JP3759101B2 - Formwork support structure and concrete construction method - Google Patents
Formwork support structure and concrete construction method Download PDFInfo
- Publication number
- JP3759101B2 JP3759101B2 JP2002339612A JP2002339612A JP3759101B2 JP 3759101 B2 JP3759101 B2 JP 3759101B2 JP 2002339612 A JP2002339612 A JP 2002339612A JP 2002339612 A JP2002339612 A JP 2002339612A JP 3759101 B2 JP3759101 B2 JP 3759101B2
- Authority
- JP
- Japan
- Prior art keywords
- girder
- concrete
- formwork
- steel
- support structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、例えば現に供用されている橋梁における橋桁など、振動を受ける鋼桁をコンクリートで被覆する場合に用いられる型枠の支持構造及びコンクリートの施工方法に関する。
【0002】
【従来の技術】
従来の型枠の支持構造としては、例えば橋梁の主桁たる鋼部材をコンクリートで被覆するための型枠を支持する支保工であって、地面等によって支持されるものが開示されている(例えば、非特許文献1参照)。
そして、この型枠の支持構造は、近年における建設工事の複雑化及び高度化や、周辺環境への影響に対する配慮の必要性の増大などに伴い、現に供用されている橋梁の橋桁たる主桁をコンクリートで被覆する場合にも用いられている。
【0003】
【非特許文献1】
土木学会編,「土木工学ハンドブックI」,第四版,技報堂出版,1993年11月20日,p.1246
【0004】
【発明が解決しようとする課題】
しかしながら、従来の型枠の支持構造では、コンクリートで被覆すべき主桁が交通振動等を受けることとなっているのに対して、その振動を受ける鋼部材をコンクリートで被覆するための型枠は地面等の不動点によって支持されていることから、鋼部材と型枠との振動差が大きくなってしまい、振動を受ける鋼部材とコンクリートとを一体化した複合構造が確実かつ十分に得られないという問題がある。
すなわち、従来の型枠の支持構造では、型枠は殆ど振動しておらず鋼部材のみが振動している状況となっており、かかる状況の下において型枠内にコンクリートを打ち込んでも、鋼部材の周辺に空隙が生じてしまい、振動を受ける鋼部材とコンクリートとの間で必要な付着強度が確保できないこととなる。
【0005】
そこで、本発明の課題は、振動を受ける鋼桁とコンクリートとを一体化した複合構造が確実かつ十分に得られるように、鋼桁と型枠との振動差を小さくできる型枠の支持構造及びコンクリートの施工方法を提供することにある。
【0006】
【課題を解決するための手段】
上記課題を解決するため、本発明に係る型枠の支持構造は、現に供用されている橋梁において車両が走行することにより振動する鋼桁をコンクリートで被覆するための型枠を支持する型枠の支持構造であって、型枠は、振動する鋼桁に剛接合によって固定され、該鋼桁によってのみ支持されていることを特徴としている。
【0007】
また、本発明に係る他の型枠の支持構造は、現に供用されている橋梁において車両が走行することにより振動する鋼桁をコンクリートで被覆するための型枠を支持する型枠の支持構造であって、型枠は、前記車両の走行方向に所定間隔で切り離され、切り離された位置の近傍で前記鋼桁によってのみ支持される各型枠片からなり、隣り合う前記型枠片どうしが伸縮継手で連結されていることを特徴としている。
【0008】
これらの型枠の支持構造によれば、振動を受ける鋼桁をコンクリートで被覆するための型枠をその振動を受ける鋼桁に剛接合によって固定し、この鋼桁からのみ支持しているので、型枠についても、鋼桁と同様、振動を受けることとなり、鋼桁と型枠との振動差を小さくできる。
【0009】
したがって、これによれば、型枠内にコンクリートを打ち込むと、凝結の進行に伴い鋼桁からコンクリートへの振動の伝達が確実に行われることとなり、その結果、振動を受ける鋼桁とコンクリートとが十分に付着することとなり、振動を受ける鋼桁とコンクリートとを一体化した複合構造が確実かつ十分に得られる。
【0010】
一方、本発明に係るコンクリートの施工方法は、現に供用されている橋梁において車両が走行することにより振動する鋼桁をコンクリートで被覆するため振動する鋼桁に剛接合によって固定し、この鋼桁によってのみ支持した型枠内にコンクリートを打ち込むことを特徴としている。
【0011】
このコンクリートの施工方法によれば、振動を受ける鋼桁に剛接合によって固定し、この鋼桁からのみ支持した型枠内にコンクリートを打ち込み、これを硬化させることとしたので、凝結の進行に伴い鋼桁からコンクリートへの振動の伝達が確実に行われることとなり、その結果、振動を受ける鋼桁とコンクリートとが十分に付着することとなり、振動を受ける鋼桁とコンクリートとを一体化した複合構造が確実かつ十分に得られる。
【0012】
【発明の実施の形態】
以下、添付図面に基づいて本発明の実施の形態を詳細に説明する。
【0013】
なお、ここでは、鉄道4の仮設橋梁における振動する部材である鋼桁がコンクリートで被覆されることにより本設橋梁におけるコンクリート桁として使用される場合について説明するが、適用箇所は鉄道の構造物に限られるものではなく,振動する部材をコンクリートで被覆する場合にはすべて、本発明が効果をもたらす。例えば,道路の本設橋梁における振動する部材である鋼桁がコンクリートで被覆されることにより本設橋梁におけるコンクリート桁として使用される場合などでも、以下の説明が妥当する。
【0014】
[型枠の支持構造]
図1は本発明の一実施の形態に係る型枠の支持構造の全体構成を示す断面図、図2は同型枠の支持構造の概略構成を示す斜視図である。
【0015】
本実施の形態において、型枠の支持構造は、図1に示すように、現に供用されている鉄道4の仮設橋梁における振動する部材である主桁1a及び枕木受桁1bからなる鋼部材1をコンクリート3(図3(c)参照、以下同じ)で被覆するための型枠2を支持する目的に用いられる。
【0016】
以下、主桁1a、枕木受桁1b、型枠2、型枠の支持構造についてさらに詳細に説明する。
【0017】
(1)主桁1a
仮設橋梁においては、図1に示すように、鉄道車両(図示外)がレール41上を走行することにより生じた振動エネルギーが、レール41から枕木42、枕木受桁1b及び桁受用ブラケット51を通じて主桁1aへと伝達される。
【0018】
すなわち、主桁1aは、振動する部材として構成されている。
【0019】
加えて、主桁1aのうち後記する補強桁12は、本設橋梁においては、コンクリート桁において圧縮力には強いが引張力には弱いコンクリート3の弱点を補う役割を果たすものとして構成されている。
【0020】
すなわち、主桁1aがコンクリート3で被覆されることにより、両者間の付着力により一体化した複合構造である本設橋梁におけるコンクリート桁が構築されることとなっている。
【0021】
具体的には、この主桁1aは、同図に示すように、ほぼI形鋼からなる工事桁11と、下側フランジの幅の方が上側フランジの幅よりも大きいI形鋼からなり、工事桁11の下側にボルト接合される補強桁12とからなるものとして構成されている。
【0022】
(2)枕木受桁1b
仮設橋梁においては、図1に示すように、鉄道4車両がレール41上を走行することにより生じた振動エネルギーが、レール41から枕木42を通じて枕木受桁1bへと伝達される。
【0023】
すなわち、枕木受桁1bは、振動する部材として構成されている。
【0024】
加えて、枕木受桁1bは、本設橋梁においては、コンクリートスラブにおいて圧縮力には強いが引張力には弱いコンクリート3の弱点を補う役割を果たすものとして構成されている。
【0025】
すなわち、枕木受桁1bがコンクリート3で被覆されることにより、両者間の付着力により一体化した複合構造である本設橋梁におけるコンクリートスラブが構築されることとなっている。
【0026】
(3)型枠2
型枠2は、図1に示すように、主桁1a及び枕木受桁1bからなる鋼部材1をコンクリート3で被覆するために用いられるものであり、本設橋梁におけるコンクリート桁及びコンクリートスラブからなるコンクリート構造物の位置、形状及び寸法が正確に確保し得るよう配置されるものとして構成されている。
【0027】
すなわち、このような型枠2によれば、コンクリート3を打ち込むことにより、主桁1a及び枕木受桁1bからなる鋼部材1がコンクリート3で被覆されることとなり、これにより、所定の形状・寸法をもつ本設橋梁におけるコンクリート構造物がつくられることとなっている。
【0028】
具体的には、型枠2は、同図に示すように、桁用型枠21と、スラブ用型枠22と、勾配型枠23とからなっている。そして、桁用型枠21は、主桁1aの上部に対応して配置される上段型枠21aと、主桁1aの下部に対応して配置される下段型枠21bとからなっている。
ここで、桁用型枠21は、図2に示すように、異なる振動をする主桁1aの各部分別に切り離され、各部分によってのみ支持される各型枠片2aと、各型枠片2aどうしを連結するための伸縮継手24とからなることを特徴とする型枠の支持構造。
【0029】
一方、スラブ用型枠22は、枕木受桁1bによって支持されるものとして構成されている。
【0030】
(4)型枠の支持構造
本実施の形態において、型枠の支持構造は、主桁1a及び枕木受桁1bからなる鋼部材1をコンクリート3で被覆するための型枠2を支持する役割を果たすものとして構成されている。
【0031】
そして、この型枠の支持構造においては、型枠2は、鋼部材1によってのみ固定状態に支持されるものとして構成されている。換言すれば、この型枠の支持構造においては、型枠2は鋼部材1以外の部材によっては固定状態に支持されていないものとして構成されている。
【0032】
すなわち、一方では、桁用型枠21が、主桁1aによってのみ支持されている。
【0033】
また、他方では、スラブ用型枠22が、枕木受桁1bによってのみ支持されている。
【0034】
ここで、桁用型枠21の各型枠片2aは、異なる振動をする主桁1aの各部分によってのみ固定状態に支持されている。換言すれば、この型枠の支持構造においては、各型枠片2aは、異なる振動をする主桁1aの各部分以外の部分によっては固定状態に支持されていない。
【0035】
すなわち、型枠2は、鋼部材1に対して移動及び回転において拘束があることとなり、これにより、鉄道4車両の走行時に鋼部材1に伝達される振動エネルギーが型枠2にも伝達されることとなっている。
【0036】
具体的には、この型枠の支持構造は、上段型枠21aを工事桁11桁によってのみ支持するための工事桁用支持手段と、スラブ用型枠22を枕木受桁1bによってのみ支持するためのスラブ用支持手段と、下段型枠21bを補強桁12によってのみ支持するための補強桁用支持手段とを備えるものとして構成されている。
【0037】
工事桁用支持手段は、工事桁11の上側フランジに設けられ、上段型枠21aを支持するための工事桁用支持アーム61と、上段型枠21aから工事桁11側に張り出され、工事桁11によって支持されるための工事桁用被支持アーム71と、工事桁11から上段型枠21a側に張り出され、上段型枠21aを支持するための補強桁用支持アーム62と、上段型枠21aから工事桁11側に張り出され、工事桁11によって支持されるための補強桁用被支持アーム72とからなっている。
【0038】
また、このスラブ用支持手段は、枕木受桁1bの下側フランジに設けられ、スラブ用型枠22を支持するためのスラブ用支持アーム81と、スラブ用型枠22から枕木受桁1b側に張り出され、枕木受桁1bによって支持されるためのスラブ用被支持アーム91とからなっている。
【0039】
さらに、補強桁用支持手段は、補強桁12から下段型枠21b側に張り出され、下段型枠21bを支持するための補強桁用支持アーム62と、下段型枠21bから補強桁12側に張り出され、補強桁12によって支持されるための補強桁用被支持アーム72とからなっている。
【0040】
つまり、補強桁用支持手段によれば、上段型枠21a及び下段型枠21bを補強桁12に載置することが可能となっており、これにより、上段型枠21a及び下段型枠21bを補強桁12のみに支持させる施工の困難さが相当に解消されることとなり、その結果、迅速かつ安価な施工が担保されることとなっている。
【0041】
上記したように、このような型枠の支持構造によれば、振動を受ける鋼部材1をコンクリート3で被覆するための型枠2をその振動を受ける鋼部材1からのみ支持することとしているので、型枠2についても、鋼部材1と同様、振動を受けることとなり、その結果、鋼部材1と型枠2との振動差をかなり小さくできることとなっている。
【0042】
したがって、これによれば、型枠2内にコンクリート3を打ち込むと、凝結の進行に伴い鋼部材1からコンクリート3への振動の伝達が確実に行われることとなり、その結果、鋼部材1とコンクリート3とが十分に付着することとなり、振動を受ける鋼部材1とコンクリート3とを一体化した複合構造が確実かつ十分に得られる。
【0043】
[コンクリートの施工方法]
図3は本発明の一実施の形態に係るコンクリートの施工方法を説明する施工手順図である。
【0044】
本実施の形態において、コンクリートの施工方法は、上記したような型枠の支持構造を用いて行うものであり、現に供用されている鉄道4の仮設橋梁における主桁1aをコンクリート3で被覆する方法として構成されている。
【0045】
そして、このコンクリートの施工方法は、図3(a)に示す補強桁接合工程と、図3(b)に示す型枠2組立工程と、図3(c)に示すコンクリート打込工程との各工程により構成されている。以下、図3を用いて、各工程について説明する。
【0046】
(1)補強桁接合工程
これは、工事桁11の下側に対して補強桁12をボルト接合により取り付ける工程である。
【0047】
(2)型枠組立工程
これは、振動する鋼部材1をコンクリート3で被覆するための型枠2を組み立てる工程である。
【0048】
具体的には、補強桁用被支持アーム72のフックをあらかじめ補強桁用支持アーム62に固着したボルトに掛けることにより、加えて、工事桁用被支持アーム71を工事桁11の上側フランジに載置することにより、桁用型枠21が主桁1aに載置されることとなり、これにより、主桁1aに対して桁用型枠21が位置決めされることとなる。
【0049】
続いて、工事桁用被支持アーム71を工事桁用支持アーム61にボルトにより剛接合することにより、位置決めされている桁用型枠21が主桁1aによって固定状態に支持されることとなる。
【0050】
このとき、桁用型枠21が主桁1aに対して位置決めされている状態において、桁用型枠21を主桁1aに剛接合によって固定することが可能となっており、これにより、桁用型枠21を振動する主桁1aのみに支持させる施工の困難さが相当に解消される。
【0051】
一方、スラブ用被支持アーム91をスラブ用支持アーム81にボルトにより剛接合することにより、スラブ用型枠22が枕木受桁1bによって吊り下げられ固定状態に支持されることとなる。
【0052】
(3)コンクリート打込工程
これは、振動する鋼部材1によってのみ支持した型枠2内にコンクリート3を打ち込む工程である。
【0053】
具体的には、コンクリート3を型枠2の隅々まで充填しながら打ち込むことにより、コンクリート3の材料分離が防止されることとなり、これにより、耐久性及び水密性の高いコンクリート3が得られる。
本実施の形態においては、入念な締め固め作業が困難という施工上の制約条件があることから、コンクリート3としては、締め固めのほとんど必要ない高流動コンクリート又は締め固めの全く必要ない自己充填コンクリートを用いている。
【0054】
ここで、コンクリート打込工程は、打ち込んだコンクリート3を硬化させる工程を含むものとして構成されている。
【0055】
具体的には、打ち込んだコンクリート3は、凝結の進行に伴い鋼部材1からコンクリート3への振動の伝達が確実に行われることとなり、その結果、振動を受ける鋼部材1とコンクリート3とが十分に付着する。
【0056】
このようなコンクリートの施工方法により、振動を受ける鋼部材1とコンクリート3とを一体化した複合構造が得られることとなる。
【0057】
【発明の効果】
本発明によれば、振動を受ける鋼桁とコンクリートとが十分に付着することとなり、振動を受ける鋼桁とコンクリートとを一体化した複合構造が確実かつ十分に得られることとなる。
【図面の簡単な説明】
【図1】本発明の一実施の形態に係る型枠の支持構造の全体構成を示す断面図である。
【図2】本発明の一実施の形態に係る型枠の支持構造の概略構成を示す斜視図である。
【図3】本発明の一実施の形態に係るコンクリートの施工方法を説明する施工手順図である。
【符号の説明】
1 鋼部材
1a 主桁
1b 枕木受桁
2 型枠
2a 型枠片
3 コンクリート
4 鉄道
11 工事桁
12 補強桁
21 桁用型枠
21a 上段型枠
21b 下段型枠
22 スラブ用型枠
23 勾配型枠
24 伸縮継手
41 レール
42 枕木
51 桁受用ブラケット
61 工事桁用支持アーム
62 補強桁用支持アーム
71 工事桁用被支持アーム
72 補強桁用被支持アーム
81 スラブ用支持アーム
91 スラブ用被支持アーム[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a formwork support structure and a concrete construction method used when a steel girder subjected to vibration, such as a bridge girder in a currently used bridge, is covered with concrete.
[0002]
[Prior art]
As a conventional support structure of a formwork, for example, a support for supporting a formwork for covering a steel member as a main girder of a bridge with concrete, which is supported by the ground or the like is disclosed (for example, Non-Patent Document 1).
The support structure for this formwork has become the main girder of the bridge currently in use as the construction work has become more complex and sophisticated in recent years and the need to consider the impact on the surrounding environment has increased. It is also used when covering with concrete.
[0003]
[Non-Patent Document 1]
Civil Engineering Handbook I, 4th edition, Gihodo Publishing, November 20, 1993, p. 1246
[0004]
[Problems to be solved by the invention]
However, in the conventional support structure of the formwork, the main girder to be covered with concrete is subject to traffic vibration etc., whereas the formwork for covering the steel member receiving the vibration with concrete is Because it is supported by a fixed point such as the ground, the difference in vibration between the steel member and the formwork becomes large, and a composite structure in which the steel member and concrete that receive vibration are integrated cannot be obtained reliably and sufficiently. There is a problem.
That is, in the conventional support structure of the formwork, the formwork hardly vibrates and only the steel member vibrates, and even if concrete is driven into the formwork under such a situation, the steel member As a result, voids are generated in the vicinity of the steel sheet, and the necessary adhesion strength cannot be ensured between the steel member subjected to vibration and the concrete.
[0005]
Therefore, an object of the present invention is to provide a mold frame support structure capable of reducing a vibration difference between a steel girder and a formwork so that a composite structure in which a steel girder subjected to vibration and concrete are integrated is obtained reliably and sufficiently. It is to provide a concrete construction method.
[0006]
[Means for Solving the Problems]
In order to solve the above-mentioned problems, a support structure for a formwork according to the present invention includes a formwork for supporting a formwork for covering a steel girder that is vibrated by running of a vehicle with concrete in a currently used bridge. The support structure is characterized in that the formwork is fixed to a vibrating steel girder by rigid joining and supported only by the steel girder .
[0007]
Further, another formwork support structure according to the present invention is a formwork support structure for supporting a formwork for covering a steel girder that is vibrated by running a vehicle with concrete in a bridge currently in use. The molds are separated at predetermined intervals in the traveling direction of the vehicle, and are composed of each mold piece supported only by the steel girder in the vicinity of the separated position , and the adjacent formwork pieces expand and contract. It is characterized by being connected by a joint.
[0008]
According to the support structure of these formwork, the formwork for covering the steel girder that receives vibration with concrete is fixed to the steel girder that receives vibration by rigid joining, and is supported only from this steel girder . As with the steel girder , the mold is also subjected to vibration, and the vibration difference between the steel girder and the mold can be reduced.
[0009]
Therefore, according to this, when driving a concrete into the mold, will be transmission of vibration to the concrete is ensured from with steel girder with the progress of condensation, resulting, and the steel girder and concrete receiving vibrations It will adhere sufficiently, and a composite structure in which the steel girder subjected to vibration and concrete are integrated can be obtained reliably and sufficiently.
[0010]
On the other hand, in the concrete construction method according to the present invention, a steel girder that vibrates when the vehicle travels in a bridge currently in use is fixed with a rigid steel girder to cover the steel girder that is vibrated with concrete. It is characterized by driving concrete into a formwork that is only supported.
[0011]
According to this concrete construction method, it was fixed by rigid joining to a steel girder subjected to vibration, and the concrete was driven into a formwork supported only from this steel girder , and this was cured, so as the setting progressed The transmission of vibration from the steel girder to the concrete is surely performed. As a result, the steel girder subjected to vibration and the concrete adhere sufficiently, and the composite structure in which the steel girder subjected to vibration and the concrete are integrated. Is reliably and sufficiently obtained.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
[0013]
In addition, although the case where the steel girder which is a vibrating member in the temporary bridge of the railway 4 is used as a concrete girder in the permanent bridge by being covered with concrete is described here, the application point is a railway structure. The present invention is effective not only when the vibrating member is covered with concrete. For example, the following explanation is valid even when a steel girder, which is a vibrating member in a main bridge of a road, is used as a concrete girder in a main bridge by being covered with concrete.
[0014]
[Support structure of formwork]
FIG. 1 is a cross-sectional view showing an overall configuration of a support structure for a mold according to an embodiment of the present invention, and FIG. 2 is a perspective view showing a schematic configuration of the support structure for the mold.
[0015]
In the present embodiment, as shown in FIG. 1, the formwork support structure includes a steel member 1 composed of a
[0016]
Hereinafter, the
[0017]
(1)
In the temporary bridge, as shown in FIG. 1, vibration energy generated when a railway vehicle (not shown) travels on the
[0018]
That is, the
[0019]
In addition, the
[0020]
That is, when the
[0021]
Specifically, as shown in the figure, the
[0022]
(2)
In the temporary bridge, as shown in FIG. 1, the vibration energy generated when the railway 4 vehicle travels on the
[0023]
That is, the
[0024]
In addition, the
[0025]
That is, when the
[0026]
(3)
As shown in FIG. 1, the
[0027]
That is, according to such a
[0028]
Specifically, as shown in the figure, the
Here, as shown in FIG. 2, the
[0029]
On the other hand, the
[0030]
(4) Formwork support structure In the present embodiment, the formwork support structure serves to support the
[0031]
In this formwork support structure, the
[0032]
That is, on the other hand, the
[0033]
On the other hand, the
[0034]
Here, each
[0035]
That is, the
[0036]
Specifically, the support structure of this formwork is to support the construction girder support means for supporting the
[0037]
The work girder support means is provided on the upper flange of the
[0038]
The slab support means is provided on the lower flange of the
[0039]
Further, the reinforcing girder support means projects from the reinforcing
[0040]
That is, according to the support means for reinforcing girders, the
[0041]
As described above, according to such a support structure of the formwork, the
[0042]
Therefore, according to this, when the
[0043]
[Concrete construction method]
FIG. 3 is a construction procedure diagram for explaining a concrete construction method according to an embodiment of the present invention.
[0044]
In the present embodiment, the concrete construction method is performed using the above-described support structure of the formwork, and the
[0045]
And this concrete construction method includes each of the reinforcing girder joining step shown in FIG. 3 (a), the
[0046]
(1) Reinforcement girder joining process This is a process of attaching the
[0047]
(2) Formwork assembling step This is a step of assembling the
[0048]
Specifically, the construction beam supported
[0049]
Subsequently, the work girder supported
[0050]
At this time, in a state where the
[0051]
On the other hand, by rigidly joining the slab supported
[0052]
(3) Concrete placing step This is a step of placing concrete 3 into the
[0053]
Specifically, the
In the present embodiment, since there is a constructional constraint condition that careful compaction work is difficult, as the
[0054]
Here, the concrete placing step is configured to include a step of hardening the placed
[0055]
Specifically, the
[0056]
By such a concrete construction method, a composite structure in which the steel member 1 subjected to vibration and the
[0057]
【The invention's effect】
According to the present invention, the steel girder subjected to vibration and the concrete sufficiently adhere to each other, and a composite structure in which the steel girder subjected to vibration and the concrete are integrated is surely and sufficiently obtained.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view showing the overall structure of a mold frame support structure according to an embodiment of the present invention.
FIG. 2 is a perspective view showing a schematic configuration of a support structure for a mold according to an embodiment of the present invention.
FIG. 3 is a construction procedure diagram illustrating a concrete construction method according to an embodiment of the present invention.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1
Claims (3)
前記型枠は、前記鋼桁に剛接合によって固定され、該鋼桁によってのみ支持されていることを特徴とする型枠の支持構造。A formwork support structure for supporting a formwork for covering a steel girder that is vibrated by running of a vehicle with concrete in a bridge currently being used,
The formwork support structure, wherein the formwork is fixed to the steel beam by rigid joining and is supported only by the steel beam .
前記型枠は、前記車両の走行方向に所定間隔で切り離され、切り離された位置の近傍で前記鋼桁によってのみ支持される各型枠片からなり、
隣り合う前記型枠片どうしが伸縮継手で連結されていることを特徴とする型枠の支持構造。A formwork support structure for supporting a formwork for covering a steel girder that is vibrated by running of a vehicle with concrete in a bridge currently being used,
The mold is separated at predetermined intervals in the traveling direction of the vehicle, and includes each mold piece supported only by the steel girders in the vicinity of the separated position.
A support structure for a formwork, wherein the adjacent formwork pieces are connected by an expansion joint.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002339612A JP3759101B2 (en) | 2002-11-22 | 2002-11-22 | Formwork support structure and concrete construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002339612A JP3759101B2 (en) | 2002-11-22 | 2002-11-22 | Formwork support structure and concrete construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004169516A JP2004169516A (en) | 2004-06-17 |
| JP3759101B2 true JP3759101B2 (en) | 2006-03-22 |
Family
ID=32702527
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2002339612A Expired - Fee Related JP3759101B2 (en) | 2002-11-22 | 2002-11-22 | Formwork support structure and concrete construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3759101B2 (en) |
-
2002
- 2002-11-22 JP JP2002339612A patent/JP3759101B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004169516A (en) | 2004-06-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP5266291B2 (en) | Construction method of bridge deck and joint structure of precast deck | |
| JP3818020B2 (en) | Cross-section precast segment method | |
| CN112281663B (en) | Construction method for widening connection of upper structures of new and old bridges | |
| CN110387826A (en) | A segmental prefabricated assembled pier steel component and its construction method and application | |
| JP2008019687A (en) | Construction method of continuous girder bridge, composite floor slab and continuous girder bridge | |
| JP3880288B2 (en) | Precast segment and bridge girder forming method using the same | |
| KR101820871B1 (en) | Supporting device and bridge construction method using the same | |
| JP3759101B2 (en) | Formwork support structure and concrete construction method | |
| JP3566704B2 (en) | Reinforcement structure of existing railway bridge | |
| JP2023074802A (en) | Connection method and connection structure | |
| JP2000104221A (en) | Composite truss bridge and its erection method | |
| JP3322637B2 (en) | Construction method of cast-in-place concrete slab of bridge | |
| JP2021147884A (en) | Floor slab joint method and floor slab renewal method | |
| JP2004116060A (en) | Construction method of corrugated steel web bridge | |
| JP3788774B2 (en) | Railroad track structure and railroad track construction method | |
| JP3814286B2 (en) | Formwork support structure | |
| JP2004324245A (en) | Floating ladder sleeper, floating ladder track and laying method thereof | |
| JPH0892923A (en) | Guard fence | |
| JP3701936B2 (en) | Formwork support structure | |
| JP6670631B2 (en) | Support structure for columnar structures | |
| JPH1096209A (en) | Precast concrete slab, manufacturing method thereof, and structure for joining precast slab and girder | |
| JP5878316B2 (en) | Partial composite structure and partial composite structure method of steel bridge | |
| JPS63171906A (en) | Reinforcement method for bridge reinforced concrete slabs | |
| JPH09273117A (en) | Joint construction of floor slab | |
| JP2002364008A (en) | Large section synthetic arch tunnel and its construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050324 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050405 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050601 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050913 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20051109 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20051220 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20051227 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 3759101 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090113 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100113 Year of fee payment: 4 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100113 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110113 Year of fee payment: 5 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120113 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130113 Year of fee payment: 7 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130113 Year of fee payment: 7 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140113 Year of fee payment: 8 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |