for the upper floor. A jig for constructing a frame of a building, which is integrally provided with an ur slab stand.
キャストコンクリート柱である特許請求の範囲第1項記
載の建築物の躯体構築用治具。2. The jig for constructing a skeleton of a building according to claim 1, wherein the column body is a pre-assembled column form with rebar or a precast concrete column.
キャストコンクリート梁である特許請求の範囲第1項も
しくは第2項記載の建築物の躯体構築用治具。3. The jig for constructing a skeleton of a building according to claim 1, wherein the beam body is a beam form frame with pre-assembled reinforcing bars or a precast concrete beam.
キャストコンクリート床である特許請求の範囲第1項乃
至第3項のいずれかに記載の建築物の躯体構築用治具。4. The jig for constructing a skeleton of a building according to any one of claims 1 to 3, wherein the floor body is a floor formwork with pre-assembled rebar or a precast concrete floor.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP27034886A JPH0745779B2 (en) | 1986-11-13 | 1986-11-13 | Jig for building the skeleton of a building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP27034886A JPH0745779B2 (en) | 1986-11-13 | 1986-11-13 | Jig for building the skeleton of a building |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS63125776A JPS63125776A (en) | 1988-05-28 |
| JPH0745779B2 true JPH0745779B2 (en) | 1995-05-17 |
Family
ID=17485008
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP27034886A Expired - Lifetime JPH0745779B2 (en) | 1986-11-13 | 1986-11-13 | Jig for building the skeleton of a building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0745779B2 (en) |
-
1986
- 1986-11-13 JP JP27034886A patent/JPH0745779B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPS63125776A (en) | 1988-05-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH08144425A (en) | Prefabricated member of mixed structure and construction method of mixed structure | |
| JPH0745779B2 (en) | Jig for building the skeleton of a building | |
| JPH0649982A (en) | Formwork unit and its construction | |
| JP3586121B2 (en) | Mixed structure of reinforced concrete column and steel beam and its construction method | |
| JPS63125743A (en) | Construction of building | |
| JP3358047B2 (en) | Manufacturing method of large slab and construction method of reinforced concrete sloping floor | |
| JPH0681463A (en) | Building method for stair | |
| JP3044113B2 (en) | Building construction method | |
| JPH0642184A (en) | Method of constructing a skeleton using half-PC floorboard | |
| JP3187618B2 (en) | How to assemble beam reinforcement | |
| JPS6195136A (en) | Construction of multistoried building skeletal by precast reinforced concrete unit | |
| JPH031562Y2 (en) | ||
| JPH0437893B2 (en) | ||
| JP2000192664A (en) | Method for construction of building | |
| JP2836406B2 (en) | Construction method of reinforced concrete wall using PC version | |
| JPH02282538A (en) | Construction method of reinforced concrete-made building frame | |
| JPH09111863A (en) | Precast member concurrently serving as column form and construction method of column member using this | |
| JPH0796804B2 (en) | How to build a building | |
| JPS6286270A (en) | Slab construction method | |
| JPS5923159Y2 (en) | Formwork equipment for manufacturing walls and floor slabs of buildings | |
| JPH05125761A (en) | Constructing method of composite structure | |
| JPH07197475A (en) | Structure of foundation | |
| JPH10121573A (en) | Half precast concrete member and method of constructing structure | |
| JPH07216907A (en) | Building foundation construction method and foundation member manufacturing method | |
| JPH0470458B2 (en) |