Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP4069729B2 - Road tunnel floor slab formation method - Google Patents
[go: Go Back, main page]

JP4069729B2 - Road tunnel floor slab formation method - Google Patents

Road tunnel floor slab formation method Download PDF

Info

Publication number
JP4069729B2
JP4069729B2 JP2002341692A JP2002341692A JP4069729B2 JP 4069729 B2 JP4069729 B2 JP 4069729B2 JP 2002341692 A JP2002341692 A JP 2002341692A JP 2002341692 A JP2002341692 A JP 2002341692A JP 4069729 B2 JP4069729 B2 JP 4069729B2
Authority
JP
Japan
Prior art keywords
floor slab
road tunnel
tunnel
forming
road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002341692A
Other languages
Japanese (ja)
Other versions
JP2004176322A (en
Inventor
一彦 的場
健太 松原
実 畠山
正夫 中山
寛 相良
和敏 向坂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2002341692A priority Critical patent/JP4069729B2/en
Publication of JP2004176322A publication Critical patent/JP2004176322A/en
Application granted granted Critical
Publication of JP4069729B2 publication Critical patent/JP4069729B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【0001】
【発明の属する技術分野】
この発明は、道路トンネルの床版形成方法に関し、特に、シールド工法で道路トンネルを構築する際の床版の形成方法に関するものである。
【0002】
【従来の技術】
道路トンネルを構築する場合、道路トンネルの内部に自動車の走行を可能にするための床版を形成する必要があり、この種の床版は、図7に示すように、通常、構築しようとする道路トンネル1の中心よりも下方に位置し、断面を横断するように延設される概略平板状の床版部2と、床版部2の両端を支持し、道路トンネル1の側部に固設される一対の側壁部3と、下端が道路トンネル1の底部に定着され、床版部2の中央を下方から支持する中柱部4とを備えている。
【0003】
ところで、このような断面形状の道路トンネルを構築する工法の一種として、シールド工法が知られている。シールド工法により道路トンネルを構築する際には、文献に開示されているか否かは知らないが、実施工現場では、一般に、前述した床版は、現場打ちコンクリートにより形成していた。
【0004】
しかしながら、このような従来の道路トンネルの床版形成方法には、以下に説明する課題があった。
【0005】
【発明が解決しようとする課題】
すなわち、床版部2,側壁部3,中柱部4を備えた床版を現場打ちで施工する際には、型枠を組み、鉄筋を組立て、コンクリートの打設、養生という工程を経るので、施工に時間がかかり、コストもかかる。
【0006】
また、床版を現場打ちで施工する際には、セグメントなどの資材運搬を伴う掘削作業との同時施工を可能にするために、資材運搬用の車両が走行するレールを設ける枕木の高さ位置は、コンクリート打設用のセントル型枠の高さ、および、コンクリートの均しなどの施工性を考慮して、道路トンネル1の中心よりも若干上方になるように設定していた。
【0007】
つまり、床版を現場打ちで施工する場合には、道路トンネル1の概略下半分で床版の現場打設を行い、概略上半分で掘削作業用の資材運搬を行っていたが、枕木の高さを高くすると、資材および運搬車両などの重量を支持するために大掛かりなものとなり、設置および撤去が高所作業となり、時間とコストがかかるという問題があった。
【0008】
本発明は、このような従来の問題点に鑑みてなされたものであって、その目的とするところは、施工時間の短縮とコストの低減が図れる道路トンネルの床版形成方法を提供することにある。
【0009】
【課題を解決するための手段】
上記目的を達成するために、本発明は、掘削面にセグメントを環状に組立てるシールド工法により道路トンネルを構築する際に、構築途中の前記道路トンネルの抗口側から切羽側に向けて床版を形成する方法であって、前記床版は、前記道路トンネルの中心よりも下方に位置し、当該道路トンネルの横断面を横断するように延設される概略平板状の床版部と、前記床版部の両端を支持し、前記道路トンネルの側部に固設される一対の側壁部と、下端が前記道路トンネルの底部に定着され、前記床版部の中央を下方から支持する中柱部とを備え、前記床版は、予め所定形状に形成されるプレキャスト部材から構成され、前記床版の構築可能な空間をあけて、掘削作業に必要な資材運搬用車両の走行が可能なレールを前記道路トンネルの底部に敷設するとともに、前記レールの外側に床版設置台車の走行が可能なガイドレールを敷設し、前記床版設置台車による前記床版の設置作業と、前記資材運搬用車両による掘削作業に必要な資材の運搬とを同時進行可能にするようにした
【0010】
このように構成した道路トンネルの床版形成方法によれば、床版は、予め所定形状に形成されるプレキャスト部材から構成されるので、床版を現場打ちコンクリートで形成する場合よりも、現場での施工時間が短くなり、施工能率も向上する。
【0011】
また、掘削作業に必要な資材運搬用車両の走行が可能なレールは、床版の構築可能な空間をあけて、道路トンネルの底部に敷設するので、大掛かりな支持構造が不要になり、設置および撤去も簡単に行える。
【0012】
前記レールは、前記中柱部の構築予定個所を中心にして、その両側に一対を設けることができる。
【0014】
前記床版は、前記一対の側壁部を前記トンネルの側部に固設した後に、前記中柱部の下端を前記道路トンネルの底部に立設し、しかる後に、前記側壁部に両端を載置するとともに、前記中柱部の上端に中央部を当接させて前記床版部を設置することができる。
【0015】
【発明の実施の形態】
以下、本発明の好適な実施の形態について、添付図面に基づいて詳細に説明する。図1から図6は、本発明にかかる道路トンネルの床版形成方法の一実施例を示している。
【0016】
同図に示した道路トンネル10は、図示省略のシールド掘進機で地山を掘削し、掘削された面にセグメントを環状に組立てることにより、トンネル形状が維持される。
【0017】
このようなシールド工法で道路トンネル10を構築する際には、切羽側でシールド掘進機の掘削作業と、同時進行的に、構築された道路トンネル10の抗口側から床版12が順次形成される。
【0018】
本実施例の場合、床版12は、図6にその詳細を示すように、床版部12aと、一対の側壁部12bと、中柱部12cとを備えている。床版部12aは、所定の厚みを有する概略平板状に形成されており、本実施例の場合、道路トンネル10の横断面内において、トンネル10の中心よりも下方に位置し、かつ、トンネル10の断面を横断するように延設され、この形態で道路トンネル10の総延長に亘って形成される。
【0019】
一対の側壁部12bは、道路トンネル10の側面に対向するように配置され、概略直角三角形状に形成されている。各側壁部12bの直角三角形の斜辺には、曲率が道路トンネル10の内面に密着する湾曲部が形成され、この湾曲部を道路トンネル10の側部に固設して、その上部側に床版部12aの両端を載置することで、床版部12aの両端を支持し、この形態で道路トンネル10の総延長に亘って形成される。
【0020】
中柱部12cは、下端が道路トンネル10の底部に定着されて、床版部12aの中央を下方から支持するものであり、この中柱部12cは、道路トンネル10の軸方向に沿って、所定の間隔を隔てて多数が立設配置される。
【0021】
このような床版部12a,側壁部12b,中柱部12cからなる床版12は、予め工場生産などにより所定形状、および、所定長さに形成されるプレキャスト部材から構成されている。本実施例の場合、床版部12aと側壁部12bは、同じ長さに設定され、中柱部12cは、この長さに対応する複数本が1セットとなる。
【0022】
床版12を道路トンネル10に形成する際には、図1に示すように、床版12の構築可能な空間をあけて、掘削作業に必要な資材運搬用車両14の走行が可能なレール16を道路トンネル10の底部に敷設している。
【0023】
本実施例の場合、レール16は、2台の車両14が走行できるように、枕木18上に所定の間隔を隔てて、4条配置されている。枕木18の中央部分には、撤去することにより、その部分に中柱部12cの設置が可能な分割部20が設けられている。
【0024】
床版12を形成する際には、本実施例の場合には、レール16の外側に敷設されたガイドレール22上を走行する床版設置台車24を用いて行われる。床版設置台車24は、下端にガイドレール22上を転動する車輪が設けられた門型台車本体24aを有している。
【0025】
台車本体24aの側部には、側壁部12bを吊下げるための吊金具24bが設けらた吊天秤24dが設置されている。また、台車本体24aの上部側には、床版部12aないしは中柱部12cを吊下げるためのホイスト24cが設けられている。
【0026】
道路トンネル10に床版12を形成する際には、まず、図1,2に示すように、一対の側壁部12bが床版設置台車24の吊金具24bに取り付けられて、設置場所まで運搬して、道路トンネル10の側部に固設される。
【0027】
この場合、図1に示すように、予め、道路トンネル10のセグメントの所定位置に、側壁部12bの係止金具26を設けておくと、側壁部12bの位置決めおよび固設が簡単に行える。
【0028】
側壁部12bの所定位置への設置が終了すると、次に、図3に示すように、ホイスト24cに中柱部12cを取り付けて、これを道路トンネル10の底部に立設する。
【0029】
この際には、枕木18の分割部20を撤去するともに、中柱部12cの下端は、例えば、無収縮コンクリート28により、道路トンネル10の底部に固設され、これにより中柱部12cが立設状態に設置される。
【0030】
中柱部12cの立設設置は、トンネル軸方向に沿って複数本が所定の間隔を隔てて行われ、この設置が終了すると、次に、図4に示すように、ホイスト24cに床版部12aを取り付けて、吊り上げて、側壁部12b上に両端側を載置し、かつ、中柱部12cの上端が中央部下面に当接させるようにして、これを設置する。
【0031】
以上の工程により、図5に示すように、床版部12a,側壁部12b,中柱部12cからなる所定長さの床版12が形成され、その後は、先述した工程を順次繰り返すことで、床版12が切羽側に延設されることになる。
【0032】
なお、側壁部12bに両端を載置した床版部12aは、側壁部12bの外周を覆う仕上げコンクリート層を形成することで、一体化され、最終的には、図6に示した構造と同じ状態になる。
【0033】
さて、以上のように構成した道路トンネルの床版形成方法によれば、床版12は、予め所定形状に形成されるプレキャスト部材から構成されるので、床版12を現場打ちコンクリートで形成する場合よりも、現場での施工時間が短くなり、施工能率も向上する。
【0034】
しかも、本実施例の場合には、掘削作業に必要な資材、例えば、セグメントを搬送する資材搬送車両14は、床版12の形成作業に影響されることなく、走行できるので、掘削作業と床版形成作業とを同時進行させることができ、この点からも施工能率の向上が図れる。
【0035】
また、掘削作業に必要な資材運搬用車両14の走行が可能なレール16は、床版12の構築可能な空間をあけて、道路トンネル10の底部に敷設するので、大掛かりな支持構造が不要になり、設置および撤去も簡単に行える。
【0036】
【発明の効果】
以上、詳細に説明したように、本発明にかかる道路トンネルの床版形成方法によれば、施工時間の短縮とコストの低減が図れる。
【図面の簡単な説明】
【図1】本発明にかかる道路トンネルの床版形成方法の初期工程の断面説明図である。
【図2】図1に示した工程に引き続いて行われる肯定の説明図である。
【図3】図2に示した工程に引き続いて行われる肯定の説明図である。
【図4】図3に示した工程に引き続いて行われる肯定の説明図である。
【図5】図4に示した工程に引き続いて行われる肯定の説明図である。
【図6】本発明にかかる道路トンネルの床版形成方法において、形成された床版の断面説明図である。
【図7】道路トンネルに形成される床版の説明図である。
【符号の説明】
10 道路トンネル
12 床版
12a 床版部
12b 側壁部
12c 中柱部
14 資材運搬用車両
16 レール
18 枕木
20 分割部
22 ガイドレール
24 床版設置台車
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for forming a floor slab for a road tunnel, and more particularly to a method for forming a floor slab when a road tunnel is constructed by a shield method.
[0002]
[Prior art]
When constructing a road tunnel, it is necessary to form a floor slab for enabling the vehicle to run inside the road tunnel, and this kind of floor slab is usually intended to be constructed as shown in FIG. A substantially flat floor slab portion 2 positioned below the center of the road tunnel 1 and extending so as to cross the cross section and both ends of the floor slab portion 2 are supported, and fixed to the side of the road tunnel 1. A pair of side wall portions 3 provided, and a middle column portion 4 that is fixed at the bottom of the road tunnel 1 and supports the center of the floor slab portion 2 from below are provided.
[0003]
By the way, a shield construction method is known as a kind of construction method for constructing a road tunnel having such a cross-sectional shape. When constructing a road tunnel by the shield construction method, it is not known whether or not it is disclosed in the literature, but at the construction site, the above-mentioned floor slab is generally formed of cast-in-place concrete.
[0004]
However, the conventional method for forming a floor slab for a road tunnel has the following problems.
[0005]
[Problems to be solved by the invention]
That is, when a floor slab having a floor slab part 2, a side wall part 3, and a middle pillar part 4 is constructed on-site, a process of assembling a mold, assembling a reinforcing bar, placing concrete, and curing is performed. The construction takes time and costs.
[0006]
Also, when the floor slab is installed on site, the height position of the sleepers where the rails on which the material transporting vehicle runs are provided to enable simultaneous construction with the excavation work involving material transport such as segments Has been set to be slightly above the center of the road tunnel 1 in consideration of the height of the concrete mold for placing concrete and workability such as leveling of concrete.
[0007]
In other words, when the floor slab was constructed on site, the floor slab was placed on the rough lower half of the road tunnel 1 and the material for excavation work was transported on the upper half. When the height is increased, the weight of the material and the transport vehicle becomes large, and there is a problem that the installation and removal becomes a work at a high place, which takes time and cost.
[0008]
The present invention has been made in view of such conventional problems, and the object of the present invention is to provide a method for forming a floor slab for a road tunnel that can reduce construction time and cost. is there.
[0009]
[Means for Solving the Problems]
In order to achieve the above object, according to the present invention, when a road tunnel is constructed by a shield method in which segments are assembled in an annular shape on an excavation surface, a floor slab is directed from the entrance side to the face side of the road tunnel that is being constructed. The floor slab is located below the center of the road tunnel, and is a substantially flat floor slab portion that extends across a cross section of the road tunnel, and the floor A pair of side wall portions that support both ends of the plate portion, and are fixed to the side portion of the road tunnel, and a middle column portion that is fixed to the bottom portion of the road tunnel and supports the center of the floor slab portion from below. The floor slab is composed of a precast member that is formed in a predetermined shape in advance, and a rail on which the material transport vehicle necessary for excavation work can be run by opening a space where the floor slab can be constructed. At the bottom of the road tunnel To together, a guide rail capable of running the floor plate placement carriage laid on the outside of the rail, and the installation work of the floor plate by the floor plate placement carriage, the materials necessary to excavation work by the material handling vehicle It was made possible to proceed with transportation at the same time .
[0010]
According to the method for forming a floor slab for a road tunnel configured in this way, the floor slab is composed of a precast member that is previously formed in a predetermined shape. Construction time is shortened and construction efficiency is improved.
[0011]
In addition, the rails that can travel the material transport vehicle necessary for excavation work are laid at the bottom of the road tunnel with a space where the floor slab can be constructed, so a large support structure is not required and Removal is also easy.
[0012]
A pair of the rails can be provided on both sides of the center pillar portion where the construction is planned.
[0014]
The floor slab has the pair of side wall portions fixed to the side of the tunnel, and then the lower end of the middle column portion is erected on the bottom of the road tunnel, and then both ends are placed on the side wall portion. At the same time, the floor slab portion can be installed with the central portion in contact with the upper end of the middle column portion.
[0015]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, preferred embodiments of the invention will be described in detail with reference to the accompanying drawings. 1 to 6 show an embodiment of a method for forming a floor slab of a road tunnel according to the present invention.
[0016]
The road tunnel 10 shown in the figure is maintained in a tunnel shape by excavating natural ground with a shield machine (not shown) and assembling segments in an annular shape on the excavated surface.
[0017]
When the road tunnel 10 is constructed by such a shield construction method, the floor slab 12 is sequentially formed from the entrance side of the constructed road tunnel 10 simultaneously with the excavation work of the shield machine on the face side. The
[0018]
In this embodiment, the floor slab 12 includes a floor slab portion 12a, a pair of side wall portions 12b, and a middle column portion 12c, as shown in detail in FIG. The floor slab portion 12a is formed in a substantially flat plate shape having a predetermined thickness. In the case of this embodiment, the floor slab portion 12a is located below the center of the tunnel 10 in the cross section of the road tunnel 10, and the tunnel 10 The cross section of the road tunnel 10 is formed to extend across the cross section of the road tunnel 10 in this form.
[0019]
The pair of side wall portions 12b are disposed so as to face the side surfaces of the road tunnel 10, and are formed in a substantially right triangle shape. On the hypotenuse of the right triangle of each side wall portion 12b, a curved portion whose curvature is in close contact with the inner surface of the road tunnel 10 is formed. This curved portion is fixed to the side portion of the road tunnel 10 and a floor slab is formed on the upper side. By placing both ends of the portion 12a, both ends of the floor slab portion 12a are supported and formed in this form over the total extension of the road tunnel 10.
[0020]
The middle column portion 12c is fixed at the bottom of the road tunnel 10 and supports the center of the floor slab portion 12a from below, and the middle column portion 12c extends along the axial direction of the road tunnel 10, Many are erected and arranged at a predetermined interval.
[0021]
The floor slab 12 including the floor slab portion 12a, the side wall portion 12b, and the middle column portion 12c is composed of a precast member that is previously formed in a predetermined shape and a predetermined length by factory production or the like. In the case of the present embodiment, the floor slab portion 12a and the side wall portion 12b are set to the same length, and the middle column portion 12c is a set of a plurality of pieces corresponding to this length.
[0022]
When the floor slab 12 is formed in the road tunnel 10, as shown in FIG. 1, a rail 16 that allows the material transporting vehicle 14 necessary for excavation work to be opened by opening a space where the floor slab 12 can be constructed. Is laid at the bottom of the road tunnel 10.
[0023]
In the case of the present embodiment, four rails 16 are arranged on the sleepers 18 at a predetermined interval so that two vehicles 14 can travel. In the central part of the sleeper 18, a dividing part 20 is provided in which the middle pillar part 12 c can be installed by removing it.
[0024]
In the case of the present embodiment, the floor slab 12 is formed by using a floor slab installation carriage 24 that runs on a guide rail 22 laid outside the rail 16. The floor slab installation carriage 24 has a gate-type carriage main body 24a provided with wheels that roll on the guide rails 22 at the lower end.
[0025]
A suspension balance 24d provided with a suspension fitting 24b for suspending the side wall portion 12b is installed on a side portion of the carriage main body 24a. A hoist 24c for suspending the floor slab portion 12a or the middle column portion 12c is provided on the upper side of the carriage main body 24a.
[0026]
When the floor slab 12 is formed in the road tunnel 10, first, as shown in FIGS. 1 and 2, the pair of side wall portions 12 b are attached to the hanging bracket 24 b of the floor slab installation carriage 24 and transported to the installation location. And fixed to the side of the road tunnel 10.
[0027]
In this case, as shown in FIG. 1, the positioning and fixing of the side wall portion 12 b can be easily performed by previously providing the locking metal fitting 26 of the side wall portion 12 b at a predetermined position of the segment of the road tunnel 10.
[0028]
When the installation of the side wall portion 12b at the predetermined position is finished, next, as shown in FIG. 3, the middle pillar portion 12c is attached to the hoist 24c, and this is erected on the bottom portion of the road tunnel 10.
[0029]
At this time, the divided portion 20 of the sleeper 18 is removed, and the lower end of the middle column portion 12c is fixed to the bottom of the road tunnel 10 by, for example, non-shrinkable concrete 28, whereby the middle column portion 12c is erected. Installed in the installed state.
[0030]
The vertical installation of the middle pillar portion 12c is performed at a predetermined interval along the tunnel axis direction. When this installation is completed, the floor slab portion is then placed on the hoist 24c as shown in FIG. 12a is attached, it lifts, both ends are mounted on the side wall part 12b, and this is installed so that the upper end of the center pillar part 12c may contact | abut to the lower surface of a center part.
[0031]
By the above steps, as shown in FIG. 5, the floor slab 12 having a predetermined length composed of the floor slab portion 12 a, the side wall portion 12 b, and the middle column portion 12 c is formed, and then the above-described steps are sequentially repeated, The floor slab 12 is extended to the face side.
[0032]
In addition, the floor slab portion 12a having both ends placed on the side wall portion 12b is integrated by forming a finished concrete layer covering the outer periphery of the side wall portion 12b, and finally has the same structure as shown in FIG. It becomes a state.
[0033]
Now, according to the road tunnel floor slab forming method configured as described above, the floor slab 12 is composed of a precast member formed in a predetermined shape in advance. As a result, the construction time on site is shortened and the construction efficiency is improved.
[0034]
In addition, in the case of the present embodiment, the material transport vehicle 14 that transports materials necessary for excavation work, for example, a segment, can travel without being affected by the work of forming the floor slab 12, so The plate forming operation can be carried out simultaneously, and the construction efficiency can be improved also from this point.
[0035]
In addition, since the rail 16 capable of traveling the material transporting vehicle 14 required for excavation work is laid at the bottom of the road tunnel 10 with a space where the floor slab 12 can be constructed, a large support structure is unnecessary. It is easy to install and remove.
[0036]
【The invention's effect】
As described above in detail, according to the method for forming a floor slab of a road tunnel according to the present invention, it is possible to shorten the construction time and the cost.
[Brief description of the drawings]
FIG. 1 is a cross-sectional explanatory view of an initial step of a method for forming a floor slab for a road tunnel according to the present invention.
FIG. 2 is an affirmative explanatory diagram subsequent to the process shown in FIG. 1;
FIG. 3 is an affirmative explanatory diagram subsequent to the step shown in FIG. 2;
4 is an affirmative explanatory diagram subsequent to the step shown in FIG. 3; FIG.
5 is an affirmative explanatory diagram subsequent to the process shown in FIG. 4; FIG.
FIG. 6 is a cross-sectional explanatory view of the floor slab formed in the road tunnel floor slab forming method according to the present invention.
FIG. 7 is an explanatory diagram of a floor slab formed in a road tunnel.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 10 Road tunnel 12 Floor slab 12a Floor slab part 12b Side wall part 12c Middle pillar part 14 Material conveying vehicle 16 Rail 18 Sleeper 20 Dividing part 22 Guide rail 24 Floor slab installation cart

Claims (3)

掘削面にセグメントを環状に組立てるシールド工法により道路トンネルを構築する際に、構築途中の前記道路トンネルの抗口側から切羽側に向けて床版を形成する方法であって、
前記床版は、前記道路トンネルの中心よりも下方に位置し、当該道路トンネルの横断面を横断するように延設される概略平板状の床版部と、
前記床版部の両端を支持し、前記道路トンネルの側部に固設される一対の側壁部と、
下端が前記道路トンネルの底部に定着され、前記床版部の中央を下方から支持する中柱部とを備え、
前記床版は、予め所定形状に形成されるプレキャスト部材から構成され、
前記床版の構築可能な空間をあけて、掘削作業に必要な資材運搬用車両の走行が可能なレールを前記道路トンネルの底部に敷設するとともに、
前記レールの外側に床版設置台車の走行が可能なガイドレールを敷設し、
前記床版設置台車による前記床版の設置作業と、前記資材運搬用車両による掘削作業に必要な資材の運搬とを同時進行可能にすることを特徴とする道路トンネルの床版形成方法。
When building a road tunnel by a shield method that assembles segments on the excavation surface in a ring shape, a method of forming a floor slab from the entrance side of the road tunnel in the middle of construction toward the face side,
The floor slab is located below the center of the road tunnel, and is a substantially flat floor slab portion extending so as to cross the cross section of the road tunnel;
A pair of side walls that support both ends of the floor slab and are fixed to the side of the road tunnel,
The lower end is fixed to the bottom of the road tunnel, and includes a middle column portion that supports the center of the floor slab portion from below,
The floor slab is composed of a precast member formed in a predetermined shape in advance,
Opening a space where the floor slab can be constructed, and laying a rail capable of traveling a material transport vehicle necessary for excavation work at the bottom of the road tunnel ,
Laying a guide rail capable of running a floor slab installation carriage on the outside of the rail,
A method for forming a floor slab in a road tunnel, wherein the floor slab installation work by the floor slab installation carriage and the transport of materials necessary for excavation work by the material transport vehicle can be simultaneously performed .
前記レールは、前記中柱部の構築予定個所を中心にして、その両側に一対設けることを特徴とする請求項1記載の道路トンネルの床版形成方法。2. The method for forming a floor slab for a road tunnel according to claim 1, wherein a pair of the rails are provided on both sides of the center pillar portion where the construction is planned. 前記床版は、前記一対の側壁部を前記トンネルの側部に固設した後に、前記中柱部の下端を前記道路トンネルの底部に立設し、しかる後に、前記側壁部に両端を載置するとともに、前記中柱部の上端に中央部を当接させて前記床版部を設置することを特徴とする請求項1または2記載の道路トンネルの床版形成方法。The floor slab has the pair of side wall portions fixed to the side of the tunnel, and then the lower end of the middle column portion is erected on the bottom of the road tunnel, and then both ends are placed on the side wall portion. The floor slab forming method for a road tunnel according to claim 1 or 2, wherein the floor slab portion is installed with a central portion in contact with an upper end of the middle pillar portion.
JP2002341692A 2002-11-26 2002-11-26 Road tunnel floor slab formation method Expired - Fee Related JP4069729B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002341692A JP4069729B2 (en) 2002-11-26 2002-11-26 Road tunnel floor slab formation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002341692A JP4069729B2 (en) 2002-11-26 2002-11-26 Road tunnel floor slab formation method

Publications (2)

Publication Number Publication Date
JP2004176322A JP2004176322A (en) 2004-06-24
JP4069729B2 true JP4069729B2 (en) 2008-04-02

Family

ID=32703945

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002341692A Expired - Fee Related JP4069729B2 (en) 2002-11-26 2002-11-26 Road tunnel floor slab formation method

Country Status (1)

Country Link
JP (1) JP4069729B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4739096B2 (en) * 2006-04-12 2011-08-03 鹿島建設株式会社 Construction equipment inside the tunnel
JP4805200B2 (en) * 2007-03-20 2011-11-02 清水建設株式会社 Arched precast version in shield tunnel
JP4694523B2 (en) * 2007-03-20 2011-06-08 清水建設株式会社 Construction method of road tunnel in shield tunnel
JP5037672B2 (en) * 2010-10-29 2012-10-03 鹿島建設株式会社 Construction equipment inside the tunnel
JP6196693B2 (en) * 2016-01-14 2017-09-13 本清鋼材株式会社 Construction method and structure of sleeper body, anchor hole box removal and Pca pillar and inverted concrete

Also Published As

Publication number Publication date
JP2004176322A (en) 2004-06-24

Similar Documents

Publication Publication Date Title
JP3029022B2 (en) Formwork apparatus for tunnel lining and lining method using the same
JP3881210B2 (en) Tunnel floor slab construction method and tunnel
CN110042867A (en) Complete combined assembled subway station prefabricated components mechanization transportation system and method
JP4069729B2 (en) Road tunnel floor slab formation method
JP2010031607A (en) Construction method for grade separation
KR101195442B1 (en) Apparatus for making box girder for bridge and a method for manufacturing box girder for bridge using this apparatus
JP6239686B2 (en) Construction material of tunnel shaft internal structure, construction lift and material transport cart
JP5793062B2 (en) Tunnel construction apparatus and tunnel construction method
CN110042861A (en) A kind of subway station assembled rail road and the connecting node with prefabricated middle plate against the wind
JP4415838B2 (en) Construction method inside tunnel
JP3458176B2 (en) Construction method of floor slab in tunnel
KR100347912B1 (en) Tunneling Plant
KR100746594B1 (en) Prefabricated vertical sphere construction method and precast structure used in the method
CN108978699B (en) Land integral prefabricated bearing platform and production and installation method thereof
KR101932118B1 (en) Apparatus of Installing Pillar for Mulriplex arch tunnel and Installing Method thereof
JP7003376B2 (en) Construction method of structure
JP3781491B2 (en) Slab construction method
JP3940587B2 (en) Construction method of divided bridge type traffic route
JP4915291B2 (en) Construction method and structure of concrete side wall
JPH08253947A (en) Installation method of form support for reverse casting
JP3453564B2 (en) Continuous construction method of tunnel block
JP2001073667A (en) Construction method of underground structure using floor slab combined with construction girder
KR101653559B1 (en) Method of repairing railway
JPH0681463A (en) Building method for stair
JP7573235B2 (en) Reinforcing bar unit transport device and reinforcing bar unit installation method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051125

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20051207

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20051207

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070614

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070626

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070822

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071225

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080107

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4069729

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110125

Year of fee payment: 3

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110125

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120125

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130125

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130125

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140125

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees