JPH0762352B2 - Method of making steep slope on embankment slope - Google Patents
Method of making steep slope on embankment slopeInfo
- Publication number
- JPH0762352B2 JPH0762352B2 JP21745989A JP21745989A JPH0762352B2 JP H0762352 B2 JPH0762352 B2 JP H0762352B2 JP 21745989 A JP21745989 A JP 21745989A JP 21745989 A JP21745989 A JP 21745989A JP H0762352 B2 JPH0762352 B2 JP H0762352B2
- Authority
- JP
- Japan
- Prior art keywords
- slope
- embankment
- crushed stone
- steep
- anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000004519 manufacturing process Methods 0.000 title 1
- 239000004575 stone Substances 0.000 claims description 22
- 238000010276 construction Methods 0.000 claims description 16
- 239000000463 material Substances 0.000 claims description 14
- 230000003014 reinforcing effect Effects 0.000 claims description 12
- 238000000034 method Methods 0.000 claims description 6
- 239000002689 soil Substances 0.000 claims description 6
- 230000014759 maintenance of location Effects 0.000 claims 1
- 230000002787 reinforcement Effects 0.000 claims 1
- 238000009412 basement excavation Methods 0.000 description 11
- 239000004567 concrete Substances 0.000 description 8
- 238000003780 insertion Methods 0.000 description 8
- 230000037431 insertion Effects 0.000 description 8
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 8
- 239000011440 grout Substances 0.000 description 7
- 238000010586 diagram Methods 0.000 description 5
- 239000011378 shotcrete Substances 0.000 description 5
- 229910000831 Steel Inorganic materials 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 230000015556 catabolic process Effects 0.000 description 2
- 238000005056 compaction Methods 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000011381 foam concrete Substances 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000005507 spraying Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【発明の詳細な説明】 <産業上の利用分野> 本発明は鉄道や道路等の盛土法面を急勾配化する方法に
関するものである。DETAILED DESCRIPTION OF THE INVENTION <Industrial field of application> The present invention relates to a method for making a steep slope on an embankment slope of a railway, a road or the like.
<従来の技術> 近年、特に都市部においては土地の効率的利用、高度利
用が求められている。<Prior Art> In recent years, efficient use and advanced use of land are required especially in urban areas.
しかし、鉄道や道路等の構造物としては、都市部におい
ても盛土形式のものが多く用いられており、大きな用地
を占めている。However, as structures such as railroads and roads, embankment type structures are often used even in urban areas and occupy large sites.
そこで、盛土の法面を急勾配化し、これにより生じる用
地の有効利用が図られている。Therefore, the slope of the embankment is made steep and effective use of the resulting land is attempted.
従来の急勾配化工法としては、盛土体の法面をより急勾
配に掘削し、掘削後の法面にコンクリートを吹き付け被
覆する方法が用いられている。As a conventional steep slope construction method, a method is used in which the slope of the embankment is excavated at a steeper slope and concrete is sprayed onto the slope after the excavation.
<本発明が解決しようとする問題点> 前記した従来の吹き付けコンクリート工法には、次のよ
うな問題点が存在する。<Problems to be Solved by the Present Invention> The above-described conventional shotcrete construction method has the following problems.
<イ>急勾配化工法においては、鉄道や道路等の営業を
停止した後、再び営業を開始するまでの短時間のうち
に、作業を完了させる必要がある。<B> In the steep slope construction method, it is necessary to complete the work within a short period of time after the business of railways and roads is stopped and before the business is restarted.
しかし、従来の吹き付けコンクリートによる方法は、コ
ンクリートの強度発現に時間がかかり、また、不測の事
故(吹き付け機の故障等)により作業ができなくなる場
合が考えられ、作業時間が多くかかるため、急勾配化工
法に用いる場合には適当でない。However, in the conventional method using sprayed concrete, it takes time to develop the strength of the concrete, and it may be impossible to work due to an unexpected accident (breakdown machine failure, etc.). It is not suitable when used for chemical methods.
<ロ>また、吹き付けコンクリートの場合は、湧水や雨
水等のために地山から浮いてしまう場合があり、確実に
法面を押さえることが困難となる。<B> Further, in the case of sprayed concrete, it may be floated from the ground due to spring water, rain water, etc., and it will be difficult to reliably control the slope.
<本発明の目的> 本発明は上記のような問題点を解決するためになされた
もので、短時間にかつ容易に盛土体の急勾配化作業がで
き、しかも湧水や雨水等の影響を受けることが少ない盛
土法面の急勾配化工法を提供することを目的とする。<Purpose of the present invention> The present invention has been made to solve the above-described problems, and it is possible to easily make a steep slope of an embankment in a short period of time, and to prevent the influence of spring water, rainwater, and the like. It aims to provide a steep slope construction method for the embankment slope that is rarely received.
<本発明の構成> 以下、図面を参照しながら本発明の一実施例について説
明する。<Structure of the Present Invention> An embodiment of the present invention will be described below with reference to the drawings.
<イ>盛土体頭部の締め固め(第1、3図) 先ず第3図に示すように、盛土体の頭部のなるべく法肩
に近い場所に、略水平方向に貫通孔を削孔する。<A> Compaction of the head of the embankment (Figs. 1 and 3) First, as shown in Fig. 3, a through hole is drilled in a position substantially horizontal to the head of the embankment in a substantially horizontal direction. .
そして、この孔内に鉄筋1を挿入して貫通させ、その両
端部を孔外に露出させておく。Then, the reinforcing bar 1 is inserted into the hole and penetrated, and both ends thereof are exposed outside the hole.
この鉄筋1の露出する両端部には、予めネジ部を形成し
ておく。Threaded portions are formed in advance on both exposed ends of the reinforcing bar 1.
一方、盛土体の延長方向に沿って、両側の法面上端部に
腹起し材2を配置する。On the other hand, along the extension direction of the embankment, the uprising members 2 are arranged at the upper ends of the slopes on both sides.
この腹起し材2には、例えば断面がコの字状の溝形鋼等
を使用し、溝部が外側に向くように配置する。For this upholstery member 2, for example, a channel steel having a U-shaped cross section is used, and it is arranged so that the groove portion faces the outside.
また、この腹起し材2の法面との接触面には、鉄筋1の
挿入孔を間隔をおいて複数開設し、この挿入孔に鉄筋1
の露出するネジ部を挿入して配置する。In addition, a plurality of insertion holes for the reinforcing bar 1 are opened at intervals on the contact surface of the uprising member 2 with the slope, and the reinforcing bar 1 is inserted in the insertion holes.
Insert and place the exposed screw part of.
なお、腹起し材2は、手で持てる程度の長さのものを使
用すると作業が行い易い。It should be noted that work can be easily carried out if the uprising member 2 is of a length that can be held by hand.
そして、腹起し材2の挿入孔より貫通する鉄筋1の両端
ネジ部に、ナット等を取り付けて締結する。Then, a nut or the like is attached and fastened to the threaded portions at both ends of the reinforcing bar 1 penetrating through the insertion hole of the derrick member 2.
これによって、腹起し材2が支圧板として作用するた
め、盛土体の頭部を両側の法面より締め固めることがで
きる。As a result, the uprising member 2 acts as a bearing plate, so that the head of the embankment can be compacted from the slopes on both sides.
<ロ>アンカー鉄筋の定着(第5図) 次に第5図に示すように、上記腹起し材2のやや下方の
法面に、盛土体の中心に向けてやや下方に傾斜するよう
に、アンカー孔3を削孔する。<B> Anchoring of anchor rebars (Fig. 5) Next, as shown in Fig. 5, on the slope slightly below the uprising member 2, incline slightly downward toward the center of the embankment. , The anchor hole 3 is drilled.
そして、このアンカー孔3内に、アンカー鉄筋31を孔奥
まで挿入する。Then, the anchor rebar 31 is inserted into the anchor hole 3 as far as the hole.
アンカー鉄筋31には、法面の掘削予定線の孔奥側にパッ
カー32が取り付けてある。A packer 32 is attached to the anchor reinforcing bar 31 on the inner side of the hole on the sloped excavation line.
また、アンカー鉄筋31は、法面の掘削予定線の孔外側が
撤去できるように、ジョイント金具33によって取り外し
可能に連結されている。Further, the anchor rebar 31 is detachably connected by a joint fitting 33 so that the outside of the hole of the planned excavation line on the slope can be removed.
但し、法面掘削後に、アンカー鉄筋31の孔外側の端部
が、法面よりやや突出するように、ジョイント金具33を
法面の掘削予定線より孔外側にやや寄せて取り付けてお
く。However, after excavation of the slope, the joint metal fitting 33 is attached to the hole slightly outside the planned excavation line of the slope so that the end of the anchor bar 31 outside the hole slightly projects from the slope.
また、法面掘削後に、アンカー鉄筋31の法面より突出す
る部分には、予めネジ部を形成しておく。In addition, after excavation of the slope, a screw portion is formed in advance in a portion of the anchor rebar 31 that protrudes from the slope.
そして、注入管等によってアンカー孔3内にグラウト材
34を充填し、グラウト材34の硬化を待って、アンカー鉄
筋31の孔外側の端部を、法面に配置した支圧板等に定着
する。Then, the grout material is put into the anchor hole 3 by an injection pipe or the like.
After filling with 34 and waiting for the grout material 34 to harden, the end of the anchor rebar 31 outside the hole is fixed to a bearing plate or the like arranged on the slope.
<ハ>法面の掘削(第6図) 法面の掘削作業の前に、線路又は道路等を閉鎖する。<C> Excavation on the slope (Fig. 6) Before excavation work on the slope, the track or road is closed.
そして、第6図に示すように、アンカー鉄筋31の周囲の
法面を、所定の角度をもって急勾配に掘削する。Then, as shown in FIG. 6, the slope around the anchor reinforcing bar 31 is steeply excavated at a predetermined angle.
掘削と同時に、ジョイント金具33を取り外し、アンカー
鉄筋31の孔外側部分を撤去する。Simultaneously with the excavation, the joint fitting 33 is removed, and the hole outside portion of the anchor reinforcing bar 31 is removed.
なお、パッカー32が取り付けてあることによって、アン
カー孔3からグラウト材34の流出を防ぐことができる。The packer 32 is attached so that the grout material 34 can be prevented from flowing out from the anchor hole 3.
<ニ>土留板の構造(第4図) 土留板4は、コンクリートまたは鋼材等で形成した板体
である。<D> Structure of earth retaining plate (FIG. 4) The earth retaining plate 4 is a plate body formed of concrete or steel.
コンクリートで形成する場合には、軽量の気泡コンクリ
ートパネルを使用すると作業性が向上する。When formed from concrete, the use of lightweight cellular concrete panels improves workability.
この土留板4には、第4図に示すように、アンカー挿入
孔41が貫通して開設されており、板体の一方の面に、鋼
材等で形成した砕石枠42が取り付けてある。As shown in FIG. 4, an anchor insertion hole 41 is formed through the earth retaining plate 4, and a crushed stone frame 42 made of steel or the like is attached to one surface of the plate body.
そして、この砕石枠42内には、金網等で形成した砕石篭
43が装着できるように構成されている。Then, in the crushed stone frame 42, a crushed stone basket formed of wire mesh or the like is used.
It is configured so that 43 can be attached.
砕石篭43には、土留板4のアンカー挿入孔41と連続する
位置に、アンカー挿入筒44を貫通させて取り付ける。On the crushed stone basket 43, an anchor insertion tube 44 is attached at a position continuous with the anchor insertion hole 41 of the earth retaining plate 4 so as to penetrate therethrough.
<ホ>土留板の設置(第6) 次に、第6図に示すように、掘削後の法面に、砕石枠42
側が法面と接触するように、土留板4を設置する。<E> Installation of retaining plate (sixth) Next, as shown in FIG. 6, a crushed stone frame 42 is formed on the slope after excavation.
The soil retaining plate 4 is installed so that the side contacts the slope.
このとき、砕石篭43は、予め砕石枠42内に装着してお
き、アンカー鉄筋31の露出端部35は、土留板4のアンカ
ー挿入孔41及び、砕石篭43のアンカー挿入筒44内に貫通
させる。At this time, the crushed stone basket 43 is mounted in the crushed stone frame 42 in advance, and the exposed end portion 35 of the anchor rebar 31 penetrates into the anchor insertion hole 41 of the earth retaining plate 4 and the anchor insertion cylinder 44 of the crushed stone basket 43. Let
次に、砕石篭43の上部の金網を開放し、その中に砕石45
を投入し、再び砕石篭43を閉塞する。Next, open the wire mesh on top of the crushed stone basket 43,
Then, the crushed stone basket 43 is closed again.
このように砕石45を、土留板4と法面との間に配置する
ことによって、盛土体内の湧水や雨水の排水を良好に行
うことができる。By disposing the crushed stones 45 between the retaining plate 4 and the slope in this way, drainage of spring water and rainwater in the embankment can be favorably performed.
そして、支圧板、ナット等を露出端部35に取り付け、土
留板4に締結する。Then, a bearing plate, a nut and the like are attached to the exposed end portion 35 and fastened to the earth retaining plate 4.
以上のようにして一段目を施工した後、同じ要領で二段
目、三段目というように、下方に施工を進めていく。After constructing the first stage as described above, the construction is proceeded downward in the same manner as the second stage and the third stage.
なお、盛土体の上下方向に隣接する土留板4間には間隔
をあけておき、第2図に示すように、この間隙部には、
砕石45を投入した小型の間詰篭5を法面側に配置し、そ
のあと間詰コンクリート51を塗り付けて間隙部を埋める
とよい。In addition, a space is provided between the soil retaining plates 4 that are adjacent to each other in the vertical direction of the embankment, and as shown in FIG.
A small padding basket 5 containing crushed stones 45 may be arranged on the slope side, and then padding concrete 51 may be applied to fill the gap.
最後まで施工が終了した後、線路又は道路等閉鎖を解除
する。After the construction is completed to the end, the track or road will be closed.
<その他の実施例1> その他の実施例として、第7、8図に示すように、アン
カー鉄筋31の代わりに引張材6を用いて、プレストレス
を導入する場合も考えられる。<Other Example 1> As another example, as shown in FIGS. 7 and 8, it is possible to use a tensile member 6 instead of the anchor reinforcing bar 31 to introduce prestress.
この場合は、先ず初めに法面を所定の角度で急勾配に掘
削し、法面に削孔した孔内に引張材6を挿入して、引張
材の孔奥部を急結材61等を充填して定着する。In this case, first, the slope is excavated at a predetermined angle with a steep slope, and the tension member 6 is inserted into the hole drilled in the slope to insert the quick-setting member 61 or the like in the deep portion of the hole of the tension member. Fill and fix.
このとき、アンカー孔の法面付近には、塩ビパイプ62等
の管体を取り付けておき、グラウト材注入時に、砕石篭
43内にグラウト材が流出しないようにする。At this time, a pipe body such as a PVC pipe 62 is attached near the slope of the anchor hole, and the crushed stone basket is used when pouring the grout material.
Make sure that the grout material does not flow out into the 43.
次に、引張材6の露出端部及び塩ビパイプ62を貫通させ
て、法面に土留板4を取り付け、引張材6を緊張して、
引張材6の露出端部を土留板4に定着させる。Next, the exposed end of the tension member 6 and the PVC pipe 62 are penetrated, the earth retaining plate 4 is attached to the slope, and the tension member 6 is tensioned.
The exposed end portion of the tension member 6 is fixed to the soil retaining plate 4.
最後に、アンカー孔内にグラウト材63充填して取り付け
作業を終了する。Finally, the grout material 63 is filled in the anchor hole, and the attachment work is completed.
<その他の実施例2> また、上記実施例では、いずれも盛土体の頭部に、鉄筋
1を略水平方向に貫通させて設置した場合であるが、第
9図に示すように、盛土の片側が切土面等の場合は、ア
ンカー鉄筋7を用いて盛土体の頭部の締め固めを行うこ
とが考えられる。<Other Example 2> In each of the above Examples, the reinforcing bar 1 was installed in the head of the embankment in a substantially horizontal direction, but as shown in FIG. When one side has a cut surface or the like, it is conceivable to use the anchor rebar 7 to compact the head of the embankment.
この場合は、盛土体の頭部に、法面から略水平方向にア
ンカー孔を削孔し、このアンカー孔内にアンカー鉄筋7
を挿入し、グラウト材71によって定着する方法である。In this case, an anchor hole is drilled in the head of the embankment in a substantially horizontal direction from the slope, and the anchor rebar 7 is inserted in the anchor hole.
Is inserted and fixed by the grout material 71.
<本発明の効果> 本発明は以上説明したようになるので、次のような効果
を期待することができる。<Effects of the Present Invention> Since the present invention has been described above, the following effects can be expected.
<イ>急勾配化工法においては、鉄道や道路等の営業を
停止した後、再び営業を開始するまでの短時間のうち
に、作業を完了させる必要がある。<B> In the steep slope construction method, it is necessary to complete the work within a short period of time after the business of railways and roads is stopped and before the business is restarted.
しかし、従来の吹き付けコンクリートによる方法は、コ
ンクリートの強度発現が充分でなければアンカーの締付
ができず、時間がかかる。However, in the conventional method using sprayed concrete, unless the strength of the concrete is sufficiently developed, the anchor cannot be tightened and it takes time.
また、不測の事故(吹き付け機の故障等)により作業が
できなくなる場合が考えられ、作業時間が多くかかるた
め、急勾配化工法に用いる場合には適当でない。In addition, there is a possibility that the work cannot be performed due to an unexpected accident (broken machine failure, etc.), and it takes a lot of work time, so it is not suitable for use in the steep slope construction method.
それに対して本発明は、コンクリートまたは鋼材等によ
り形成した既製の土留板によって、法面を押さえること
ができる。On the other hand, in the present invention, the slope can be suppressed by the ready-made earth retaining plate formed of concrete or steel.
従って、従来のようにコンクリートの強度発現を待つ必
要がなく、短時間に施工を完了させることができ、盛土
体の急勾配化工法に適した方法であると言える。Therefore, it can be said that the method is suitable for the steep slope construction method of the embankment, because it is possible to complete the construction in a short time without having to wait for the strength of the concrete to develop as in the conventional case.
また、吹き付け機等の装置を必要としないため、不測の
事故(吹き付け機の故障等)により作業が中断すること
がない。Further, since no device such as a spraying machine is required, the work is not interrupted by an unexpected accident (breakdown of the spraying machine, etc.).
<ロ>従来の吹き付けコンクリートの場合は、湧水や雨
水等のために地山から浮いてしまう場合があり、確実に
法面を押さえることが困難となる。<B> In the case of conventional sprayed concrete, it may be floated from the ground due to spring water, rain water, etc., and it is difficult to reliably hold the slope.
それに対して本発明は、土留板と法面との間に砕石を配
置することによって、湧水や雨水等を良好に排水するこ
とができる。On the other hand, the present invention can satisfactorily drain spring water, rainwater, etc. by disposing crushed stones between the soil retaining plate and the slope.
そのため、湧水や雨水等の影響を受けることがほとんど
なく、確実に法面を押さえることができる。Therefore, the slope can be surely suppressed without being affected by spring water, rainwater, or the like.
<ハ>土留板に軽量の発泡コンクリートパネルを使用す
れば、取り付け作業が容易かつ短時間に行うことがで
き、施工性が向上する。<C> If a lightweight foam concrete panel is used for the soil retaining plate, the installation work can be performed easily and in a short time, and the workability is improved.
<ニ>本発明は、施工が短時間に行えるため、特に、営
業路線の停止時間内の作業に適している。<D> The present invention is particularly suitable for the work during the downtime of the commercial line because the construction can be performed in a short time.
<ホ>盛土体の頭部を、法面を傷めることなく、鉄筋等
によって早期に締め固めることにより、法面の掘削時に
発生する側方への盛土体の変形を抑えることができる。<E> The head of the embankment is compacted early by reinforcing bars without damaging the slope, so that lateral deformation of the embankment that occurs during excavation of the slope can be suppressed.
そのため、盛土体上面の路盤や路床の沈下、水平変位
を、極力少なくすることができ、安全性が高くなる。Therefore, it is possible to minimize the subsidence and the horizontal displacement of the roadbed or the roadbed on the top surface of the embankment, which improves safety.
<ヘ>盛土体の頭部の締め固め作業は、盛土頭部に鉄筋
等を略水平方向に設置するだけでよいため、すべての作
業を側方から行うことができる。<F> Since the work of compacting the head of the embankment body only needs to be installed in the head of the embankment in a substantially horizontal direction, all the work can be performed from the side.
そのため、路線の閉鎖をする必要がなく、徐行運転程度
で作業を行うことができる。Therefore, it is not necessary to close the route, and the work can be performed at a slow speed.
従って、路線閉鎖後の作業に時間的余裕ができる。Therefore, it is possible to spare time for the work after the line is closed.
【図面の簡単な説明】 第1図:本発明の一実施例の説明図 第2図:土留板の設置状態の側面図 第3図:盛土体の頭部の締め固め説明図 第4図:土留板の説明図 第5、6図:施工方法の説明図 第7、8図:その他の実施例1の説明図 第9図:その他の実施例2の説明図BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1: Explanatory diagram of an embodiment of the present invention FIG. 2: Side view of installed state of earth retaining plate FIG. 3: Explanatory diagram of compaction of head of embankment FIG. Fig. 5 and 6: Explanatory diagram of construction method Fig. 7 and 8: Explanatory diagram of other example 1 Fig. 9: Explanatory diagram of other example 2
───────────────────────────────────────────────────── フロントページの続き (72)発明者 大高 陽一 神奈川県横浜市緑区長津田町4199―1 ラ イオンズ第3―502 (72)発明者 西岡 哲 神奈川県座間市入谷4―3011―6 座間ハ イツ2―1411 (72)発明者 中村 和之 神奈川県川崎市麻生区細山3―16―7 (72)発明者 田村 幸彦 神奈川県横浜市緑区桂台2―22―15 プラ シード桂106 (72)発明者 笹木 敏信 神奈川県鎌倉市岡本1241―4 鎌倉ロジュ マンC―904 (72)発明者 越智 健三 神奈川県横浜市緑区霧が丘3―24―1― 106 (72)発明者 鄭 光司 神奈川県川崎市宮前区土橋2―15―2― 506 (72)発明者 壺内 達也 神奈川県川崎市宮前区東有馬1―2―2 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Yoichi Otaka Yoichi Otaka 4199-1, Nagatsuta-cho, Midori-ku, Yokohama-shi, Kanagawa Rionz 3-502 (72) Inventor Satoshi Nishioka 4-3011-6 Iriya, Zama-shi, Kanagawa Zama Heights 2-1411 (72) Inventor Kazuyuki Nakamura 3-16-7 Hosoyama, Aso-ku, Kawasaki City, Kanagawa Prefecture (16) (72) Inventor Yukihiko Tamura 2-22-15, Katsuradai, Midori-ku, Yokohama City, Kanagawa Prefecture 106 (72) ) Inventor Toshinobu Sasaki 1241-4 Okamoto, Kamakura City, Kanagawa Prefecture Rojuman C-904, Kamakura (72) Inventor Kenzo Ochi 3-24-1-106 Kiritsuga, Midori-ku, Yokohama City, Kanagawa Prefecture (72) Inventor, Koji Zheng, Kawasaki, Kanagawa Prefecture 2-15-2-2 Tsuchihashi, Miyamae-ku, Ichi, 506 (72) Inventor Tatsuya Tsubouchi 1-2-2 Higashiarima, Miyamae-ku, Kawasaki-shi, Kanagawa
Claims (3)
において、 盛土体の頭部に略水平方向に鉄筋を貫通させ、この鉄筋
の両端部を、盛土体の延長方向に沿って法面の上端部に
配置した腹起し材に定着し、 この腹起し材の下方の法面に、盛土体の中心に向けて下
方にやや傾斜するようアンカー鉄筋を定着し、 次にこれらのアンカー鉄筋の周囲の法面をより急勾配に
掘削し、 砕石篭を取り付けた土留板にアンカー鉄筋の露出端部を
貫通させて、砕石篭が法面側に位置するよう土留板を法
面に設置し、 砕石篭内に砕石を投入した後、アンカー鉄筋の露出端部
を土留板に定着させたことを特徴とする、 盛土法面の急勾配化工法。1. A method of excavating a slope of a fill body to make it steep, in which a rebar is pierced through a head of the fill body in a substantially horizontal direction, and both ends of the rebar are along an extension direction of the fill body. Anchored to the upholstery material placed at the upper end of the slope, and anchored to the slope below the upholstery material so as to incline slightly toward the center of the embankment, and then The slope around these anchor rebars is excavated more steeply, the exposed end of the anchor reinforcement is penetrated through the retaining plate with the crushed stone basket, and the retaining plate is cut so that the crushed stone basket is located on the slope side. A steep slope construction method for the embankment slope, which is characterized by placing the crushed stone in a crushed stone basket and fixing the exposed end of the anchor rebar to the retaining plate.
において、 盛土体の頭部に水平方向に鉄筋を貫通させ、この鉄筋の
両端部を、盛土体の延長方向に沿って法面の上端部に配
置した腹起し材に定着し、 次にこの腹起し材の下方の法面をより急勾配に掘削し、 この急勾配に掘削した法面に、盛土体の中心に向けて下
方にやや傾斜するよう削孔し、 この孔内に引張材を挿入して、引張材の孔奥部を定着
し、 次に砕石篭を取り付けた土留板にアンカー鉄筋の露出端
部を貫通させて、砕石篭が法面側に位置するよう土留板
を法面に設置し、 砕石篭内に砕石を投入した後に、引張材を緊張し、引張
材の露出端部を土留板に定着させたことを特徴とする、 盛土法面の急勾配化工法。2. A method of excavating a slope of a fill body to make it steep, in which a rebar is pierced horizontally in the head of the fill body, and both ends of the rebar are provided along the extension direction of the fill body. It is settled on the upholstery material placed at the upper end of the slope, then the slope below the upholstery is excavated at a steeper slope, and the slope of the steep slope is centered on the embankment. Hole so that it inclines slightly downward toward the hole, insert the tension material into this hole, fix the inner part of the hole of the tension material, and then attach the crushed stone basket to the earth retaining plate and the exposed end of the anchor rebar. The earth retaining plate on the slope so that the crushed stone basket is located on the slope side.After the crushed stone is put into the crushed stone basket, the tension material is tensioned and the exposed end of the tension material is attached to the soil retention plate. A steep slope construction method for the embankment slope, which is characterized by being fixed.
土法面の急勾配化工法において、 前記盛土体の頭部に略水平方向に貫通させた鉄筋の代わ
りに、 盛土体の頭部に略水平方向にアンカー体を定着した盛土
法面の急勾配化工法。3. The steep slope construction method for the embankment slope according to claim 1, wherein the head of the embankment is replaced by a reinforcing bar which is penetrated in a substantially horizontal direction. A steep slope construction method for the embankment slope where anchors are fixed to the head in a substantially horizontal direction.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP21745989A JPH0762352B2 (en) | 1989-08-25 | 1989-08-25 | Method of making steep slope on embankment slope |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP21745989A JPH0762352B2 (en) | 1989-08-25 | 1989-08-25 | Method of making steep slope on embankment slope |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH0384117A JPH0384117A (en) | 1991-04-09 |
| JPH0762352B2 true JPH0762352B2 (en) | 1995-07-05 |
Family
ID=16704563
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP21745989A Expired - Fee Related JPH0762352B2 (en) | 1989-08-25 | 1989-08-25 | Method of making steep slope on embankment slope |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0762352B2 (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4930962B2 (en) * | 2005-03-28 | 2012-05-16 | パナソニック株式会社 | Coated molded body manufacturing equipment |
| JP4725853B2 (en) * | 2006-06-16 | 2011-07-13 | 新東工業株式会社 | Parallel adjustment mechanism, pressure molding apparatus using the parallel adjustment mechanism, and parallel adjustment method of the pressure molding apparatus |
| CN108486976B (en) * | 2018-04-30 | 2023-06-27 | 安徽省公路桥梁工程有限公司 | Roadbed structure at mountain highway filling and digging junction and construction method thereof |
| CN109113080B (en) * | 2018-09-12 | 2020-05-22 | 北京工业大学 | Rock mass high cut slope anchor pier net cage coupling ecological slope protection method |
-
1989
- 1989-08-25 JP JP21745989A patent/JPH0762352B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0384117A (en) | 1991-04-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US7530765B2 (en) | Structure of intermediate wall of three arch excavated tunnel and method for constructing the same | |
| Fookes et al. | Stabilization and control of local rock falls and degrading rock slopes | |
| US4964750A (en) | Traffic barrier and method of construction | |
| US5131786A (en) | Traffic barrier and method of construction | |
| CN108678000A (en) | A kind of U-shaped retaining structure of roadbed Xia Chuan highways and its construction method | |
| KR102056345B1 (en) | Slope face adjusting constructor of embanking roadbed for railway track, and construction method for the same | |
| KR20210078779A (en) | Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same | |
| KR101283672B1 (en) | Non open cut method using the lifting device | |
| KR100362615B1 (en) | A Repairing Method of Underground Voids of Approach Slab in Abutment Constructure | |
| JPH0762352B2 (en) | Method of making steep slope on embankment slope | |
| JP2653731B2 (en) | Embankment slope steepening method | |
| KR100509707B1 (en) | None open cut tunnelling of arch type with hume pipe and con'c rib | |
| JPH0762350B2 (en) | Method of making steep slope on embankment slope | |
| JPH0762351B2 (en) | Method of making steep slope on embankment slope | |
| JPH0762349B2 (en) | Method of making steep slope on embankment slope | |
| KR100493516B1 (en) | Micro pile and assembly foundation reinforcement structure member and its method for pier | |
| CN111691255B (en) | Construction method for municipal road along river and enclosure used by construction method | |
| CN112663431A (en) | Concrete pavement fracture subsidence section treatment structure and construction method | |
| JPH03279501A (en) | Widening of road | |
| KR200331521Y1 (en) | None open cut tunnelling of arch type with with hume pipe and con'c rib | |
| JPH0477764B2 (en) | ||
| JP2612600B2 (en) | How to repair the median strip | |
| JP3881342B2 (en) | Bubble mortar embankment structure | |
| CN223434358U (en) | A waterproof structure for underground tunneling | |
| JP3105706B2 (en) | Construction method of piled raft foundation using existing foundation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 13 Free format text: PAYMENT UNTIL: 20080705 |
|
| FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 14 Free format text: PAYMENT UNTIL: 20090705 |
|
| LAPS | Cancellation because of no payment of annual fees |