Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP3867008B2 - Construction method of viaduct - Google Patents
[go: Go Back, main page]

JP3867008B2 - Construction method of viaduct - Google Patents

Construction method of viaduct Download PDF

Info

Publication number
JP3867008B2
JP3867008B2 JP2002122061A JP2002122061A JP3867008B2 JP 3867008 B2 JP3867008 B2 JP 3867008B2 JP 2002122061 A JP2002122061 A JP 2002122061A JP 2002122061 A JP2002122061 A JP 2002122061A JP 3867008 B2 JP3867008 B2 JP 3867008B2
Authority
JP
Japan
Prior art keywords
bridge girder
sliding
viaduct
underground space
view
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002122061A
Other languages
Japanese (ja)
Other versions
JP2003313823A (en
Inventor
正英 高宮
宏育 稲森
宏司 白谷
進次 室井
一浩 笠原
貴宏 佐竹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Nippon Steel Engineering Co Ltd
Original Assignee
Taisei Corp
Nippon Steel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, Nippon Steel Engineering Co Ltd filed Critical Taisei Corp
Priority to JP2002122061A priority Critical patent/JP3867008B2/en
Publication of JP2003313823A publication Critical patent/JP2003313823A/en
Application granted granted Critical
Publication of JP3867008B2 publication Critical patent/JP3867008B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、高架橋の斜路部と既設道路とを接続する摺付部の構築方法に特徴のある高架橋の構築方法に関する。
【0002】
【従来の技術】
従来、既設道路の平面交差部などにおいて、一方の既設道路を高架化する工事が多く行われている。このとき、既設道路と高架部とを結ぶ斜路部は、既設道路面上に構築されるため、斜路部の構築を開始した時点から高架化工事が終了する時点までの長期間に渡って大規模な交通規制を実施しなければならず、この交通規制に起因する渋滞が発生していた。
【0003】
このような背景の中、斜路部の構築に伴う交通規制に起因する渋滞を緩和すべく、図16に示すように、既設道路Rの上空に橋桁21を水平に張り出して架設した後に、橋桁21を所定の勾配に傾斜させて斜路部を構築する高架橋の構築方法が提案されている。
【0004】
かかる高架橋の構築方法によれば、橋桁21を傾斜させるまでは、橋桁21の下方に車両を通行させることができるので、大規模な交通規制は、橋桁21を傾斜させる短期間だけよく、したがって、斜路部の構築作業に伴う交通規制に起因する交通渋滞を大幅に緩和することができる。
【0005】
【発明が解決しようとする課題】
しかしながら、前記の高架橋の構築方法によっても、既設道路Rと橋桁21(斜路部)とを接続する摺付部22については、依然として既設道路R上に構築しなければならない。すなわち、摺付部22の構築を開始した時点から橋桁21を摺付部22に接続して高架橋20上に車両を走行させるまでは、距離は短いものの摺付部22を避けるための交通規制を実施しなければならい。例えば、図17に示すように、六車線(片側三車線)の既設道路Rの上空に四車線の橋桁21を架設する場合であれば、摺付部22は、当然に四車線分の幅を必要とするので、摺付部22付近については、片側一車線通行にせざるをえず、したがって、交通量の多いときには、摺付部22付近の交通規制に起因して渋滞が発生してしまう。
【0006】
そこで、本発明は、既設道路の上空に橋桁を架設した後に、当該橋桁を所定の勾配に傾斜させて斜路部を構築する高架橋の構築方法において、摺付部の構築に伴う交通規制に起因する渋滞を緩和することが可能な高架橋の構築方法を提供することを課題とする。
【0007】
【課題を解決するための手段】
このような課題を解決するために、請求項1の発明は、既設道路の上空に橋桁を架設した後に、当該橋桁を所定の勾配に傾斜させて斜路部を構築する高架橋の構築方法において、前記既設道路を掘り下げて形成した地下空間部の内部に前記橋桁の先端を降下させることで、前記斜路部と前記既設道路とを接続する摺付部を構築することを特徴とする高架橋の構築方法。
【0008】
かかる高架橋の構築方法は、既設道路を掘り下げて形成した地下空間部を利用して摺付部を構築するものである。この場合、摺付部の構築作業を行わないとき、もしくは、摺付部の構築作業が完了した後は、地下空間部を覆工板で覆うことで、覆工板上に車両を通行させることが可能で、したがって、摺付部の構築に伴う交通規制を大幅に減少させることができる。
【0009】
請求項2の発明は、既設道路の上空に橋桁を架設した後に、当該橋桁を所定の勾配に傾斜させて斜路部を構築する高架橋の構築方法において、前記既設道路を掘り下げて形成した地下空間部の内部で摺付用橋桁を組み立てた後、前記地下空間部の内部に前記摺付用橋桁を収納しておき、その後、前記摺付用橋桁を所定の勾配で傾斜させて、前記斜路部と前記既設道路とを接続する摺付部を構築することを特徴とする。
【0010】
かかる高架橋の構築方法は、既設道路を掘り下げて形成した地下空間の内部で摺付部となる摺付用橋桁を組み立てるとともに、摺付用橋桁を所定の勾配で傾斜させるまで、地下空間部の内部に摺付用橋桁を収納しておくものである。地下空間部を覆工板などで覆うことで、摺付用橋桁が車両の通行を妨げることがなくなり、したがって、摺付部の構築に伴う交通規制を大幅に減少させることができる。
【0011】
【発明の実施の形態】
本発明の実施の形態を添付した図面を参照しつつ、詳細に説明する。図1乃至図8は、本発明の高架橋の構築方法の手順を説明する図であり、各図とも、(a)に平面図を、(b)に側面図を示す。また、図9乃至図14は、地下空間部を拡大した図であり、各図とも、(a)に正面図を、(b)に側面図を示す。
【0012】
本発明に係る高架橋の構築方法は、図7に示すように、既設道路Rの上空に橋桁11,12を水平に架設した後に、橋桁11,12を所定の勾配に傾斜させて斜路部A2を構築する高架橋の構築方法において、既設道路Rを掘り下げて形成した地下空間部1を利用して斜路部A2と既設道路Rとを接続する摺付部A1を構築するものである。なお、以下では、六車線(片側三車線)の既設道路Rの中央の四車線(片側二車線)の上空に四車線の高架橋Aを構築する場合を例示する。
【0013】
(高架橋の構築手順)
図1に示すように、六車線の既設道路Rのうち、中央の二車線分を常設の作業帯R2として確保し、外側の車線R1,R1(各二車線)に車両を通行させるとともに、作業帯R2で杭S11を地中に打ち込む。次に、図9に示すように、杭S11上にフーチングS12、躯体S13、パラペットS14などを順次立ち上げて後述する摺付用橋桁2を支持するための橋台S1を高架橋区間の起点となる位置に構築する(図7参照)。同様に、橋桁11,12(図7参照)を支持するための橋脚S2,S3,S4及び斜張橋の主塔S5を所定の間隔をあけて構築する(図1,図2参照)。なお、橋台S1、橋脚S2〜S4および主塔S5の構造形式は、図示した構造形式に限定されることはなく、地盤条件その他を考慮して適宜最適な構造形式を採用することができる。
【0014】
次に、図3に示すように、夜間など交通量の少ない時間帯(以下、単に「夜間」と称する。)を利用して、車線R1,R1を最外側の一車線に規制して作業帯R2を拡幅した上で、土留壁1aを構築しつつ(図10(a)参照)、既設道路R(R1,R2)を掘り下げて、その内部で摺付用橋桁2を製作するための地下空間部1を構築する。地下空間部1は、後述する摺付用橋桁2を内部に収納可能な寸法・形状とする。また、土留壁1aは、現場打ちコンクリートで構築してもよいし、プレキャスト製のL型擁壁などで構築してもよい。
【0015】
地下空間部1の構築が完了した後、図4,図11に示すように、夜間に車線R1,R1を最外側の一車線に規制したうえで、地下空間部1の内部で摺付用橋桁2を組み立てる。摺付用橋桁2は、複数のブロック2aに分割された状態で搬入される。また、勾配の変化点では、縦断線形に緩和曲線を設ける必要があるので、摺付用橋桁2の上面の縦断形状を緩和曲線形状にしておくとよい。
【0016】
また、地下空間部1の構築作業および摺付用橋桁2の組立作業と並行して、床版10a,11aをそれぞれケーブル10b,11bで吊り下げつつ、主塔S5から順次水平に張り出して、高架部A3となる橋桁10および斜路部A2となる橋桁11を架設する(図7参照)。なお、勾配の変化点では、縦断線形に緩和曲線を設ける必要があるので、本実施形態では、橋桁11を傾斜させたときに所定の縦断線形になるように、緩和曲線形状を予め考慮したうえで橋桁11を架設する。すなわち、橋桁11は、完全な水平を保った状態で張り出されているわけではない。また、主塔S5と床版10aとの接続部は、上下方向に回転可能な構造に形成されている。
【0017】
なお、図5,図12に示すように、昼間など交通量の多い時間帯(以下、単に「昼間」と称する。)には、地下空間部1の開口部に覆工板3を覆設して片側二車線を確保する。また、夜間には、車線R1,R1を最外側の一車線に規制したうえで、覆工板3を撤去して作業を行う。このように、地下空間部1に覆工板3を適宜覆設することで、摺付用橋桁2(摺付部A1)を構築した後でも、常時交通規制を実施する必要がない。したがって、摺付部A1の構築作業に伴う交通規制を削減することが可能であり、交通規制に起因する交通渋滞を緩和することができる。
【0018】
次に、ベントB1,B3を橋脚S2,S3上に、ベントB2を橋脚S2,S3の中間にそれぞれ立設した後に(図5参照)、橋桁11の先端から床版12aを水平に張り出し、橋脚S2,S3上に橋桁12を構築する(図6,図12参照)。このとき、地下空間部1を覆工板3で覆っておけば、覆工板3上に作業機械を配置することもできる。
【0019】
橋桁12を所定位置まで水平に張り出して架設したら、図7に示すように、ワイヤ11bの長さ及びベントB1〜B3(図6参照)の高さを調節して、橋桁11,12を所定の勾配で傾斜させて斜路部A2を構築する。
【0020】
橋桁11,12を傾斜させる作業と並行して、図13に示すように、地下空間部1の両側にジャッキ5を装備した複数の重量台車4を配置するとともに、ジャッキ5,5の上面に吊ビーム6を架け渡す。そして、吊ビーム6から垂下するワイヤ7(図13(a)参照)を摺付用橋桁2に玉掛したうえで、摺付用橋桁2を吊り上げて移動させ、一端を橋台S1上に載置するとともに、他端側(斜路部側)をさらに吊り上げて摺付用橋桁2を所定の勾配に傾斜させる。最後に、橋桁12と摺付用橋桁2とを接続して、摺付部A1および斜路部A2の構築が完了する。
【0021】
その後、高架橋A上の舗装を行ったうえで、高架橋A上に車両を通行させる(図14参照)。また、地下空間部1の両側方には、防護柵1bを設置する。
【0022】
また、主塔S5およびケーブル10a,11aを仮設とする場合には、これを撤去するとともに、橋脚S4に橋桁11を受け替える(図8参照)。
【0023】
このように、摺付部A1となる摺付用橋桁2を地下空間部1の内部で組み立てるとともに、地下空間部1を適宜覆工板3で覆うことで、摺付部A1の構築に伴う交通規制を大幅に削減することができる。すなわち、従来の高架橋の構築方法のように既設道路R上に摺付部を構築してしまうと、摺付部付近では、交通量にかかわらず車線R1,R1を常に一車線に規制しなければならないが、本実施形態のように地下空間部1を利用して摺付用橋桁2(摺付部A1)を構築するとともに、交通量の多いときに地下空間部1を覆工板3で覆うことにより、摺付部A1付近でも二車線を確保することが可能で、したがって、交通渋滞を大幅に緩和することができる。
【0024】
また、摺付用橋桁2は、その組立完了後、所定の勾配で傾斜させるまでは、地下空間部1に完全に収納された状態になるので、高架橋Aの構築工程の早い時期に摺付用橋桁2を構築しても、摺付用橋桁2(摺付部A1)が通行の妨げになることはない。すなわち、摺付用橋桁2を地下空間部1の内部で構築することで、高架橋Aの構築工程の自由度が高まり、施工効率が向上する。
【0025】
なお、図15(a)に示すように、一端を橋台S1上に載置した状態で摺付用橋桁2を組み立ててもよく、この場合には、図15(b)に示すように、ジャッキ5を装備した重量台車4を橋脚S2側(斜路部側)だけに配置して摺付用橋桁2を持ち上げればよい。
【0026】
また、本実施形態では、ジャッキ5を備えた重量台車4を使用して摺付用橋桁2を所定の勾配に傾斜させたが、これに限定されることはなく、例えば、クレーンを使用して傾斜させてもよいし、摺付用橋桁2の下面に配置したジャッキを使用して傾斜させてもよい。これらは、施工条件などを考慮して適宜最適な方法を選択すればよい。
【0027】
さらに、本実施形態では、地下空間部1の内部で組み立てられた摺付用橋桁2を傾斜させることで摺付部A1を構築していたが、これに限定されることはなく、例えば、図示は省略するが、水平に張り出して架設された橋桁の先端を地下空間部内へ降下させ、直接に橋台S1上へ載置して摺付部A1としてもよい。
【0028】
また、水平に張り出される橋桁の架設方法、構造形式なども、図示のものに限定されことはない。また、本実施形態では、ベントB1〜B3を利用して橋桁12を水平に架設しているが、これに限定されることはなく、例えば、図16のように、斜路部となる橋桁の全てが斜張橋により構築されたものであってもよい。
【0029】
【発明の効果】
本発明に係る高架橋の構築方法によれば、既設道路を掘り下げて形成した地下空間部を利用して摺付部を構築するもので、摺付部の構築作業を行わないとき、もしくは、構築作業が完了した後は、地下空間部を覆工板で覆うことで、覆工板上に車両を通行させることが可能で、したがって、摺付部の構築に伴う交通規制に起因する交通渋滞を大幅に減少させることができる。
【図面の簡単な説明】
【図1】 (a)は本発明に係る高架橋の構築方法の手順を示す平面図、(b)は同じく側面図である。
【図2】 (a)は図1に続く手順を示す平面図、(b)は同じく側面図である。
【図3】 (a)は図2に続く手順を示す平面図、(b)は同じく側面図である。
【図4】 (a)は図3に続く手順を示す平面図、(b)は同じく側面図である。
【図5】 (a)は図4に続く手順を示す平面図、(b)は同じく側面図である。
【図6】 (a)は図5に続く手順を示す平面図、(b)は同じく側面図である。
【図7】 (a)は図6に続く手順を示す平面図、(b)は同じく側面図である。
【図8】 (a)は図7に続く手順を示す平面図、(b)は同じく側面図である。
【図9】 (a)は図2の地下空間部付近を示す正面図、(b)は同じく側面図である。
【図10】 (a)は図3の地下空間部付近を示す正面図、(b)は同じく側面図である。
【図11】 (a)は図4の地下空間部付近を示す正面図、(b)は同じく側面図である。
【図12】 (a)は図5の地下空間部付近を示す正面図、(b)は同じく側面図である。
【図13】 (a)は図7の地下空間部付近を示す正面図、(b)は同じく側面図である。
【図14】 (a)は図8の地下空間部付近を示す正面図、(b)は同じく側面図である。
【図15】 (a)は摺付用橋桁の他の構築方法を示す側面図、(b)は(a)に続く手順を説明する側面図である。
【図16】 従来の高架橋の構築方法を説明する側面図である。
【図17】 (a)(b)(c)は従来の高架橋の構築方法にける摺付部の構築手順を説明する図である。
【符号の説明】
1 地下空間部
2 摺付用橋桁
3 覆工板
4 重量台車
5 ジャッキ
A 高架橋
A1 摺付部
A2 斜路部
A3 高架部
S1 橋台
R 既設道路
R1 車線
R2 作業帯
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a viaduct that is characteristic of a method for constructing a slidable portion that connects a ramp portion of a viaduct and an existing road.
[0002]
[Prior art]
Conventionally, a lot of work has been done to elevate one existing road, such as at a plane intersection of an existing road. At this time, the ramp connecting the existing road and the elevated part is built on the existing road surface, so it is large-scale over a long period from the start of construction of the ramp to the end of the elevated work. Traffic regulations had to be implemented, and traffic jams were caused by these traffic regulations.
[0003]
In such a background, in order to alleviate the traffic jam caused by the traffic regulation accompanying the construction of the ramp section, as shown in FIG. 16, after the bridge girder 21 is horizontally extended over the existing road R, the bridge girder 21 is installed. A method for constructing a viaduct has been proposed in which a slope portion is constructed by inclining to a predetermined gradient.
