JPH0776884B2 - Automatic operation management method for process plant - Google Patents
Automatic operation management method for process plantInfo
- Publication number
- JPH0776884B2 JPH0776884B2 JP63094892A JP9489288A JPH0776884B2 JP H0776884 B2 JPH0776884 B2 JP H0776884B2 JP 63094892 A JP63094892 A JP 63094892A JP 9489288 A JP9489288 A JP 9489288A JP H0776884 B2 JPH0776884 B2 JP H0776884B2
- Authority
- JP
- Japan
- Prior art keywords
- plant
- process plant
- state
- state quantity
- output
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
Landscapes
- Testing And Monitoring For Control Systems (AREA)
Description
【発明の詳細な説明】 [発明の目的] (産業上の利用分野) 本発明は、プロセスプラントの自動運転管理方法に関す
る。DETAILED DESCRIPTION OF THE INVENTION [Object of the Invention] (Field of Industrial Application) The present invention relates to an automatic operation management method for a process plant.
(従来の技術) プロセスプラントの自動化運転は、プラントを構成する
機器レベルでは進んでおり、これらの機器をシーケンシ
ャルに起動して、人間の介在が全く不要な状態でプラン
トを運転可能にしたものもすでに存在している。しかし
ながら、このような全自動プロセスプラントでは、予め
想定した通りにプラントが作動する場合は問題ないが、
一部の機器が予定通りに性能発揮しなかったり、故障し
た場合には、プラントの自動運転が不可能になったり、
プラントが暴走する危険性がある。(Prior Art) Automated operation of process plants is advanced at the level of equipment that constitutes the plant, and some equipment can be operated sequentially without human intervention to start the equipment. It already exists. However, in such a fully automatic process plant, there is no problem if the plant operates as expected in advance,
If some equipment does not perform as planned, or if it fails, automatic operation of the plant becomes impossible,
There is a risk of the plant going out of control.
このように機器をシーケンシャルに起動すると、プラン
ト状態と独立に機器が起動されて不都合が生じる場合が
多いため、機器の起動の条件にプラントの状態を考慮し
たルールベースのシステムの導入が考えられるが、この
システムにおいても、このルールを適用する運転状態を
限定しないと、設計時に考慮していないプラント状態で
使用した場合の動作は保証できないので、本質的な問題
解決とはならない。If the equipment is started up sequentially in this way, it often happens that the equipment is started independently of the plant status, which may cause inconvenience.Therefore, it is possible to introduce a rule-based system that considers the plant status as the equipment start-up condition. Even in this system, unless the operating conditions to which this rule is applied are limited, the operation when used in a plant condition that is not taken into consideration at the time of design cannot be guaranteed, and therefore it is not an essential problem solving.
(発明が解決しようとする課題) 本来、プロセスプラントを構成する機器の起動の順序
は、その機器が持つ機能がプロセスプラント全体にとっ
てどのような意味を持つのか、何のためにあるのかとい
った本質的な問題を理解した上で定められるものであ
る。しかしながら、シーケンス制御はそれをただ単に結
果としての起動順序を取出したものにすぎないので、標
準的な運転には適用できても、何らかのトラブルが発生
した場合には上述したような問題が生じる。(Problems to be Solved by the Invention) Originally, the starting sequence of the equipment that constitutes a process plant is essentially what the function of the equipment means to the entire process plant and what it is for. It is decided after understanding various problems. However, since the sequence control is merely one in which the resulting starting sequence is taken out, it can be applied to standard operation, but if some trouble occurs, the above-mentioned problems occur.
本発明はかかる点に対処してなされたもので、人間が機
器の起動を制御する場合、プラントが予定の状態から大
きくずれた時、機器の起動順序を定めた際に基礎とした
原理原則に戻って操作順序を定め直すように、自動制御
においてもプロセスプラントを運転するにあたって考慮
すべき原理原則にしたがって操作手順を定めるようにす
ることにより、どのような状態においてもプラントを適
切に運用することができる自動運転管理方法を提供する
ことを目的とする。The present invention has been made in consideration of such a point, and in the case where a human controls the start-up of equipment, when the plant largely deviates from the planned state, the principle principle based on which the start-up order of the equipment is determined. Proper operation of the plant in any state by determining the operation procedure according to the principles and principles that should be taken into consideration when operating the process plant even in automatic control, such as returning to redetermining the operation sequence. The purpose is to provide an automatic operation management method that can
[発明の構成] (課題を解決するための手段) 本発明の自動運転管理方法は、プロセスプラントの最終
目標に対し、プロセスプラントの運転状態を代表する主
要な状態量と、プロセスプラントの安全上必ず満たすべ
き運転条件として評価される安全性評価と、主要な状態
量および安全性評価の各々の確保に必要なもしくは各々
に依存する、機器の作動による発現する機能との三者の
関係を予め明らかにするとともに、主要な状態量の相互
の関係から変更すべき状態量を規定した運転方策を予め
定義し、最終目標に対する運転操作の手順を、安全性評
価を満たす機能を確保し、ついでプロセスプラントの運
転状態に応じて選定される運転方策にしたがって所定の
状態量を変更するよう、前記三者の関係に基づいて状態
量ごとに運転目標を設定する形で導出することを特徴と
する。[Structure of the Invention] (Means for Solving the Problems) The automatic operation management method of the present invention provides a main state quantity that represents the operating state of the process plant with respect to the final goal of the process plant and safety of the process plant. The three-way relationship between the safety evaluation, which is always evaluated as the operating condition to be satisfied, and the function that is expressed by the operation of the equipment, which is necessary or dependent on each of the main state quantities and the safety evaluation, is pre-established. In addition to clarifying, the driving policy that defines the state variables to be changed from the mutual relation of the main state variables is defined in advance, the procedure of the driving operation to the final goal is secured, and the function to satisfy the safety evaluation is secured. Set an operation target for each state quantity based on the relationship of the three parties so as to change the predetermined state quantity according to the operation policy selected according to the operating state of the plant Characterized in that it derived in that form.
(作用) 本発明のプロセスプラントの自動運転管理方法において
は、まず安全性評価の実施により、所定の機能が発揮さ
れるように運転目標が設定され、この運転目標にしたが
って安全確保のための機器が自動起動される。ついで、
状態量を確保するための機能が状態量に対して十分でな
い場合は、対応する状態量を制限する運転制限目標が設
定され、所定の機能が発揮されるように運転目標が設定
されて、必要な機器が自動起動される。(Operation) In the automatic operation management method for a process plant of the present invention, first, an operation target is set by performing safety evaluation so that a predetermined function is exhibited, and a device for ensuring safety according to this operation target. Is automatically started. Then,
When the function to secure the state quantity is not sufficient for the state quantity, the operation limit target that limits the corresponding state quantity is set, and the operation target is set so that the predetermined function is exerted, and it is necessary. Devices are automatically started.
安全性評価を満たす機能および状態量を保持する機能が
確認されると、プロセスプラントの起動あるいは停止と
いう目標にしたがって変更すべき状態量が選定され、状
態量ごとに状態量の増加、減少のための操作手順が順序
をもつ運転目標の集り、あるいは順序を考慮する必要の
ない運転目標の集りの形で作成されたデータに基づいて
運転目標が設定される。When the function that satisfies the safety evaluation and the function that holds the state quantity are confirmed, the state quantity to be changed is selected according to the goal of starting or stopping the process plant, and the state quantity increases or decreases for each state quantity. The operation target is set based on the data created in the form of a set of operating targets whose order is, or a set of operating targets in which the order does not need to be considered.
これらの運転目標の設定によって自動運転が遂行される
が、プラントにおいて何らかの異常事態が発生した場合
には、状態量を維持する機能の一部が要求を満たさなく
なり、これにより対応する状態量に対して運転制限目標
が設定され、先に設定された運転目標はこの運転制限目
標によって抑制される。Although automatic operation is performed by setting these operation targets, if some abnormal situation occurs in the plant, some of the functions that maintain the state quantity do not satisfy the demand, and as a result, The operation limit target is set by the above, and the previously set operation target is suppressed by this operation limit target.
このように本発明の自動運転管理方法では、プラントに
おける状態量と機能の関係に基づいて、プラントがどの
ような運転状態にあっても適切な操作手順を導出するこ
とができるので、異常事態にも対処することができるプ
ロセスプラントの全自動運転が可能となる。Thus, in the automatic operation management method of the present invention, based on the relationship between the state quantity and the function in the plant, it is possible to derive an appropriate operating procedure regardless of the operating state of the plant, so in an abnormal situation It becomes possible to operate the process plant fully automatically.
(実施例) 以下、図面に基づき本発明の実施例として沸騰水型原子
力発電プラントの起動を自動運転する方法について詳細
に説明する。(Embodiment) Hereinafter, a method for automatically starting a boiling water nuclear power plant as an embodiment of the present invention will be described in detail with reference to the drawings.
まず、操作手順を導出するにあたって必要な、沸騰水型
原子力発電プラントの起動時の状態量と機能と安全性評
価の関係を第1図に示す。状態量は発電プラントを起動
する上で重要なプラントパラメータで、ここでは出力レ
ベル1、タービン復水器真空度2、炉圧3が選ばれる。
安全性評価は発電プラントの運転状態を安全上の観点か
ら評価したもので、外部放出放射能4、緊急時炉心冷却
の余裕5および炉水中の溶存酸素の濃度などを考慮した
炉水状態6が評価の対象となる。そして、これらの安全
性評価はそれぞれ排ガス処理能力7、非常時冷却能力
8、炉水浄化能力9といった機能に依存する。一方、機
能は機器を運転することにより発現されるもので、例え
ば給水ポンプを起動することで給水能力という機能が発
現されることになる。状態量と機能の関係で、点線で結
ばれているものは、状態量を維持するためにはその機能
が発揮されていなければならないことを示しており、実
線で結ばれている場合は、実現すべき機能が状態量に依
存していることを示している。すなわち、出力レベル1
を維持するために必要な機能としては圧力制御能力10、
運転モードスイッチ管理能力11、出力計測能力12、給水
能力13があり、復水器真空度2を維持するために必要な
機能としてはシール能力14および排気能力15があり、炉
圧3を維持するために必要な機能としては減圧阻止能力
16がある。それに対し、発電能力17は出力レベル1およ
び復水器真空度2に依存するのでそれぞれと実線で結ば
れ、前述の排ガス処理能力7および非常時冷却能力8も
炉圧3に依存するので実線で結ばれる。なお、それぞれ
の安全性評価が出力レベル1と実線で結ばれているの
は、出力レベル1が低い状態では、安全処置機能が十分
働いていなくても問題にならず、安全性評価は満足され
るためである。First, FIG. 1 shows the relationship between the state quantity and function at the time of starting the boiling water nuclear power plant, which is necessary for deriving the operating procedure, and the safety evaluation. The state quantity is an important plant parameter for starting the power generation plant, and here, the output level 1, the turbine condenser vacuum degree 2, and the furnace pressure 3 are selected.
The safety evaluation is an evaluation of the operating condition of the power plant from a safety point of view. The external emission radioactivity 4, the margin 5 for emergency core cooling, and the reactor water condition 6 considering the concentration of dissolved oxygen in the reactor water are Subject to evaluation. The safety evaluations depend on the exhaust gas treatment capacity 7, the emergency cooling capacity 8, and the reactor water purification capacity 9, respectively. On the other hand, the function is expressed by operating the device, and for example, the function of water supply capacity is expressed by activating the water supply pump. In the relationship between the state quantity and the function, what is connected by the dotted line indicates that the function must be exerted in order to maintain the state quantity, and if it is connected by the solid line, it is realized. It shows that the function to be performed depends on the state quantity. That is, output level 1
The pressure control ability is 10, which is necessary to maintain
There are operation mode switch management capacity 11, output measurement capacity 12, and water supply capacity 13. Sealing capacity 14 and exhaust capacity 15 are required to maintain condenser vacuum level 2, and reactor pressure 3 is maintained. Decompression prevention capability is a necessary function
There are 16. On the other hand, since the power generation capacity 17 depends on the output level 1 and the condenser vacuum degree 2, it is connected with each other by a solid line, and the exhaust gas treatment capacity 7 and the emergency cooling capacity 8 also depend on the reactor pressure 3 so that the solid line shows. Tied together. Note that each safety evaluation is connected to the output level 1 by a solid line. When the output level 1 is low, it does not matter even if the safety measure function is not working sufficiently, and the safety evaluation is satisfied. This is because
以上、第1図は発電プラントの状態量を保つために必要
な三者の関係を示しているが、発電プラントを目標とす
る運転状態に移行させようとする場合には、状態量の目
標量と比較して変更すべき状態量が選定される。第2図
ないし第5図は発電プラントの起動という最終目標に対
し、復水器真空度、炉圧、出力レベルの3個の状態量の
相互の関係から、変更すべき状態量を決定するプラント
の運転方策を示すものである。これらの図は、3つの状
態量を座標軸とする3次元空間上で定義されているもの
を出力レベル一定の4個の平面で切ったもので、それぞ
れの図における出力レベルは順に中性子源領域、中間領
域、定格出力の10%程度、定格出力の15%以上である。
各図とも真空度および炉圧の大きさを小程度、中程度、
目標達成の3段階に分けて、それぞれの状態量によって
選択される運転方策を表示した。ここで選択される運転
方策としては次の6つがある。As described above, FIG. 1 shows the relationship among the three parties necessary to maintain the state quantity of the power plant. However, when attempting to shift the power plant to the target operating state, the target quantity of the state quantity is set. The state quantity to be changed is selected in comparison with. Figures 2 to 5 show the plant that determines the state quantity to be changed from the mutual relationship among the three state quantities of condenser vacuum, reactor pressure, and power level, with respect to the final goal of starting the power plant. It shows the driving strategy. These figures are those defined in a three-dimensional space with three state quantities as coordinate axes, cut by four planes with a constant output level. The output levels in each figure are the neutron source region, Intermediate range, about 10% of rated output, 15% or more of rated output.
In each figure, the degree of vacuum and furnace pressure are small, medium,
The driving strategy selected according to each state quantity was displayed in three stages of achieving the target. There are the following six driving strategies selected here.
出力上昇、炉水温度上昇、真空度上昇、 炉圧上昇、出力低下、スクラム 通常の運転では前半の3個の方策が採られ、後半3個の
方策は何らかの不具合が生じている場合に用いられる。
例えば、通常出力上昇によって炉圧は上昇するものであ
るが、出力がある程度あるにもかかわらず炉圧が上昇し
ない場合に炉圧上昇の方策が採られる。この方策は、炉
圧の上昇を妨げるものがあるか否かを調べ、ない場合は
出力を上昇させるものである。また、出力低下の方策
は、出力レベルが比較的高くなっているにもかかわらず
復水器真空度あるいは炉圧が十分高くならず、発生する
エネルギーを電気出力に変換することができない場合に
採用される。Power rise, Reactor water temperature rise, Vacuum degree rise, Reactor pressure rise, Power fall, Scrum In normal operation, the first three measures are taken, and the latter three measures are used when something goes wrong. .
For example, although the reactor pressure normally rises due to the increase in the output, when the reactor pressure does not increase despite the output is to some extent, a measure for increasing the reactor pressure is adopted. This measure investigates whether or not there is a hindrance to the rise in the furnace pressure, and if not, increases the power output. Also, the measure to reduce the output is adopted when the condenser vacuum level or furnace pressure is not sufficiently high even though the output level is relatively high, and the generated energy cannot be converted to electric output. To be done.
運転方策は変更すべき状態量を決定するものであるが、
状態量を変更するための操作手順は第1図に示した状態
量と機能と安全性評価の三者の関係に基づいて、状態量
ごとに順序をもった運転目標の形で導出され表される。
例えば、出力上昇の操作手順は次表に示すような表現で
記述することができる。The driving strategy determines the state quantity to be changed,
The operating procedure for changing the state quantity is derived and expressed in the form of an operational goal in order for each state quantity, based on the relationship among the state quantity, the function, and the safety evaluation shown in FIG. It
For example, the operating procedure for increasing the output can be described by the expressions shown in the following table.
表に示したデータは、出力上昇のための制御棒操作ある
いは再循環操作を司る上位制御系に出力上昇の操作目標
を設定するものである。個々の記述について説明する
と、(22−1)から(24−1)は出力上昇のための反応
度操作を行わない条件を示している。(22−1)はドラ
イウェル点検中ならば、炉心を未臨界にするような操作
を指示するものであり、(23−1)と(24−1)はそれ
ぞれタービン、発電機が併入中である場合は出力上昇の
ための反応度操作をしないことを意味している。(25−
1)以降が出力上昇のための運転目標を設定しているも
ので、(25−1)では炉心が未臨界である場合は炉心を
臨界にする運転目標がたてられる。(26−1)では炉水
温度が100℃以下である場合は炉水温度を100℃にする運
転目標が設定される。(27−1)では炉圧が30kg以下で
ある場合は炉圧30kgを運転目標に設定する。(28−1)
は、炉圧が30kg以上であれば、第1回のドライウェル点
検を実施済みでなければ、これを実施するようガイドを
提示し、点検が完了している場合で炉圧が50kg以下であ
れば炉圧50kgを運転目標に設定する。(29−1)では、
炉圧が定格圧力以下であれば、炉圧定格圧力を運転目標
に設定する。(30−1)はAPRM(Average Power Range
Monitor)の値が下限値以下であれば、これより若干上
の値になるまで出力上昇させることを運転目標に設定す
る。(31−1)は、タービンバイパス弁開度が設定値以
下の場合、これが所定の値になるまで出力上昇させるこ
とを運転目標に設定する。(32−1)は、発電機が運転
されている状態でAPRMの計数値が20%より小さい場合
に、20%まで出力を上昇させることを運転目標に設定す
る。(33−1)は、同様に40%まで出力上昇させること
を運転目標に設定する。(34−1)は最終的に100%ま
で出力上昇させることを運転目標に設定する。 The data shown in the table are for setting the operation target of the output increase in the host control system that controls the control rod operation or the recirculation operation for increasing the output. Explaining the individual descriptions, (22-1) to (24-1) show conditions in which the reactivity operation for increasing the output is not performed. (22-1) indicates the operation to make the core subcritical if drywell inspection is in progress, and (23-1) and (24-1) indicate that a turbine and a generator are installed together. If it is, it means that the reactivity operation for increasing the output is not performed. (25−
The operation target for increasing the power is set from 1) onward, and in (25-1), when the core is subcritical, the operation target is set to make the core critical. In (26-1), when the reactor water temperature is 100 ° C or lower, an operation target for setting the reactor water temperature to 100 ° C is set. In (27-1), if the furnace pressure is 30 kg or less, set the furnace pressure to 30 kg as the operation target. (28-1)
If the furnace pressure is 30kg or more, if the first dry well inspection has not been carried out, a guide will be presented to perform it, and if the inspection is completed, the furnace pressure should be 50kg or less. For example, set the furnace pressure to 50 kg as the operation target. (29-1)
If the furnace pressure is below the rated pressure, set the furnace pressure rated pressure as the operation target. (30-1) is APRM (Average Power Range)
If the value of (Monitor) is less than or equal to the lower limit value, the operation target is set to increase the output until it becomes a value slightly above this value. When the turbine bypass valve opening is equal to or less than the set value, (31-1) sets the operation target to increase the output until it reaches a predetermined value. (32-1) sets the operation target to increase the output to 20% when the APRM count value is smaller than 20% while the generator is operating. Similarly, (33-1) sets the operating target to increase the output to 40%. (34-1) sets the operation target to finally increase the output to 100%.
なお、この表の中で下部に書かれた運転目標は上部の条
件がすべて満足されない場合にのみ実現される。例え
ば、(32−4)に示された20%までの出力上昇の運転目
標が設定されるためには、これ以前にあるすべての条件
は否定されている必要がある。すなわち、炉水温度は10
0℃以上であり、炉圧は定格圧力以上であり、APRMの値
は下限値以上であり、タービンは併入済みである。In addition, the operation target written in the lower part of the table is realized only when all the conditions in the upper part are not satisfied. For example, in order to set the operation target of the output increase up to 20% shown in (32-4), all the conditions existing before this need to be denied. That is, the reactor water temperature is 10
The temperature is 0 ° C or higher, the furnace pressure is the rated pressure or higher, the APRM value is the lower limit or higher, and the turbine has already been installed.
本発明の自動運転管理方法にしたがってプラントを自動
運転するためのシステムを第6図に示す。図中、符号10
1、102はそれぞれプラントと、そのプラントを制御する
制御系である。そして、自動運転システムは、運転目標
の発生に至る機能実現のための操作手順に対応するデー
タ、例えば前述の表に示したようなデータが収納された
操作手順データ部103と、プラント101と制御系102の状
態を監視する運転状態監視部104と、この運転状態監視
部104からの運転状態を入力して操作手順データ部103の
データに基づいて運転目標を定める推論部105と、この
推論部105で設定された運転目標を入力し、制御系設定
値の設定あるいは機器の起動などを実施する要求運転目
標部106と、推論部105において安全性評価などの理由で
制限すべき状態量があると判断された場合に導出された
運転制限目標を記録し、これによって先に設定された要
求運転目標部106の運転目標を規制する運転制限目標部1
07とで構成される。FIG. 6 shows a system for automatically operating a plant according to the automatic operation management method of the present invention. In the figure, reference numeral 10
Reference numerals 1 and 102 denote a plant and a control system for controlling the plant, respectively. Then, the automatic driving system, the data corresponding to the operation procedure for realizing the function leading to the generation of the operation target, for example, the operation procedure data section 103 in which the data shown in the above table is stored, the plant 101 and the control. An operating state monitoring unit 104 that monitors the state of the system 102, an inference unit 105 that inputs an operating state from the operating state monitoring unit 104 and determines an operating target based on the data of the operation procedure data unit 103, and this inference unit There is a required operation target section 106 that inputs the operation target set in 105 and sets the control system set value or starts the equipment, and the state quantity that should be restricted in the reasoning section 105 for reasons such as safety evaluation. The operation restriction target unit 1 that records the derived operation restriction target when it is determined that the operation target of the required operation target unit 106 previously set by this is restricted.
Composed of 07 and.
沸騰水型原子力発電プラントの起動に際し、通常の運転
操作手順は次のように導出される。When starting a boiling water nuclear power plant, a normal operation procedure is derived as follows.
まず、第1図の安全性評価4、5、6により排ガス処理
能力7、非常時冷却能力8、炉水浄化能力9を発現する
機器が起動される。これらの機能は出力レベルが高くな
った時点で必要となるので、起動の初めの段階では必要
ないと思われるが、これは発電所の運用基準に準拠する
ものである。First, the equipment that exhibits the exhaust gas treatment capacity 7, the emergency cooling capacity 8, and the reactor water purification capacity 9 is activated by the safety evaluations 4, 5, and 6 in FIG. These functions are required at the time of high power levels and may not be needed at the beginning of start-up, but this is in compliance with the operating standards of the power plant.
第1図に示した安全性評価を満足するための機能が確保
されると、出力レベル1、復水器真空度2、炉圧3の3
個の状態量が評価され、第2図ないし第5図に示したよ
うに運転方策が選択される。起動の最初の段階では炉圧
(炉水温度)も真空度も出力レベルも低いので、第2図
より炉水温度の上昇と復水器の真空度上昇に対応する運
転が実施される。なお、出力上昇に対応する運転方策は
採られないので制御棒操作は行われないが、現在の中性
子束レベルにふさわしい中性子計測器が挿入されている
ことが確認される。Once the functions for satisfying the safety evaluation shown in Fig. 1 are secured, output level 1, condenser vacuum degree 2, and furnace pressure 3
The individual state quantities are evaluated and the driving strategy is selected as shown in FIGS. Since the reactor pressure (reactor water temperature), the degree of vacuum, and the output level are low at the initial stage of startup, the operation corresponding to the rise in the reactor water temperature and the rise in the condenser vacuum is carried out from FIG. It should be noted that it is confirmed that the neutron measuring instrument suitable for the current neutron flux level is inserted, though the control rod operation is not performed because the operation measure corresponding to the output increase is not adopted.
ついで、炉水温度が80℃以上、真空度が50mmHgになる
と、出力上昇すなわち制御棒引抜きが実行される。真空
度上昇も同時に実施される。ここで、出力上昇の運転方
策が選択されると、表に示したような出力上昇操作が上
から実行される。例えば、タービンが併入中であること
が運転状態監視部104で確認されると、(23−1)が成
立するので、出力上昇操作は行われないことになる。Then, when the reactor water temperature is 80 ° C. or higher and the degree of vacuum is 50 mmHg, the output is increased, that is, the control rod is pulled out. The vacuum degree is also raised at the same time. Here, when the driving strategy for increasing the output is selected, the output increasing operation as shown in the table is executed from above. For example, if it is confirmed by the operation state monitoring unit 104 that the turbine is in the process of being inserted, (23-1) is established, and thus the output increasing operation is not performed.
運転方策にしたがって出力が上昇し、これとともに炉圧
が上昇するが、炉圧が20kg/cm2となると、給水能力の確
保として第1図よりMDRFP(Motor Driven Reactor Feed
WaTer Pump)の起動が必要となる。このように、状態
量の変化に対応してこれを確保あるいはこれを利用する
機器が起動され、プラントの目標とする運転状態に移行
される。Output increases as the operating strategy, but the same time the furnace pressure increases, the furnace pressure is 20kg / cm 2, MDRFP than the first figure as ensuring water supply capacity (Motor Driven Reactor Feed
WaTer Pump) needs to be started. In this way, the equipment that secures or uses the state quantity in response to the change in the state quantity is activated, and the operating state targeted by the plant is entered.
次に、スクラム直後の起動を考える。スクラム原因によ
って異なるが、復水器の真空度も炉圧も目標状態にあっ
たとすると、この場合も第1図に示した安全性評価を満
足するための操作がまず実行される。ついで、出力上昇
の運転方策が選択され、直ちに制御棒が引抜かれるが、
同時に圧力と真空度を保持するための運転が実行され
る。ただし、給水能力を例にとると、スクラム後もTDRF
P(Turbine Driven Feed Water Pump)が稼働している
場合は給水能力は確保されていると判断されるので、MD
RFPが起動されることはない。Next, consider starting immediately after scrum. Although it depends on the cause of the scrum, if both the degree of vacuum of the condenser and the furnace pressure are in the target states, the operation for satisfying the safety evaluation shown in FIG. 1 is first executed in this case as well. Then, a driving strategy for increasing the output is selected and the control rod is immediately withdrawn,
At the same time, the operation for maintaining the pressure and the degree of vacuum is executed. However, taking water supply capacity as an example, the TDRF
When P (Turbine Driven Feed Water Pump) is operating, it is judged that the water supply capacity is secured, so MD
RFP is never activated.
以上の説明からも明らかなように、第1図に示したプラ
ントの状態量と機能の関係からプラントの運転操作手順
が導出される。この関係はどのようなプラント状態にお
いても満たされなければならないので、任意の状態から
操作手順が合成されるものである。As is clear from the above description, the operating procedure of the plant is derived from the relationship between the state quantity and the function of the plant shown in FIG. Since this relationship must be satisfied in any plant condition, the operating procedure is synthesized from any condition.
[発明の効果] 以上説明したように、本発明のプロセスプラントの自動
運転管理方法によれば、プロセスプラントがどのような
運転状態にあっても適切な操作手順を導出することがで
き、これを用いることによりプロセスプラントの全自動
運転が可能になる。[Effects of the Invention] As described above, according to the process plant automatic operation management method of the present invention, it is possible to derive an appropriate operation procedure regardless of the operating state of the process plant. By using it, fully automatic operation of the process plant becomes possible.
第1図は沸騰水型原子力発電プラントの状態と機能と安
全性評価の関係を示す図、第2図ないし第5図は3個の
状態量の相互関係から選択される運転方策を提示する
図、第6図は本発明の方法によってプラントの自動運転
を実施するためのシステムの構成を示すブロック図であ
る。FIG. 1 is a diagram showing the relationship between the state and function of a boiling water nuclear power plant and safety evaluation, and FIGS. 2 to 5 are diagrams presenting operational strategies selected from the interrelationship of three state quantities. FIG. 6 is a block diagram showing the configuration of a system for carrying out automatic operation of a plant by the method of the present invention.
Claims (1)
セスプラントの運転状態を代表する主要な状態量と、プ
ロセスプラントの安全上必ず満たすべき運転条件として
評価される安全性評価と、前記主要な状態量および安全
性評価の各々の確保に必要なもしくは各々に依存する、
機器の作動により発現する機能との三者の関係を予め明
らかにするとともに、前記主要な状態量の相互の関係か
ら変更すべき状態量を規定した運転方策を予め定義し、
前記最終目標に対する運転操作の手順を、前記安全性評
価を満たす機能を確保し、ついでプロセスプラントの運
転状態に応じて選定される前記運転方策にしたがって所
定の状態量を変更するよう、前記三者の関係に基づいて
状態量ごとに運転目標を設定する形で導出することを特
徴とするプロセスプラントの自動運転管理方法。1. A main state quantity that represents the operating state of the process plant with respect to the final goal of the process plant, a safety evaluation that is evaluated as an operating condition that must be satisfied in terms of the safety of the process plant, and the main state. Quantity required and / or dependent on each to ensure safety assessment,
In addition to clarifying in advance the relationship of the three with the function that appears due to the operation of the equipment, predefine a driving policy that defines the state quantity to be changed from the mutual relationship of the main state quantities,
The operation procedure for the final goal is to ensure a function that satisfies the safety evaluation, and then to change the predetermined state quantity according to the operation policy selected according to the operation state of the process plant, An automatic operation management method for a process plant, characterized by deriving an operation target for each state quantity based on the relationship between
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63094892A JPH0776884B2 (en) | 1988-04-18 | 1988-04-18 | Automatic operation management method for process plant |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63094892A JPH0776884B2 (en) | 1988-04-18 | 1988-04-18 | Automatic operation management method for process plant |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH01265310A JPH01265310A (en) | 1989-10-23 |
| JPH0776884B2 true JPH0776884B2 (en) | 1995-08-16 |
Family
ID=14122691
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP63094892A Expired - Lifetime JPH0776884B2 (en) | 1988-04-18 | 1988-04-18 | Automatic operation management method for process plant |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH0776884B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE112018006086T5 (en) * | 2017-11-29 | 2020-09-03 | Mitsubishi Hitachi Power Systems, Ltd. | Operating condition evaluation device, operating condition evaluation method and control system for power plant |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS57707A (en) * | 1980-05-30 | 1982-01-05 | Hitachi Ltd | Deciding method for accident operating method |
| JPS59161707A (en) * | 1983-03-07 | 1984-09-12 | Hitachi Ltd | Plant operation guide device |
| JPH065487B2 (en) * | 1984-01-13 | 1994-01-19 | 株式会社日立製作所 | Plant operation guidance system |
| JPS6336310A (en) * | 1986-07-30 | 1988-02-17 | Nippon Atom Ind Group Co Ltd | Automatic plant operating system |
-
1988
- 1988-04-18 JP JP63094892A patent/JPH0776884B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH01265310A (en) | 1989-10-23 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH06201891A (en) | Device and method of controlling nuclear reactor | |
| CA1243098A (en) | Distributed control with mutual spare switch over capability | |
| EP0696032B2 (en) | Transient adjusted overpower protection system | |
| JPH0776884B2 (en) | Automatic operation management method for process plant | |
| EP0239054A1 (en) | Process control system and method | |
| CN117438119B (en) | High temperature gas-cooled reactor transition core unit interlocking control method and system | |
| JPS63154994A (en) | Fuel exchanger controller | |
| JPH04118591A (en) | Control rod draw-off monitoring system | |
| JPH04194782A (en) | Recirculation flow controller | |
| Nishino et al. | INTERNAL EVENT LEVEL-1 PRA FOR SODIUM-COOLED FAST REACTOR CONSIDERING SAFETY MEASURES OF DEFENSE-IN-DEPTH LEVEL 1 TO 4 | |
| JPH01299497A (en) | Nuclear reactor pressure controller | |
| JPH0196598A (en) | Functional hierarchical configuration output control system | |
| JPS6069710A (en) | Plant operation diagnosis guide method | |
| JPH03255987A (en) | After-stop operating method for fast breeder | |
| JPH01259300A (en) | Control panel monitoring and supporting system | |
| JPS5848890A (en) | Control rod operation assisting device | |
| CN118629681A (en) | A method, device and equipment for interlocking control of high temperature gas-cooled reactor multi-stack operation | |
| JPS59143992A (en) | Reactor isolation cooling system | |
| KR20220099850A (en) | Preventive method of reactor trip in case of one RCP trip in Small Modular Reactor | |
| CN114353102A (en) | Control method and system for safety protection of sludge fluidized bed incinerator | |
| Nowicki et al. | On-line data acquisition and processing system for the HTGR | |
| JPS6239788A (en) | Controller for output from nuclear reactor | |
| JPS5915000B2 (en) | Computer-based load runback control method for power generation plants | |
| JPS6019004B2 (en) | Driving operation monitoring device | |
| JPH0432799A (en) | Nuclear reactor operation area limiting device |