JP3362019B2 - Earth retaining wall and RC composite structure - Google Patents
Earth retaining wall and RC composite structureInfo
- Publication number
- JP3362019B2 JP3362019B2 JP33261599A JP33261599A JP3362019B2 JP 3362019 B2 JP3362019 B2 JP 3362019B2 JP 33261599 A JP33261599 A JP 33261599A JP 33261599 A JP33261599 A JP 33261599A JP 3362019 B2 JP3362019 B2 JP 3362019B2
- Authority
- JP
- Japan
- Prior art keywords
- retaining wall
- earth retaining
- main body
- steel plate
- reinforcing bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【0001】[0001]
【発明の属する技術分野】本願発明は、鋼材を芯材とす
る土留め壁の内側に鉄筋コンクリート構造の本体構造物
を構築するに当たって、土留め壁の芯材の鋼材と鉄筋コ
ンクリート構造の本体外周壁をジベルを介して一体化し
てなる土留め壁・RC合成構造物に関するもので、建物
の地下部分あるいはトンネルや地下駐車場などの地中構
造物に適用される。TECHNICAL FIELD The present invention relates to the construction of a main body structure of a reinforced concrete structure inside a soil retaining wall having a steel core material, in which the steel material of the core material of the soil retaining wall and the outer peripheral wall of the main body of the reinforced concrete structure are formed. This relates to earth retaining walls and RC composite structures that are integrated through a dowel, and is applied to underground parts of buildings or underground structures such as tunnels and underground parking lots.
【0002】[0002]
【従来の技術】従来の土留め壁・RC壁合成構造物の構
築では、H形鋼などを芯材とする土留め壁としての地中
連続壁を構築し、地中連続壁によって囲まれる、あるい
は挟まれる構造物地下部分あるいは地中構造物部分を掘
削した後、土留め壁の内側面の洗浄を行い、芯材となる
H形鋼等のフランジにスタッドジベルなどを、現場溶接
により取り付けている。その後、本体側壁や本体床版部
分の配筋作業を行い、コンクリートの打設により、上述
したスタッドジベルなどを介して土留め壁とRC構造の
本体壁を一体化し、合成構造物を形成している。2. Description of the Related Art In the construction of a conventional earth retaining wall / RC wall composite structure, an underground continuous wall as an earth retaining wall having H-shaped steel as a core material is constructed and surrounded by the underground continuous wall. Alternatively, after excavating the underground part of the structure to be sandwiched or the underground structure part, wash the inner surface of the earth retaining wall, and attach the stud dowel etc. to the flange of the H-section steel etc. which is the core material by field welding. There is. After that, the side wall of the main body and the floor slab of the main body are laid out, and the concrete retaining wall is integrated with the earth retaining wall and the main body wall of the RC structure through the above-mentioned stud dowel to form a composite structure. There is.
【0003】また、特開平7−48846号公報には、
スタッドジベルの現場溶接の問題や、スタッドジベルを
あらかじめ工場で溶接しておく場合の施工上の問題を解
決することを目的として、土留め壁の芯材にあらかじめ
短いネジ切りボルトを工場で溶接しておき、ネジ切りボ
ルトに保護キャップを被せて地中に建て込み、土留め壁
内側の掘削を行った後、保護キャップを外してカプラー
によりネジ切りコネクタを上記ネジ切りボルトと接合
し、ジベルとして用いる合成地下壁の構築方法が開示さ
れている。Further, Japanese Patent Application Laid-Open No. 7-48846 discloses that
In order to solve the problem of welding the stud dowel in the field and the problem of construction when the stud dowel is welded at the factory beforehand, short threaded bolts are welded at the factory in advance to the core material of the earth retaining wall. In advance, cover the threaded bolt with a protective cap and build it in the ground, after excavating the inside of the earth retaining wall, remove the protective cap and join the threaded connector with the above threaded bolt with a coupler, A method of constructing a synthetic basement wall for use is disclosed.
【0004】[0004]
【発明が解決しようとする課題】従来の土留め壁・RC
壁合成構造物の一般的な構築方法において、スタッドジ
ベルをあからじめ芯材に溶接した状態で芯材を建て込む
ことが考えられるが、その場合、建込み時にスタッドジ
ベルが変形したり損傷したりする恐れがある。また、建
込み後の内面側の掘削時においても、多数のスタッドジ
ベルが突出する部分をスタッドジベルに変形、損傷を与
えずに掘削し、洗浄することは作業上困難である。[Problems to be Solved by the Invention] Conventional retaining wall / RC
In the general construction method of wall composite structures, it is possible to build the core material by welding the stud dowel to the core material in a state that it is deformed or damaged during installation. There is a risk of doing it. Further, even when excavating the inner surface side after the construction, it is difficult in terms of work to excavate and clean the portion where a large number of stud dowels project without deforming or damaging the stud dowels.
【0005】また、特開平7−48846号公報記載の
方法においては、上記の問題点が解決されるものの、保
護キャップの取付け、取外し、現場でのカプラーによる
多数のネジ切りコネクタとネジ切りボルトの接合等に多
くの手間を要し、必ずしも現場作業の効率化につながら
ない。本願発明は、上述のような従来技術における課題
の解決を図ったものであり、あらかじめ土留め壁の芯材
に取り付けた穴あき鋼板ジベルにより、現場作業の大幅
な簡略化が可能であり、かつジベルによる一体性にも優
れる土留め壁・RC合成構造物を提供することを目的と
している。Further, in the method described in Japanese Patent Laid-Open No. 7-48846, although the above-mentioned problems are solved, a protective cap is attached and detached, and a large number of threaded connectors and threaded bolts by couplers are used in the field. A lot of labor is required for joining, etc., and it does not necessarily lead to the improvement of work efficiency on site. The invention of the present application is intended to solve the problems in the conventional technology as described above, and by the perforated steel plate dowel attached to the core material of the earth retaining wall in advance, it is possible to greatly simplify the site work, and It is intended to provide an earth retaining wall / RC composite structure that is also excellent in unity by Gibel.
【0006】[0006]
【課題を解決するための手段】本願の請求項1に係る土
留め壁・RC合成構造物は、先行して施工された土留め
壁の芯材である鋼材と、前記土留め壁の内側に構築され
た鉄筋コンクリート構造の本体外周壁を、前記鋼材の土
留め壁内側面に突出させたジベルを介して一体化してな
る土留め壁・RC合成構造物において、前記ジベルとし
て帯状の鋼板の長手方向に複数の穴を形成してなる穴あ
き鋼板ジベルを、前記鋼材の土留め壁内側に突出させて
鋼材の長手方向に沿って接合し、前記本体外周壁のコン
クリート内に埋め込んであることを特徴とするものであ
る。The earth retaining wall / RC composite structure according to claim 1 of the present application has a steel material which is a core material of the earth retaining wall, which has been constructed in advance, and an inside of the earth retaining wall. In an earth retaining wall / RC composite structure in which a main body outer peripheral wall of a constructed reinforced concrete structure is integrated through a dowel protruding to an inner surface of the earth retaining wall of the steel material, in a longitudinal direction of a strip-shaped steel plate as the gibbel. Characterized in that a perforated steel plate dowel formed by forming a plurality of holes in the steel material is projected inside the earth retaining wall of the steel material and joined along the longitudinal direction of the steel material, and is embedded in the concrete of the outer peripheral wall of the main body. It is what
【0007】土留め壁の芯材となる鋼材としては、H形
鋼が一般的であるが、H形鋼に限定する必要はなく、任
意の断面の鋼材を利用可能である。穴あき鋼板ジベル
は、通常は、内側に構築される鉄筋コンクリート構造の
本体壁の区間に設ければよく、短尺のものを多数取り付
ける場合と、長尺のものを1枚または数枚取り付ける場
合とが考えられる。また、芯材がH形鋼である場合など
において、H形鋼のフランジに1列設ける場合と複数列
設ける場合とが考えられる。穴あき鋼板ジベルの鋼材へ
の接合は、通常、工場での溶接によって行うことにな
り、品質管理の面で有利である。As a steel material for the core material of the earth retaining wall, an H-section steel is generally used, but it is not limited to the H-section steel, and a steel material having an arbitrary cross section can be used. Generally, the perforated steel plate dowel may be provided in the section of the main body wall of the reinforced concrete structure constructed inside, and there are a case where a large number of short ones are attached and a case where one or a few long ones are attached. Conceivable. Further, when the core material is an H-shaped steel, it may be possible to provide one row or a plurality of rows on the flange of the H-shaped steel. Joining of a perforated steel plate dowel to a steel material is usually performed by welding in a factory, which is advantageous in terms of quality control.
【0008】本願発明では、土留め壁の芯材の建込み
を、あらかじめ穴あき鋼板ジベルを接合した状態で行う
ことができるため、現場での作業が少なく、施工が容易
となる。また、穴あき鋼板ジベルは、芯材の長手方向に
取り付けられており、芯材の建込みに際しての地盤から
の鉛直方向の抵抗に対しては、従来のスタッドボルトや
丸鋼に比べ、断面剛性の面からもはるかに大きな支圧抵
抗力が得られるため、変形や損傷の恐れがない。さら
に、穴あき鋼板ジベル自体、スタッドボルトなどに比
べ、断面剛性が大きいことから、疲労特性の面でも優れ
ている。According to the present invention, since the core material of the earth retaining wall can be built in the state where the perforated steel plate dowel is joined in advance, the work on the site is small and the construction is easy. In addition, the perforated steel plate dowel is attached in the longitudinal direction of the core material, and it has a cross-sectional rigidity that is higher than that of conventional stud bolts and round steel against the vertical resistance from the ground when installing the core material. Since a much larger bearing resistance can be obtained from the aspect of, there is no fear of deformation or damage. Furthermore, since it has greater cross-sectional rigidity than the perforated steel plate dowel itself, stud bolts, etc., it is also excellent in terms of fatigue characteristics.
【0009】請求項2は、請求項1に係る土留め壁・R
C合成構造物において、前記穴あき鋼板ジベルの穴に、
本体外周壁のコンクリートとの一体性を増すための差し
筋または水平方向鉄筋を通してある場合である。すなわ
ち、穴あき鋼板ジベルの穴を利用して、これに差し筋ま
たは水平方向鉄筋を通すことで、さらにコンクリートと
の一体性を高めることができる。また、この穴を鉄筋コ
ンクリート構造の本体外周壁や本体床版の鉄筋の位置決
めや保持に利用することも可能である。A second aspect is the earth retaining wall / R according to the first aspect.
In the C composite structure, in the hole of the perforated steel plate dowel,
This is the case when there are rebars or horizontal rebars to increase the integrity of the outer peripheral wall of the main body with the concrete. That is, by utilizing the holes of the perforated steel plate dowel and passing the reinforcing bars or horizontal reinforcing bars through the holes, the integrity with concrete can be further enhanced. It is also possible to use this hole for positioning and holding the outer peripheral wall of the main body of the reinforced concrete structure and the reinforcement of the main body slab.
【0010】なお、水平方向鉄筋の配筋は、穴あき鋼板
ジベルの穴を一部切欠くことにより容易となる。請求項
3は、請求項1または2に係る土留め壁・RC合成構造
物において、前記本体外周壁と鉄筋コンクリート構造の
本体床版との接合位置について、前記本体床版の鉄筋端
部を前記土留め壁の芯材である鋼材近傍まで延長して折
り曲げ、この折曲げ部分を、前記穴あき鋼板ジベルの穴
に通した差し筋または水平方向鉄筋と前記鋼材の表面と
の間に挟み込んだ形で拘束し定着させてある場合であ
る。The arrangement of horizontal reinforcing bars is facilitated by partially cutting out the holes of the perforated steel plate dowel. According to a third aspect of the present invention, in the earth retaining wall / RC composite structure according to the first or second aspect, at the joint position between the outer peripheral wall of the main body and the main body slab of the reinforced concrete structure, the rebar end portion of the main body slab is the soil. Bend by extending it to the vicinity of steel, which is the core material of the retaining wall, and fold this bent portion between the reinforcing bar or horizontal rebar inserted through the hole of the perforated steel plate dowel and the surface of the steel material. This is the case when they are restrained and fixed.
【0011】本体外周壁と本体床版(底版、頂版を含
む)との接合部は、構造物の強度上、重要な箇所であ
り、床版の鉄筋を延長したり、隅角部のハンチ部分にハ
ンチ補強筋を配筋するなどして補強がなされる。従来の
構造では、土留め壁の芯材となる鋼材に治具を取り付
け、その治具に延長した床版の鉄筋を定着させるといっ
たことが行われているが、請求項3に係る発明では、穴
あき鋼板ジベルの穴に通した差し筋または水平方向鉄筋
を利用して定着を行う構造となっており、治具の取付け
手間が省ける。The joint portion between the outer peripheral wall of the main body and the main floor slab (including the bottom slab and the top slab) is an important point in terms of the strength of the structure. The reinforcing bars of the floor slab are extended and the corner punches are provided. Reinforcement is made by arranging a haunch reinforcement bar in the part. In the conventional structure, a jig is attached to a steel material serving as a core material of the earth retaining wall, and the reinforcing bar of the floor slab extended to the jig is fixed. However, in the invention according to claim 3, The structure is such that fixing is carried out by using the reinforcing bar or horizontal reinforcing bar that passes through the hole of the perforated steel plate dowel, which saves the trouble of attaching the jig.
【0012】また、従来の構造では、定着用の治具をあ
らかじめ芯材に取り付けておく場合、芯材の高止まりな
ど、施工上の制約から定着が困難となる場合があるが、
本願発明では穴あき鋼板ジベルの任意の穴を利用できる
ため、そのような制約が少ない。なお、挟み込んだ形で
拘束しというのは、必ずしもこれらが密着している必要
はなく、コンクリートを介して拘束されていることで十
分である。Further, in the conventional structure, when the fixing jig is attached to the core material in advance, the fixing may be difficult due to construction restrictions such as the core material staying high.
In the present invention, since any hole of the perforated steel plate dowel can be used, there are few such restrictions. It should be noted that the constraint in the sandwiched form does not necessarily need to be in close contact with each other, and it is sufficient to be restrained through concrete.
【0013】請求項4は、請求項2または3に係る土留
め壁・RC合成構造物において、前記穴あき鋼板ジベル
の穴に、本体外周壁側に開口する切欠きを設け、前記差
し筋または水平方向鉄筋を切欠き部分から挿入できるよ
うにしたものである。特に水平方向鉄筋の場合、本体外
周壁の配筋の一部であることから、穴あき鋼板ジベルの
穴に通すことが難しかったり、あるいは不可能な場合が
ある。そのような場合には、請求項4のように、穴に本
体外周壁側に開口する切欠きを設けることで、差し筋ま
たは水平方向鉄筋を横から嵌め込むことができ、現場作
業が容易となる。According to a fourth aspect of the present invention, in the earth retaining wall / RC composite structure according to the second or third aspect, the hole of the perforated steel plate dowel is provided with a notch opening to the outer peripheral wall side of the main body, The horizontal reinforcing bars can be inserted through the notches. Particularly in the case of a horizontal reinforcing bar, it is difficult or impossible to pass through the hole of a perforated steel plate dowel because it is a part of the bar arrangement of the outer peripheral wall of the main body. In such a case, as described in claim 4, by providing the hole with a notch that opens to the outer peripheral wall side of the main body, the reinforcing bar or the horizontal reinforcing bar can be fitted from the side, which facilitates field work. Become.
【0014】請求項5は、請求項1または2に係る土留
め壁・RC合成構造物において、前記本体外周壁と鉄筋
コンクリート構造の本体床版との接合位置について、前
記本体床版の鉄筋端部を前記土留め壁の芯材である鋼材
近傍まで延長して折り曲げ、この折曲げ部分を、前記穴
あき鋼板ジベルの穴にスペーサーまたは止め具を介して
取り付けた差し筋または水平方向鉄筋と前記鋼材の表面
との間に挟み込んだ形で拘束し定着させたものである。According to a fifth aspect of the present invention, in the earth retaining wall / RC composite structure according to the first or second aspect, regarding the joint position between the outer peripheral wall of the main body and the main body floor slab of the reinforced concrete structure, the reinforcing bar end portion of the main body floor slab is connected. And extend it to near the steel material that is the core material of the earth retaining wall, and bend this bent portion to the hole of the perforated steel plate dowel through a spacer or a stopper or a horizontal reinforcing bar and the steel material. It is fixed and fixed by being sandwiched between it and the surface of.
【0015】基本的な概念は請求項3の場合と同様であ
るが、本体床版の鉄筋が太径の場合等、穴あき鋼板ジベ
ルの穴に差し込んだ差し筋または水平方向鉄筋と土留め
壁の芯材である鋼材の表面との間に、本体床版の鉄筋の
折曲げ部分を挿入するのに十分なスペースがない場合が
考えられる。その場合には、請求項5のように、穴あき
鋼板ジベルの穴に直接差し筋などを挿入する代わりに、
スペーサーまたは止め具を挿入し、これらを介して差し
筋を止め付けるようにすることで、本体床版の鉄筋を挿
入するスペースを確保することができる。The basic concept is the same as that of claim 3, but when the rebar of the main body floor slab has a large diameter, the rebar or horizontal rebar and the earth retaining wall inserted into the hole of the perforated steel plate dowel. It is conceivable that there is not enough space between the core material and the surface of the steel material to insert the bent portion of the reinforcing bar of the main body floor slab. In that case, instead of directly inserting a reinforcing bar or the like into the hole of the perforated steel plate dowel as in claim 5,
By inserting a spacer or a stopper and fixing the reinforcing bar through these, a space for inserting the reinforcing bar of the main body floor slab can be secured.
【0016】[0016]
【発明の実施の形態】図1は、本願の請求項1、2に係
る土留め壁・RC合成構造物の一実施形態における穴あ
き鋼板ジベルの取付け状態を示したものである。この例
では、土留め壁の芯材としてのH形鋼1の土留め壁内側
面側のフランジ1aに、2本の穴あき鋼板ジベル2をあ
らかじめ工場溶接により取り付けてある。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows an attached state of a perforated steel plate dowel in an embodiment of an earth retaining wall / RC composite structure according to claims 1 and 2 of the present application. In this example, two perforated steel plate dowels 2 are attached in advance to the flange 1a of the H-shaped steel 1 as the core material of the earth retaining wall on the inner side surface side of the earth retaining wall by factory welding.
【0017】穴あき鋼板ジベル2は、帯状鋼板に所定間
隔で穴2aを形成したものであり、本体側壁3のコンク
リートが穴2a内に入り込むことで、コンクリートとの
付着力(主として機械的付着力)を増している。なお、
素材となる帯状鋼板として、縞鋼板など表面に凹凸を有
するものを用いればさらに付着力を増すことができる。The perforated steel plate dowel 2 is formed by forming holes 2a at predetermined intervals on a strip-shaped steel plate, and the concrete of the side wall 3 of the main body enters into the holes 2a so that the adhesive force (mainly mechanical adhesive force) with the concrete is increased. ) Is increasing. In addition,
The adhesive force can be further increased by using a strip-shaped steel plate as a material, such as a striped steel plate, having unevenness on the surface.
【0018】また、穴あき鋼板ジベル2の穴2aに差し
筋4を通すことによっても、さらに付着力を増すことが
できる。図中、5a、5bは、本体壁3のコンクリート
中に配筋される縦筋および横筋である。図6は、土留め
壁・RC合成構造物を、道路用の地中トンネルに適用し
た場合の鉛直断面の一例を示したもので、図1は、図6
中、Cで示した部分に相当する。Further, the adhesive force can be further increased by passing the bar 4 through the hole 2a of the perforated steel plate dowel 2. In the figure, 5a and 5b are vertical and horizontal bars arranged in the concrete of the main body wall 3. FIG. 6 shows an example of a vertical cross section when the earth retaining wall / RC composite structure is applied to an underground tunnel for roads, and FIG.
It corresponds to the part indicated by C in the middle.
【0019】施工手順としては、まず、あらかじめ上述
した穴あき鋼板ジベル2を取り付けたH形鋼1を芯材と
する土留め壁を、トンネル構築位置両側のトンネル延長
方向に構築する。次に、トンネル位置両側の土留め壁間
を掘削し、穴あき鋼板ジベル2を露出させ、洗浄を行
う。その後、本体壁3の配筋を行い、コンクリートを打
設し、穴あき鋼板ジベル2を介して、土留め壁と本体壁
3を一体化する。As a construction procedure, first, earth retaining walls having an H-shaped steel 1 to which the perforated steel plate dowel 2 is attached in advance as core material are constructed in the tunnel extension direction on both sides of the tunnel construction position. Next, excavation is performed between the earth retaining walls on both sides of the tunnel position, the perforated steel plate dowel 2 is exposed, and cleaning is performed. After that, the main body wall 3 is laid out, concrete is poured, and the earth retaining wall and the main body wall 3 are integrated through the perforated steel plate dowel 2.
【0020】なお、図中、10は構造物本体直下位置の
地盤改良部分、11は中間杭を示す。図2は、本願の請
求項3に係る土留め壁・RC合成構造物の一実施形態に
おける穴あき鋼板ジベル2と床版6(底版)の配筋との
関係を示したもので、図6のD部分に相当する。In the figure, 10 is a ground improvement portion directly below the structure body, and 11 is an intermediate pile. FIG. 2 shows the relationship between the perforated steel plate Gibel 2 and the reinforcement of the floor slab 6 (bottom slab) in one embodiment of the earth retaining wall / RC composite structure according to claim 3 of the present application. Corresponds to the D part of.
【0021】図に示すように、本体床版6の主筋7を、
土留め壁の芯材であるH形鋼1のフランジ1a近傍まで
延長して折り曲げ、この折曲げ部分7aを、穴あき鋼板
ジベル2の穴2aに通した差し筋4とフランジ1aの表
面との間に挟み込んだ形で拘束し、コンクリートの打設
により定着させてある。この場合、現場での作業は、主
筋7の折り曲げ部分7が位置する穴2aに差し筋4を挿
入するだけであり、従来の定着方法に比べ、現場作業が
非常に簡単になる。As shown in the figure, the main bar 7 of the main body floor slab 6 is
The H-shaped steel 1 which is the core material of the earth retaining wall is extended and bent to the vicinity of the flange 1a, and the bent portion 7a is passed through the hole 2a of the perforated steel plate dowel 2 and the surface of the flange 1a. It is restrained by sandwiching it and fixed by placing concrete. In this case, the on-site work only requires inserting the insert bar 4 into the hole 2a in which the bent portion 7 of the main bar 7 is located, which makes the on-site work much easier than the conventional fixing method.
【0022】本体壁3と本体床版6との接合部における
ハンチ部分には、ハンチ補強筋9を配筋してある。図3
は、本願の請求項4に係る土留め壁・RC合成構造物の
一実施形態における穴あき鋼板ジベルに形成した切欠き
部分の形状の一例を示したものである。。A haunch reinforcing bar 9 is arranged at the haunch portion at the joint between the body wall 3 and the body floor slab 6. Figure 3
FIG. 8 shows an example of the shape of a notch portion formed in a perforated steel plate dowel in an embodiment of the earth retaining wall / RC composite structure according to claim 4 of the present application. .
【0023】穴あき鋼板ジベル12に、コンクリート中
への配筋の一部である水平方向鉄筋4aを通す場合、図
2のような閉じた穴では水平方向鉄筋4aの配筋が難し
くなる。これに対し、図3の例では、穴あき鋼板ジベル
12の穴12aが開口しているため、図中の矢印の方向
から水平方向鉄筋4aを挿入することができる。従っ
て、あらかじめ多数の鉄筋を組んである場合等でも適用
可能である。なお、水平方向鉄筋4aを挿入する場合に
限らず、差し筋を通す場合にも適用することができる。When the horizontal reinforcing bar 4a, which is a part of the reinforcing bar in the concrete, is passed through the perforated steel plate dowel 12, it is difficult to arrange the horizontal reinforcing bar 4a in the closed hole as shown in FIG. On the other hand, in the example of FIG. 3, since the hole 12a of the perforated steel plate dowel 12 is open, the horizontal reinforcing bar 4a can be inserted from the direction of the arrow in the figure. Therefore, it can be applied even when a large number of reinforcing bars are assembled in advance. The present invention can be applied not only to the case of inserting the horizontal reinforcing bar 4a but also to the case of inserting a reinforcing bar.
【0024】図4は、本願の請求項5に係る土留め壁・
RC合成構造物における差し筋の取付け構造の一例を示
したものである。上述した図2のように床版の主筋の折
曲げ部分7aを拘束する場合に、主筋が太径だと、H形
鋼1のフランジ表面と、差し筋との間のスペースが十分
でない場合がある。FIG. 4 shows the earth retaining wall according to claim 5 of the present application.
It is an example of an attachment structure of a bar in an RC composite structure. When restraining the bent portion 7a of the main bar of the floor slab as shown in FIG. 2 described above, if the main bar has a large diameter, the space between the flange surface of the H-section steel 1 and the bar may not be sufficient. is there.
【0025】これに対し、例えば図4(c) に示すような
ねじ棒付きプレート13を、スペーサーとして穴あき鋼
板ジベル2の穴2aにナット13cで止め付け、フック
形状の差し筋14のフック部分を穴あき鋼板ジベル2の
穴2aに差し込み、反対側の端部をねじ棒付きプレート
13の穴13bに差し込むようにすれば、その内側に主
筋の折曲げ部分7aを納めるのに十分なスペースを確保
することができる。On the other hand, for example, a plate 13 with a screw rod as shown in FIG. 4 (c) is fixed as a spacer to the hole 2a of the perforated steel plate dowel 2 with the nut 13c, and the hook portion of the hook-shaped bar 14 is formed. Is inserted into the hole 2a of the perforated steel plate dowel 2, and the opposite end is inserted into the hole 13b of the plate 13 with a threaded rod, so that there is sufficient space inside to accommodate the bent portion 7a of the main bar. Can be secured.
【0026】主筋の折曲げ部分7aを差し筋14を利用
して拘束する作用・効果は図2の場合と同様である。図
5は、本願の請求項5に係る土留め壁・RC合成構造物
における差し筋の取付け構造の他の例を示したものであ
る。すなわち、この例は、差し筋24を図5(c) のよう
な形に折り曲げ、その端部を棒状の止め筋23で、穴あ
き鋼板ジベル2の穴2aに止め付けることで、その内側
に主筋の折曲げ部分7aを納めるのに十分なスペースを
確保するようにしたものである。The action and effect of restraining the bent portion 7a of the main bar by using the bar 14 are the same as in the case of FIG. FIG. 5 shows another example of the attachment structure of the reinforcing bar in the earth retaining wall / RC composite structure according to claim 5 of the present application. That is, in this example, the reinforcing bar 24 is bent into a shape as shown in FIG. 5 (c), and its end is fixed to the hole 2a of the perforated steel plate dowel 2 by the bar-shaped locking bar 23, so that This is to ensure a sufficient space for accommodating the bent portion 7a of the main bar.
【0027】[0027]
【発明の効果】土留め壁の芯材の長手方向に取り付け
た穴あき鋼板ジベルは、スタッドジベルと比べた場合、
芯材の建込みや、内側の掘削に際し、変形や損傷の恐れ
が少ないため、あらかじめ芯材に取り付けた状態で建て
込むことができる。また、スタッドボルトなどに比べ、
疲労特性の面でも優れている。The perforated steel plate dowel attached in the longitudinal direction of the core material of the earth retaining wall, when compared with the stud dowel,
Since there is little risk of deformation or damage at the time of building the core material or excavating the inside, the core material can be built in the state of being attached in advance. Also, compared to stud bolts,
It is also excellent in fatigue characteristics.
【0028】上述のように、穴あき鋼板ジベルをあら
かじめ工場などで溶接した状態で、芯材を建て込むこと
ができるため、現場での工種が減少し、現場施工が容易
となる。また、工場などで取り付けるため、品質管理が
容易である。
請求項2に係る発明においては、穴あき鋼板ジベルの
穴に差し筋または水平方向鉄筋を通すことで、さらにコ
ンクリートとの一体性を高めることができる。また、こ
の穴を鉄筋コンクリート構造の本体外周壁や本体床版の
鉄筋の位置決めや保持に利用することも可能である。As described above, the core material can be built in a state where the perforated steel plate dowel is welded in advance in a factory or the like, so that the number of kinds of work on the site is reduced and the on-site construction is facilitated. Also, since it is installed in a factory, quality control is easy. In the invention according to claim 2, the integrity of the concrete can be further enhanced by passing the reinforcing bar or the horizontal reinforcing bar through the hole of the perforated steel plate dowel. It is also possible to use this hole for positioning and holding the outer peripheral wall of the main body of the reinforced concrete structure and the reinforcement of the main body slab.
【0029】請求項3に係る発明においては、本体床
版の鉄筋端部の折曲げ部分を穴あき鋼板ジベルの穴に通
した差し筋または水平方向鉄筋と土留め壁の芯材である
鋼材との間に挟み込む形で拘束し、定着させているた
め、床版部分も含めて一体化が図れ、強度上、問題とな
りやすい本体壁と床版部分の補強の効果を併せ持ってい
る。According to a third aspect of the present invention, a reinforcing bar or a horizontal reinforcing bar in which the bent portion of the reinforcing bar end of the main body floor slab is passed through a hole of a perforated steel plate dowel and a steel material as a core material of the earth retaining wall, Since it is sandwiched between and fixed, it is possible to integrate it, including the floor slab, and it has the effect of reinforcing the main body wall and floor slab, which tend to be a problem in strength.
【0030】請求項4に係る発明においては、差し筋
または水平方向鉄筋を横から嵌め込むことができるた
め、特に本体外周壁の配筋の一部となる水平方向鉄筋に
ついて、穴あき鋼板ジベルへの挿入が容易となる。
請求項5に係る発明では、差し筋または水平方向鉄筋
と土留め壁の芯材となる鋼材の表面との間に広いスペー
スが確保でき、例えば床版主筋が太径の場合などにも対
処することができる。In the invention according to claim 4, since the reinforcing bar or the horizontal reinforcing bar can be fitted from the side, particularly for the horizontal reinforcing bar which is a part of the reinforcing bar of the outer peripheral wall of the main body, the perforated steel plate dowel is attached. Is easy to insert. In the invention according to claim 5, a wide space can be secured between the reinforcing bar or the horizontal reinforcing bar and the surface of the steel material serving as the core material of the earth retaining wall, and for example, the case where the floor slab main bar has a large diameter is dealt with. can do.
【図1】 本願の請求項1、2に係る土留め壁・RC合
成構造物の一実施形態における穴あき鋼板ジベルの取付
け状態を示したもので、(a) は鉛直断面図、(b) はその
A−A断面図である。FIG. 1 shows an attached state of a perforated steel plate dowel in an embodiment of an earth retaining wall / RC composite structure according to claims 1 and 2 of the present application, in which (a) is a vertical sectional view and (b) is Is a sectional view taken along line AA.
【図2】 本願の請求項3に係る土留め壁・RC合成構
造物の一実施形態における穴あき鋼板ジベルと床版(底
版)配筋との関係を示したもので、(a) は鉛直断面図、
(b) はそのB−B断面図である。FIG. 2 shows the relationship between perforated steel plate dowels and floor slab (bottom slab) reinforcement in one embodiment of the earth retaining wall / RC composite structure according to claim 3 of the present application, where (a) is a vertical line. Cross section,
(b) is the BB sectional drawing.
【図3】 本願の請求項4に係る土留め壁・RC合成構
造物について、穴あき鋼板ジベルに形成した切欠き部分
の形状の一例を示す鉛直断面図である。FIG. 3 is a vertical cross-sectional view showing an example of the shape of a notch portion formed in a perforated steel plate dowel in the earth retaining wall / RC composite structure according to claim 4 of the present application.
【図4】 本願の請求項5に係る土留め壁・RC合成構
造物における差し筋の取付け構造の一例を示したもの
で、(a) は鉛直断面図、(b) はそのA−A断面図、(c)
は(b) に示される全ねじ棒付きプレート単独の拡大図で
ある。FIG. 4 is a view showing an example of a structure for attaching a reinforcing bar in an earth retaining wall / RC composite structure according to claim 5 of the present application, in which (a) is a vertical sectional view and (b) is its AA cross section. Figure, (c)
[Fig. 3] is an enlarged view of the plate with full-threaded rod alone shown in (b).
【図5】 本願の請求項5に係る土留め壁・RC合成構
造物における差し筋の取付け構造の他の例を示したもの
で、(a) は鉛直断面図、(b) はそのB−B断面図、(c)
は(b) に示される差し筋単独の拡大斜視図である。FIG. 5 shows another example of the structure for attaching the reinforcing bar in the earth retaining wall / RC composite structure according to claim 5 of the present application, in which (a) is a vertical sectional view and (b) is its B- B sectional view, (c)
[Fig. 3] is an enlarged perspective view of the sole bar shown in (b).
【図6】 土留め壁・RC合成構造物の地中トンネルへ
の適用例を示す鉛直断面図である。FIG. 6 is a vertical cross-sectional view showing an application example of an earth retaining wall / RC composite structure to an underground tunnel.
1…H形鋼、2…穴あき鋼板ジベル、2a…穴、3…本
体壁、4…差し筋、4a…水平方向鉄筋、5a…縦筋、
5b…横筋、6…本体床版(底版)、7…主筋、7a…
折曲げ部分、8…せん断補強筋、9…ハンチ補強筋、1
0…地盤改良部分、11…中間杭、12…穴あき鋼板ジ
ベル、12a…切欠きを設けた穴、13…全ねじ棒付き
プレート、13a…ねじ部、13b…穴、13c…ナッ
ト、14…差し筋、23…止め筋、24…差し筋1 ... H-section steel, 2 ... Perforated steel plate dowel, 2a ... Hole, 3 ... Main body wall, 4 ... Reinforcing bar, 4a ... Horizontal reinforcing bar, 5a ... Vertical bar,
5b ... horizontal streak, 6 ... main body floor slab (bottom slab), 7 ... main bar, 7a ...
Bent portion, 8 ... Shear reinforcement, 9 ... Haunch reinforcement, 1
0 ... Ground improvement part, 11 ... Intermediate pile, 12 ... Perforated steel plate dowel, 12a ... Hole provided with notch, 13 ... Plate with full screw rod, 13a ... Screw part, 13b ... Hole, 13c ... Nut, 14 ... Rebar, 23 ... Retainer, 24 ... Rebar
───────────────────────────────────────────────────── フロントページの続き (72)発明者 金治 英貞 大阪府大阪市住之江区南港北1−14−16 阪神高速道路公団大阪建設局内 (72)発明者 佐藤 奈津代 兵庫県神戸市中央区東川崎町1−3−3 神戸ハーバーランドセンタービル22F 阪神高速道路公団神戸第二建設部内 (72)発明者 日紫喜 剛啓 東京都調布市飛田給2丁目19番1号 鹿 島建設株式会社技術研究所内 (72)発明者 須田 久美子 東京都調布市飛田給2丁目19番1号 鹿 島建設株式会社技術研究所内 (72)発明者 古市 耕輔 東京都調布市飛田給2丁目19番1号 鹿 島建設株式会社技術研究所内 (72)発明者 平 陽兵 東京都調布市飛田給2丁目19番1号 鹿 島建設株式会社技術研究所内 (72)発明者 安藤 進 大阪府大阪市西区阿波座1丁目3番15号 鹿島建設株式会社関西支店内 (72)発明者 齊藤 勲雄 大阪府大阪市西区阿波座1丁目3番15号 鹿島建設株式会社関西支店内 (72)発明者 村田 俊彦 東京都港区元赤坂1丁目2番7号 鹿島 建設株式会社内 (56)参考文献 特開 平6−108460(JP,A) 特開 平5−331836(JP,A) 特開 平11−241340(JP,A) (58)調査した分野(Int.Cl.7,DB名) E02D 29/045 E02D 5/20 102 E21D 13/00 ─────────────────────────────────────────────────── ─── Continued Front Page (72) Inventor Hidesada Kinji 1-14-16 Minami Kohoku, Suminoe-ku, Osaka City, Osaka Prefecture Hanshin Expressway Public Corporation Osaka Construction Bureau (72) Inventor Natsuyo Sato Higashikawasaki, Chuo-ku, Kobe-shi, Hyogo Prefecture 1-3-3 Machi Kobe Harborland Center Building 22F Hanshin Expressway Public Corporation Kobe No. 2 Construction Department (72) Inventor Takehiro Nisshiki 2-19-1 Tobita, Chofu-shi, Tokyo Kashima Construction Co., Ltd. Technical Research Institute (72) Invention Kumiko Suda 2-191-1 Tobita-yasu, Chofu-shi, Tokyo Inside Kashima Construction Co., Ltd. (72) Inventor Kosuke Furuichi 2-19-1 Tobita-cho, Chofu-shi, Tokyo Kashima Construction Co., Ltd. (72) ) Inventor Yohei Hei 2-191-1 Tobita-cho, Chofu-shi, Tokyo Kashima Construction Co., Ltd. Technical Research Laboratory (72) Inventor Ando 1-3-15 Awaza, Nishi-ku, Osaka-shi, Osaka Prefecture In Kansai Branch, Kashima Construction Co., Ltd. (72) Inventor Isao Saito 1-3-15, Awaza, Nishi-ku, Osaka City, Osaka Prefecture (72) Inventor, Kansai Branch Toshihiko Murata 1-2-7 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (56) Reference JP-A-6-108460 (JP, A) JP-A-5-331836 (JP, A) JP-A-11 -241340 (JP, A) (58) Fields investigated (Int.Cl. 7 , DB name) E02D 29/045 E02D 5/20 102 E21D 13/00
Claims (5)
る鋼材と、前記土留め壁の内側に構築された鉄筋コンク
リート構造の本体外周壁を、前記鋼材の土留め壁内側面
に突出させたジベルを介して一体化してなる土留め壁・
RC合成構造物において、前記ジベルとして帯状の鋼板
の長手方向に複数の穴を形成してなる穴あき鋼板ジベル
を、前記鋼材の土留め壁内側に突出させて鋼材の長手方
向に沿って接合し、前記本体外周壁のコンクリート内に
埋め込んであることを特徴とする土留め壁・RC合成構
造物。1. A steel material, which is a core material of an earth retaining wall constructed in advance, and a main body outer peripheral wall of a reinforced concrete structure constructed inside the earth retaining wall, projecting to an inner surface of the earth retaining wall of the steel material. An earth retaining wall that is integrated through the gibel.
In the RC composite structure, a perforated steel plate dowel formed by forming a plurality of holes in the longitudinal direction of a strip-shaped steel plate as the dowel is projected inside the earth retaining wall of the steel material and joined along the longitudinal direction of the steel material. An earth retaining wall / RC composite structure characterized by being embedded in concrete of the outer peripheral wall of the main body.
壁のコンクリートとの一体性を増すための差し筋または
水平方向鉄筋を通してある請求項1記載の土留め壁・R
C合成構造物。2. The earth retaining wall / R according to claim 1, wherein the holes of said perforated steel plate dovetails are provided with reinforcing bars or horizontal reinforcing bars for increasing the integrity of the outer peripheral wall of the main body with concrete.
C synthetic structure.
の本体床版との接合位置について、前記本体床版の鉄筋
端部を前記土留め壁の芯材である鋼材近傍まで延長して
折り曲げ、この折曲げ部分を、前記穴あき鋼板ジベルの
穴に通した差し筋または水平方向鉄筋と前記鋼材の表面
との間に挟み込んだ形で拘束し定着させてある請求項1
または2記載の土留め壁・RC合成構造物。3. The joint position between the outer peripheral wall of the main body and the main body slab of the reinforced concrete structure, the end of the rebar of the main body slab is extended and bent to near the steel material which is the core material of the earth retaining wall, and this folding is performed. The bent portion is constrained and fixed by being sandwiched between a reinforcing bar or a horizontal reinforcing bar passing through the hole of the perforated steel plate dowel and the surface of the steel material.
Or the earth retaining wall and RC composite structure described in 2.
壁側に開口する切欠きを設け、前記差し筋または水平方
向鉄筋を切欠き部分から挿入できるようにした請求項2
または3記載の土留め壁・RC合成構造物。4. The hole of the perforated steel plate dowel is provided with a notch opening to the outer peripheral wall side of the main body so that the bar or the horizontal reinforcing bar can be inserted from the notch portion.
Or the earth retaining wall / RC composite structure described in 3.
の本体床版との接合位置について、前記本体床版の鉄筋
端部を前記土留め壁の芯材である鋼材近傍まで延長して
折り曲げ、この折曲げ部分を、前記穴あき鋼板ジベルの
穴にスペーサーまたは止め具を介して取り付けた差し筋
または水平方向鉄筋と前記鋼材の表面との間に挟み込ん
だ形で拘束し定着させてある請求項1または2記載の土
留め壁・RC合成構造物。5. The joint position between the outer peripheral wall of the main body and the main body slab of the reinforced concrete structure is extended by bending the end of the reinforcing bar of the main body slab to near the steel material that is the core material of the earth retaining wall, and this folding is performed. The bent portion is constrained and fixed by being sandwiched between a reinforcing bar or a horizontal reinforcing bar attached to a hole of the perforated steel plate through a spacer or a stopper and the surface of the steel material. The earth retaining wall and RC composite structure described in 2.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP33261599A JP3362019B2 (en) | 1999-11-24 | 1999-11-24 | Earth retaining wall and RC composite structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP33261599A JP3362019B2 (en) | 1999-11-24 | 1999-11-24 | Earth retaining wall and RC composite structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2001146756A JP2001146756A (en) | 2001-05-29 |
| JP3362019B2 true JP3362019B2 (en) | 2003-01-07 |
Family
ID=18256937
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP33261599A Expired - Lifetime JP3362019B2 (en) | 1999-11-24 | 1999-11-24 | Earth retaining wall and RC composite structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3362019B2 (en) |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2009052283A (en) * | 2007-08-27 | 2009-03-12 | Ihi Corp | Method and apparatus for connecting between steel member and concrete member |
| JP2011069057A (en) * | 2009-09-24 | 2011-04-07 | Okabe Co Ltd | Prefabricated concrete pile |
| JP2012046979A (en) * | 2010-08-27 | 2012-03-08 | Kumagai Gumi Co Ltd | Building foundation using earth retaining wall |
| JP6254469B2 (en) * | 2014-03-25 | 2017-12-27 | Jfeスチール株式会社 | Steel member for retaining wall and composite structural wall using the steel member for retaining wall |
| JP7427507B2 (en) * | 2020-04-02 | 2024-02-05 | 鹿島建設株式会社 | Bonding structure and bonding method |
| JP7384755B2 (en) * | 2020-06-24 | 2023-11-21 | 鹿島建設株式会社 | Core material and upper core material removal method |
-
1999
- 1999-11-24 JP JP33261599A patent/JP3362019B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2001146756A (en) | 2001-05-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101058520B1 (en) | A retaining wall composed of PA piles and its construction method | |
| KR101780370B1 (en) | Composite structure using shear connector made of anchor and socket shoe | |
| CN101939492B (en) | Precast temporary facility structure and construction method for the same | |
| KR102357963B1 (en) | Earthquake resistant slurry wall structure | |
| JP4812324B2 (en) | Retaining wall and its construction method | |
| JP3362019B2 (en) | Earth retaining wall and RC composite structure | |
| JP3690437B2 (en) | Seismic reinforcement structure for existing buildings | |
| KR20200136127A (en) | Deck plate wall installation method using underground pavement | |
| KR20000061241A (en) | Precast concrete beam and connecting method with the other building elements | |
| KR102568888B1 (en) | Seismic resistant slurry wall with joint pilaster | |
| JP4436187B2 (en) | Concrete sheet pile | |
| JP5008683B2 (en) | Pile head reinforcement member and pile head reinforcement structure using it | |
| JP4068398B2 (en) | Underground structure | |
| JP4449595B2 (en) | Column-beam joint structure, method for constructing column-beam joint structure, method for constructing underground structure, and building | |
| JP7274332B2 (en) | junction structure | |
| KR100662774B1 (en) | Cheolgolbo Joint Connection Device | |
| JP4419456B2 (en) | Method of joining reinforced concrete member and steel pipe concrete | |
| JP3161886B2 (en) | Foundation for small buildings | |
| KR102926386B1 (en) | Seismic resistant slurry wall and construction method thereof | |
| JP2001254353A (en) | Earth retaining wall / RC composite structure and its construction method | |
| JP3140397B2 (en) | Steel basement | |
| JP7587156B2 (en) | Joint structure between steel wall and reinforced concrete member and its construction method | |
| KR102743424B1 (en) | Local Reinforcement Element for Steel Reinforcement of Pile, Pile having such Local Reinforcement, Constructing Method of such Pile, and Retaining Wall having such Piles | |
| KR20080059951A (en) | Combined pile foundation and underground retaining wall construction method and shear friction reinforcement for them | |
| KR20060117746A (en) | PC girder member for base frame frame, assembly structure and method of construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20021008 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 3362019 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081018 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111018 Year of fee payment: 9 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111018 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141018 Year of fee payment: 12 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
| EXPY | Cancellation because of completion of term |