[0004]
According to such a construction method of the viaduct, since the vehicle can be passed under the bridge girder 21 until the bridge girder 21 is tilted, large-scale traffic regulation is only required for a short period during which the bridge girder 21 is tilted. Traffic congestion caused by traffic restrictions associated with the construction work of the ramp can be greatly eased.
[0005]
[Problems to be solved by the invention]
However, even with the construction method of the viaduct described above, the sliding portion 22 that connects the existing road R and the bridge girder 21 (slope portion) must still be constructed on the existing road R. That is, from the time when construction of the sliding portion 22 is started, until the bridge girder 21 is connected to the sliding portion 22 and the vehicle is driven on the viaduct 20, traffic regulation for avoiding the sliding portion 22 although the distance is short. Must be implemented. For example, as shown in FIG. 17, when a four-lane bridge girder 21 is installed above the existing road R of six lanes (three lanes on one side), the sliding portion 22 naturally has a width corresponding to four lanes. Since it is necessary, the vicinity of the slidable portion 22 has to be one-lane traffic on one side. Therefore, when there is a large amount of traffic, traffic congestion occurs due to traffic restrictions in the vicinity of the slidable portion 22.
[0006]
Accordingly, the present invention is, after rack set the bridge girder in high over the existing roads, in method for constructing a viaduct which is inclined the bridge girder to the predetermined gradient to build ramp portion, due to traffic restrictions due to the construction of the sliding mounting portion It is an object of the present invention to provide a method for constructing a viaduct that can alleviate traffic congestion.
[0007]
[Means for Solving the Problems]
To solve such problems, a first aspect of the present invention, after the call set the bridge girder in high over the existing roads, in method for constructing a viaduct which is inclined the bridge girder to the predetermined gradient to build ramp portion, A method for constructing a viaduct characterized by constructing a sliding portion connecting the ramp and the existing road by lowering the end of the bridge girder inside an underground space formed by digging down the existing road .
[0008]
Such a viaduct construction method is to construct a sliding portion using an underground space formed by digging down an existing road. In this case, when the construction work of the sliding part is not performed, or after the construction work of the sliding part is completed, the vehicle is allowed to pass on the lining board by covering the underground space part with the lining board. Therefore, it is possible to greatly reduce traffic restrictions associated with the construction of the sliding portion.
[0009]
According to a second aspect of the present invention, there is provided a viaduct construction method in which a bridge girder is installed over the existing road, and then the bridge girder is inclined to a predetermined slope to construct a ramp section . The underground space formed by digging down the existing road After assembling the sliding bridge girder, the sliding bridge girder is stored inside the underground space, and then the sliding bridge girder is inclined with a predetermined gradient, A sliding portion connecting the existing road is constructed.
[0010]
Such a viaduct construction method assembles a sliding bridge girder that becomes a sliding portion inside an underground space formed by digging down an existing road, and the inside of the underground space portion until the sliding bridge girder is inclined at a predetermined gradient. The bridge girder for sliding is stored. By covering the underground space with a lining board or the like, the sliding bridge girder does not hinder the passage of the vehicle, and therefore traffic regulations associated with the construction of the sliding portion can be greatly reduced.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described in detail with reference to the accompanying drawings. 1 to 8 are diagrams for explaining the procedure of the method for constructing a viaduct of the present invention. In each figure, (a) is a plan view and (b) is a side view. Moreover, FIG. 9 thru | or FIG. 14 is the figure which expanded the underground space part, and each figure shows a front view in (a) and a side view in (b).
[0012]
As shown in FIG. 7, the method for constructing a viaduct according to the present invention is as follows. After the bridge girders 11 and 12 are installed horizontally over the existing road R, the bridge girders 11 and 12 are inclined to a predetermined slope to form the ramp portion A <b> 2. In the construction method of the viaduct to be constructed, the sliding portion A1 that connects the ramp portion A2 and the existing road R is constructed using the underground space portion 1 formed by digging down the existing road R. In the following, a case where a four-lane viaduct A is constructed over the center four lanes (one lane two lanes) of the existing road R of six lanes (one lane three lanes) will be exemplified.
[0013]
(Procedure for construction of viaduct)
As shown in FIG. 1, among the existing roads R of six lanes, the middle two lanes are secured as permanent work zones R2, and vehicles are allowed to pass through the outer lanes R1 and R1 (each two lanes). The pile S11 is driven into the ground with the band R2. Next, as shown in FIG. 9, the footing S <b> 12, the frame S <b> 13, the parapet S <b> 14, etc. are sequentially raised on the pile S <b> 11 and the abutment S <b> 1 for supporting the sliding bridge girder 2 described later is the starting point of the viaduct section. (See FIG. 7). Similarly, the piers S2, S3, S4 and the main tower S5 of the cable-stayed bridge for supporting the bridge girders 11, 12 (see FIG. 7) are constructed at predetermined intervals (see FIGS. 1 and 2). The structural form of the abutment S1, the piers S2 to S4, and the main tower S5 is not limited to the illustrated structural form, and an optimal structural form can be appropriately adopted in consideration of ground conditions and the like.
[0014]
Next, as shown in FIG. 3, the lanes R1 and R1 are restricted to the outermost lane using a time zone with a low traffic volume such as nighttime (hereinafter simply referred to as “nighttime”). An underground space for digging down the existing road R (R1, R2) and producing the sliding bridge girder 2 inside it while building the retaining wall 1a after widening R2 (see FIG. 10 (a)) Build part 1. The underground space 1 has dimensions and a shape that can accommodate a sliding bridge girder 2 described later. Moreover, the earth retaining wall 1a may be constructed with cast-in-place concrete, or may be constructed with a precast L-shaped retaining wall or the like.
[0015]
After the construction of the underground space part 1 is completed, as shown in FIGS. 4 and 11, the lanes R1 and R1 are restricted to one outermost lane at night, and then the sliding bridge girder inside the underground space part 1 Assemble 2 The sliding bridge girder 2 is carried in a state of being divided into a plurality of blocks 2a. Moreover, since it is necessary to provide a relaxation curve in the vertical alignment at the change point of the gradient, it is preferable that the vertical profile on the upper surface of the sliding bridge girder 2 be a relaxation curve shape.
[0016]
In parallel with the construction work for the underground space 1 and the assembly work for the sliding bridge girder 2, the floor slabs 10 a and 11 a are respectively suspended from the main tower S 5 while being suspended by the cables 10 b and 11 b, and are elevated. A bridge girder 10 serving as a part A3 and a bridge girder 11 serving as a ramp part A2 are installed (see FIG. 7). In addition, since it is necessary to provide a relaxation curve in a longitudinal line at the change point of the gradient, in this embodiment, the relaxation curve shape is considered in advance so that a predetermined longitudinal line shape is obtained when the bridge girder 11 is inclined. The bridge girder 11 is installed. That is, the bridge girder 11 is not overhanged in a state of being kept completely horizontal. Moreover, the connection part of the main tower S5 and the floor slab 10a is formed in the structure which can rotate to an up-down direction.
[0017]
As shown in FIGS. 5 and 12, a cover plate 3 is placed over the opening of the underground space 1 in a time zone with a heavy traffic volume such as daytime (hereinafter simply referred to as “daytime”). Secure two lanes on one side. Further, at night, the lanes R1 and R1 are restricted to one outermost lane, and then the lining plate 3 is removed to perform the work. Thus, even if the sliding bridge girder 2 (sliding portion A1) is constructed by appropriately covering the lining plate 3 in the underground space portion 1, it is not necessary to always carry out traffic regulation. Therefore, it is possible to reduce traffic restrictions associated with the construction work of the sliding portion A1, and it is possible to alleviate traffic congestion caused by traffic restrictions.
[0018]
Next, after the vents B1 and B3 are erected on the piers S2 and S3 and the vent B2 is erected between the piers S2 and S3 (see FIG. 5), the floor slab 12a is horizontally projected from the end of the bridge girder 11, A bridge girder 12 is constructed on S2 and S3 (see FIGS. 6 and 12). At this time, if the underground space 1 is covered with the lining plate 3, the work machine can be arranged on the lining plate 3.
[0019]
When the bridge girder 12 is horizontally extended to a predetermined position and installed, as shown in FIG. 7, the length of the wire 11b and the height of the vents B1 to B3 (see FIG. 6) are adjusted to The ramp A2 is constructed by inclining with a gradient.
[0020]
In parallel with the operation of inclining the bridge girders 11 and 12, as shown in FIG. 13, a plurality of heavy trucks 4 equipped with jacks 5 are arranged on both sides of the underground space portion 1 and suspended on the upper surfaces of the jacks 5 and 5. Cross the beam 6. Then, after hanging the wire 7 (see FIG. 13A) hanging from the suspension beam 6 on the sliding bridge girder 2, the sliding bridge girder 2 is lifted and moved, and one end is placed on the abutment S1. At the same time, the other end side (slope portion side) is further lifted to incline the sliding bridge girder 2 to a predetermined gradient. Finally, the bridge girder 12 and the sliding bridge girder 2 are connected to complete the construction of the sliding portion A1 and the ramp portion A2.
[0021]
Then, after paving on the viaduct A, the vehicle passes on the viaduct A (see FIG. 14). In addition, protective fences 1b are installed on both sides of the underground space 1.
[0022]
When the main tower S5 and the cables 10a and 11a are temporary, they are removed and the bridge girder 11 is replaced with the pier S4 (see FIG. 8).
[0023]
Thus, while assembling the sliding bridge girder 2 to be the sliding portion A1 inside the underground space portion 1 and covering the underground space portion 1 with the lining plate 3 as appropriate, traffic accompanying the construction of the sliding portion A1 Regulations can be greatly reduced. That is, if a sliding part is constructed on the existing road R as in the conventional viaduct construction method, the lanes R1 and R1 must always be restricted to one lane near the sliding part regardless of the traffic volume. Although it does not become, while constructing the bridge girder 2 for sliding (sliding part A1) using the underground space part 1 like this embodiment, the underground space part 1 is covered with the lining board 3 when there is much traffic. As a result, it is possible to secure two lanes near the sliding portion A1, and therefore, traffic congestion can be greatly reduced.
[0024]
Further, since the sliding bridge girder 2 is completely stored in the underground space 1 until it is inclined at a predetermined gradient after its assembly is completed, it is used for sliding at an early stage of the construction process of the viaduct A. Even if the bridge girder 2 is constructed, the sliding bridge girder 2 (sliding portion A1) does not hinder traffic. That is, by constructing the sliding bridge girder 2 inside the underground space 1, the degree of freedom in the construction process of the viaduct A is increased, and the construction efficiency is improved.
[0025]
As shown in FIG. 15A, the sliding bridge girder 2 may be assembled with one end placed on the abutment S1, and in this case, as shown in FIG. The heavy truck 4 equipped with 5 is arranged only on the pier S2 side (slope part side) and the sliding bridge girder 2 is lifted.
[0026]
In the present embodiment, the sliding bridge girder 2 is inclined to a predetermined slope using the heavy truck 4 provided with the jack 5, but the present invention is not limited to this. For example, a crane is used. You may make it incline, and you may incline it using the jack arrange | positioned on the lower surface of the bridge girder 2 for sliding. For these, an optimum method may be selected as appropriate in consideration of construction conditions and the like.
[0027]
Furthermore, in this embodiment, although the sliding part A1 was constructed | assembled by inclining the sliding bridge girder 2 assembled inside the underground space part 1, it is not limited to this, For example, illustration Is omitted, but the tip of the bridge girder that extends horizontally may be lowered into the underground space and placed directly on the abutment S1 to form the sliding portion A1.
[0028]
Further, the construction method and the structure type of the bridge girder extending horizontally are not limited to those shown in the drawing. Moreover, in this embodiment, although the bridge girder 12 is installed horizontally using vent B1-B3, it is not limited to this, For example, as shown in FIG. 16, all the bridge girders used as a ramp part are shown. May be constructed by a cable-stayed bridge.
[0029]
【The invention's effect】
According to the construction method of the viaduct according to the present invention, the sliding portion is constructed using the underground space formed by digging down the existing road, and when the construction operation of the sliding portion is not performed, or the construction work After completing the above, it is possible to pass the vehicle on the lining plate by covering the underground space with the lining plate, and thus greatly reduce the traffic congestion caused by the traffic regulation accompanying the construction of the sliding part. Can be reduced.
[Brief description of the drawings]
FIG. 1A is a plan view showing a procedure of a method for constructing a viaduct according to the present invention, and FIG.
2A is a plan view showing a procedure following FIG. 1, and FIG. 2B is a side view of the same.
3A is a plan view showing a procedure following FIG. 2, and FIG. 3B is a side view of the same.
4A is a plan view showing a procedure following FIG. 3, and FIG. 4B is a side view of the same.
5A is a plan view showing a procedure following FIG. 4, and FIG. 5B is a side view of the same.
6A is a plan view showing a procedure following FIG. 5, and FIG. 6B is a side view of the same.
7A is a plan view showing a procedure following FIG. 6, and FIG. 7B is a side view of the same.
8A is a plan view showing a procedure following FIG. 7, and FIG. 8B is a side view of the same.
9A is a front view showing the vicinity of the underground space in FIG. 2, and FIG. 9B is a side view of the same.
10A is a front view showing the vicinity of the underground space in FIG. 3, and FIG. 10B is a side view of the same.
11A is a front view showing the vicinity of the underground space in FIG. 4, and FIG. 11B is a side view of the same.
12A is a front view showing the vicinity of the underground space in FIG. 5, and FIG. 12B is a side view of the same.
13A is a front view showing the vicinity of the underground space in FIG. 7, and FIG. 13B is a side view of the same.
14A is a front view showing the vicinity of the underground space in FIG. 8, and FIG. 14B is a side view of the same.
FIG. 15A is a side view showing another construction method of a sliding bridge girder, and FIG. 15B is a side view explaining a procedure following (a).
FIG. 16 is a side view illustrating a conventional method for constructing a viaduct.
FIGS. 17A, 17B, and 17C are diagrams for explaining a construction procedure of a sliding portion in a conventional viaduct construction method.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Underground space part 2 Bridge girder for sliding 3 Covering board 4 Heavy truck 5 Jack A Viaduct A1 Sliding part A2 Slope part A3 Overpass part S1 Abutment R Existing road R1 Lane R2 Work zone

Claims (2)

既設道路の上空に橋桁を架設した後に、当該橋桁を所定の勾配に傾斜させて斜路部を構築する高架橋の構築方法において、前記既設道路を掘り下げて形成した地下空間部の内部に前記橋桁の先端を降下させることで、前記斜路部と前記既設道路とを接続する摺付部を構築することを特徴とする高架橋の構築方法。After rack set the bridge girder in high over the existing roads, by inclining the bridge girder to the predetermined gradient in method for constructing a viaduct building a ramp portion, of the bridge girder in the interior of the existing underground space portion formed by digging a road A method for constructing a viaduct characterized by constructing a sliding portion that connects the ramp portion and the existing road by lowering the tip . 既設道路の上空に橋桁を架設した後に、当該橋桁を所定の勾配に傾斜させて斜路部を構築する高架橋の構築方法において、前記既設道路を掘り下げて形成した地下空間部の内部で摺付用橋桁を組み立てた後、前記地下空間部の内部に前記摺付用橋桁を収納しておき、その後、前記摺付用橋桁を所定の勾配で傾斜させて、前記斜路部と前記既設道路とを接続する摺付部を構築することを特徴とする高架橋の構築方法。 In a construction method of a viaduct in which a bridge girder is constructed with a predetermined slope after a bridge girder is installed over the existing road , a sliding girder is built inside an underground space formed by digging down the existing road. The sliding bridge girder is stored inside the underground space, and then the sliding bridge girder is inclined with a predetermined gradient to connect the ramp portion and the existing road. how to build a highly crosslinked you characterized by constructing a sliding toothed portion.
JP2002122061A 2002-04-24 2002-04-24 Construction method of viaduct Expired - Fee Related JP3867008B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002122061A JP3867008B2 (en) 2002-04-24 2002-04-24 Construction method of viaduct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002122061A JP3867008B2 (en) 2002-04-24 2002-04-24 Construction method of viaduct

Publications (2)

Publication Number Publication Date
JP2003313823A JP2003313823A (en) 2003-11-06
JP3867008B2 true JP3867008B2 (en) 2007-01-10

Family

ID=29537778

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002122061A Expired - Fee Related JP3867008B2 (en) 2002-04-24 2002-04-24 Construction method of viaduct

Country Status (1)

Country Link
JP (1) JP3867008B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111578989B (en) * 2020-05-06 2022-06-10 中铁第四勘察设计院集团有限公司 Exploration method of fault confined water bridge abutment and bridge abutment erection method
CN117536111A (en) * 2023-11-17 2024-02-09 中建三局集团有限公司 Construction method for urban overhead ramp reconstruction

Also Published As

Publication number Publication date
JP2003313823A (en) 2003-11-06

Similar Documents

Publication Publication Date Title
JP2003253623A (en) Bridge girder replacement method
CN115748483A (en) Pile-pier-beam integrated bridge fabrication machine construction method
JP4343606B2 (en) Bridge construction method
US20100272509A1 (en) Traffic barrier section
JP3867008B2 (en) Construction method of viaduct
JP4685341B2 (en) Viaduct construction method
JP4671912B2 (en) Bridge replacement method
JP2005090108A (en) Bridge erection method
JP4263935B2 (en) Construction method and elevated detour
JP4280208B2 (en) Viaduct replacement method
JP4037855B2 (en) Road bridge erection method
CN115748489B (en) A method for building a new viaduct on an existing bridge
JP4098581B2 (en) Overpass bridge construction method
JP2004278230A (en) Road grade crossing construction method and pier connection structure
JP2004285799A (en) Construction method for bridge side span of overpass
JP3940587B2 (en) Construction method of divided bridge type traffic route
JP3619515B2 (en) Split-bridge type traffic road and method for constructing split-bridge type traffic road
JP3779978B2 (en) Elevated traffic route
JP2007277996A (en) Three-dimensional viaduct approach section construction method and three-dimensional viaduct approach section structure
JP2004169318A (en) Construction method of viaduct pier
JP2005090109A (en) Bridge erection method and bridge superstructure unit
JP4519588B2 (en) Three-dimensional intersection construction method
JPS60258311A (en) Construction of high structure
JPH11293628A (en) Hung scaffold assembling method for bridge
KR102595013B1 (en) Construction Method of Underground Road to Minimize Traffic Control

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040402

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060410

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060419

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060607

TRDD Decision of grant or rejection written
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20060804

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060927

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20061006

R150 Certificate of patent or registration of utility model

Ref document number: 3867008

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091013

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313122

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091013

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101013

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101013

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101013

Year of fee payment: 4

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101013

Year of fee payment: 4

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101013

Year of fee payment: 4

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101013

Year of fee payment: 4

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111013

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121013

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131013

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees