JP7569462B2 - Project management device, project management method, and project management program - Google Patents
Project management device, project management method, and project management program Download PDFInfo
- Publication number
- JP7569462B2 JP7569462B2 JP2024008921A JP2024008921A JP7569462B2 JP 7569462 B2 JP7569462 B2 JP 7569462B2 JP 2024008921 A JP2024008921 A JP 2024008921A JP 2024008921 A JP2024008921 A JP 2024008921A JP 7569462 B2 JP7569462 B2 JP 7569462B2
- Authority
- JP
- Japan
- Prior art keywords
- cost
- amount
- project
- forecast
- budget
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000007726 management method Methods 0.000 title claims description 38
- 238000000034 method Methods 0.000 claims description 62
- 238000004364 calculation method Methods 0.000 claims description 28
- 230000001186 cumulative effect Effects 0.000 claims description 10
- 230000010365 information processing Effects 0.000 claims description 10
- 238000010586 diagram Methods 0.000 description 32
- 238000010276 construction Methods 0.000 description 20
- 238000012545 processing Methods 0.000 description 15
- 230000004044 response Effects 0.000 description 12
- 238000012423 maintenance Methods 0.000 description 10
- 238000004891 communication Methods 0.000 description 8
- 230000006870 function Effects 0.000 description 7
- 238000012946 outsourcing Methods 0.000 description 5
- 238000004590 computer program Methods 0.000 description 4
- 238000012384 transportation and delivery Methods 0.000 description 3
- 238000005553 drilling Methods 0.000 description 2
- 230000003287 optical effect Effects 0.000 description 2
- 238000013439 planning Methods 0.000 description 2
- 238000003825 pressing Methods 0.000 description 2
- 238000007792 addition Methods 0.000 description 1
- LFYJSSARVMHQJB-QIXNEVBVSA-N bakuchiol Chemical compound CC(C)=CCC[C@@](C)(C=C)\C=C\C1=CC=C(O)C=C1 LFYJSSARVMHQJB-QIXNEVBVSA-N 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000015556 catabolic process Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000010422 painting Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000003672 processing method Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- 230000001052 transient effect Effects 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Financial Or Insurance-Related Operations Such As Payment And Settlement (AREA)
Description
本発明は、プロジェクト管理装置、プロジェクト管理方法、及びプロジェクト管理プログラムに関する。 The present invention relates to a project management device, a project management method, and a project management program.
企業会計基準委員会により、2018年3月30日に、我が国における収益認識に関する包括的な会計基準である新収益認識基準が公表され、2021年4月から原則適用が開始される。新収益認識基準に対応するシステムとして、例えば、特許文献1がある。 On March 30, 2018, the Accounting Standards Board of Japan published the New Revenue Recognition Standards, which are comprehensive accounting standards related to revenue recognition in Japan, and will be applied in principle from April 2021. For example, Patent Document 1 is an example of a system that complies with the New Revenue Recognition Standards.
しかしながら、特許文献1では、進行基準を採用する場合に、早期に、期末時原価予定金額及び期末時収益予定金額を算出することに関して何等記載されていない。 However, Patent Document 1 does not state anything about calculating the estimated end-of-period costs and estimated end-of-period revenues early when using the percentage-of-completion method.
本発明は、上記問題点に鑑みてなされたものであり、進行基準を採用する場合に、早期に、期末時原価予定金額及び期末時収益予定金額を予想して、経営リソースを対策することで収益の改善を実現することが可能なプロジェクト管理装置、プロジェクト管理方法、及びプロジェクト管理プログラムを提供することを目的とする。 The present invention has been made in consideration of the above problems, and aims to provide a project management device, a project management method, and a project management program that, when a progress-of-completion method is adopted, can predict the planned end-of-period costs and planned end-of-period revenues early and improve profits by taking measures with management resources.
上述した課題を解決し、目的を達成するために、本発明は、制御部を備えたプロジェクト管理装置であって、前記制御部は、対象のプロジェクトについて、予算金額、複数の原価科目、各原価科目の内部予算金額を含む実行予算情報を入力する実行予算入力手段と、
対象のプロジェクトについて、各原価科目の発注金額及び仕入予定日を含む発注情報を入力する発注情報入力手段と、前記原価科目毎に規定される原価予想分類に基づいて、各原価科目の期末時原価予定金額を算出する原価予定金額算出手段と、を備えたことを特徴とする。
In order to solve the above-mentioned problems and achieve the object, the present invention provides a project management device including a control unit, the control unit including: an execution budget input unit for inputting execution budget information including a budget amount, a plurality of cost items, and an internal budget amount for each cost item for a target project;
The system is characterized by comprising an order information input means for inputting order information including the order amount and planned purchase date of each cost item for the target project, and a cost forecast amount calculation means for calculating the end-of-period planned cost amount of each cost item based on the cost forecast classification defined for each cost item.
また、本発明の一態様によれば、前記制御部は、さらに、前記各原価科目の期末時原価予定金額に基づいて、原価比例により対象のプロジェクトの期末時収益予定金額を算出する収益予定金額算出手段を備えることにしてもよい。 According to one aspect of the present invention, the control unit may further include a planned revenue calculation means for calculating a planned revenue amount at the end of the period for the target project in proportion to the cost based on the planned cost amount at the end of the period for each of the cost items.
また、本発明の一態様によれば、材料費及び外注費の原価予想分類は、時点原価予想を使用し、仕入予定月に原価を発生させることにしてもよい。 Furthermore, according to one aspect of the present invention, the cost forecast classification of material costs and subcontract costs may use a current cost forecast, with costs incurred in the planned month of purchase.
また、本発明の一態様によれば、労務費、経費については、経過原価予想し、月次時点での原価発生金額と実行予算額から今後原価発生額を月割して計算することにしてもよい。 In addition, according to one aspect of the present invention, for labor costs and expenses, historical costs may be forecast, and future costs may be calculated on a monthly basis based on the cost incurred amount at the monthly point in time and the actual budget amount.
また、本発明の一態様によれば、前記プロジェクトは、建設業界、IT業界、又は機械業界に関するものであることにしてもよい。 According to one aspect of the present invention, the project may be related to the construction industry, the IT industry, or the machinery industry.
また、上述した課題を解決し、目的を達成するために、本発明は、制御部を備えた情報処理装置に実行させるためのプロジェクト管理方法であって、前記制御部で実行される、
対象のプロジェクトについて、予算金額、複数の原価科目、各原価科目の内部予算金額を含む実行予算情報を入力する実行予算入力工程と、対象のプロジェクトについて、各原価科目の発注金額及び仕入予定日を含む発注情報を登録する発注情報登録工程と、前記原価科目毎に規定される原価予想分類に基づいて、各原価科目の期末時原価予定金額を算出する原価予定金額算出工程と、を含むことを特徴とする。
In order to solve the above-mentioned problems and achieve the object, the present invention provides a project management method to be executed by an information processing device having a control unit, the method being executed by the control unit,
The method includes an execution budget input process for inputting execution budget information including a budget amount, a plurality of cost items, and an internal budget amount for each cost item for a target project, an order information registration process for registering order information including an order amount and a planned purchase date for each cost item for the target project, and a planned cost amount calculation process for calculating a planned cost amount at the end of the period for each cost item based on a cost forecast classification defined for each cost item.
また、上述した課題を解決し、目的を達成するために、本発明は、制御部及び記憶部を備えた情報処理装置に実行させるためのプロジェクト管理プログラムであって、前記制御部において、対象のプロジェクトについて、予算金額、複数の原価科目、各原価科目の内部予算金額を含む実行予算情報を入力する実行予算入力工程と、対象のプロジェクトについて、各原価科目の発注金額及び仕入予定日を含む発注情報を登録する発注情報登録工程と、前記原価科目毎に規定される原価予想分類に基づいて、各原価科目の期末時原価予定金額を算出する原価予定金額算出工程と、を実行させるためのプロジェクト管理プログラムであることを特徴とする。 In order to solve the above-mentioned problems and achieve the object, the present invention is a project management program to be executed by an information processing device having a control unit and a storage unit, and is characterized in that the project management program causes the control unit to execute an execution budget input process for inputting execution budget information for a target project, including a budget amount, multiple cost items, and an internal budget amount for each cost item, an order information registration process for registering order information for the target project, including an order amount and a planned purchase date for each cost item, and a planned cost amount calculation process for calculating the planned cost amount at the end of the period for each cost item based on a cost forecast classification specified for each of the cost items.
本発明によれば、進行基準を採用する場合に、早期に、期末時原価予定金額及び期末時収益予定金額を予想して、経営リソースを対策することで収益の改善を実現することが可能になるという効果を奏する。 According to the present invention, when the percentage of completion method is adopted, it is possible to predict the planned cost amount and the planned revenue amount at the end of the period early on, and improve profits by taking measures with management resources.
本発明の実施形態を図面に基づいて詳細に説明する。なお、本発明は本実施形態により限定されるものではない。 An embodiment of the present invention will be described in detail with reference to the drawings. Note that the present invention is not limited to this embodiment.
[1.概要]
企業会計基準委員会により、2018年3月30日に、我が国における収益認識に関する包括的な会計基準である新収益認識基準が公表され、2021年4月から原則適用が開始される。
[1. Overview]
On March 30, 2018, the Accounting Standards Board of Japan published the New Revenue Recognition Standard, a comprehensive accounting standard for revenue recognition in Japan, which will generally come into effect from April 2021.
建設業、IT業、及び機械業界等において、新収益認識基準により、原則、完成基準から進行基準への計算方式が変更となる。 In the construction, IT, and machinery industries, the new revenue recognition standards will, in principle, change the calculation method from the completed contract method to the percentage of completion method.
具体的には、「財又はサービスに対する支配が顧客に一定の期間にわたり移転することとなる要件に該当する場合には、財又はサービスを顧客に移転する履行義務を充足するにつれて、一定の期間にわたり収益を認識する(会計基準第38項及び第41項から第45項、適用指針第9項から第13項及び第15項から第22項引用」。 Specifically, "When the criteria for transferring control of goods or services to a customer over time are met, revenue is recognized over time as the performance obligation to transfer the goods or services to the customer is satisfied (Accounting Standard, paragraphs 38 and 41 to 45; Implementation Guidance, paragraphs 9 to 13 and 15 to 22)."
従来、完成基準を採用するケースが多く、期末時完成するかどうかを現場から集計して売上予定を立てることができたが、今後、原則進行基準を採用することになり、工期毎に期末時原価予定金額、並びに、期末時収益予定金額の計算に膨大な工数が必要となり、業務効率向上の策が求められている。 Previously, the completed construction method was often used, and sales could be forecast by collecting data from the site on whether work was completed at the end of the period. However, going forward, the percentage of completion method will be adopted as the rule, and a huge amount of work will be required to calculate the estimated cost amount and estimated revenue amount at the end of the period for each construction period, calling for measures to improve operational efficiency.
本実施の形態は、進行基準における期末時収益着地を予想するにあたり、工事毎の工期及び原価分類毎の特徴から収益見込みを算出するものである。 In this embodiment, when predicting the end-of-period revenue under the percentage of completion method, revenue forecasts are calculated based on the construction period of each project and the characteristics of each cost classification.
本実施の形態は、進行基準を採用する場合に、早期に、期末時原価予定金額及び期末時収益予定金額を予想し、経営リソースを対策することで収益の改善を実現することを目的とする。 The purpose of this embodiment, when the percentage of completion method is adopted, is to predict the planned cost amount and the planned revenue amount at the end of the period early and improve profits by taking measures with management resources.
本実施の形態では、原価分類の特徴により計算方法を区分けし、期末原価予定金額を算出する。例えば、設備工事の場合、大型機器など材料仕入が原価に占める割合が多いため、材料費は納期情報をもとに正確な情報を算出する必要がある。 In this embodiment, the calculation method is classified according to the characteristics of the cost classification, and the estimated end-of-period cost amount is calculated. For example, in the case of facility construction, the cost of materials such as large equipment accounts for a large proportion of the cost, so accurate information on material costs must be calculated based on delivery date information.
具体的には、本実施の形態では、実行予算時に立案する際に、材料費、外注費などの原価発生時期が予定可能な外部支出原価(時点原価予想)と、労務費、経費などの期間経過により累積する原価(経過原価予想)に分類し、その特性により工期から今後発生原価を算出する。外注費については、出来高査定など出来高進捗により期間経過により蓄積する原価に分類する可能性もあるため、原価分類毎に設定可能とする。 Specifically, in this embodiment, when planning the execution budget, costs are classified into external expenditure costs (point in time cost forecast) such as material costs and subcontract costs, whose occurrence can be predicted, and costs that accumulate over time such as labor costs and expenses (expected cost forecast), and future costs to be incurred are calculated based on the construction period according to their characteristics. Subcontract costs may also be classified as costs that accumulate over time depending on the progress of work, such as through performance appraisal, so this can be set for each cost category.
[2.構成]
本実施の形態に係るプロジェクト管理装置100の構成の一例について、図1参照して説明する。図1は、プロジェクト管理装置100の構成の一例を示すブロック図である。
2. Configuration
An example of the configuration of a
プロジェクト管理装置100は、市販のデスクトップ型パーソナルコンピュータである。なお、プロジェクト管理装置100は、デスクトップ型パーソナルコンピュータのような据置型情報処理装置に限らず、市販されているノート型パーソナルコンピュータ、PDA(Personal Digital Assistants)、スマートフォン、タブレット型パーソナルコンピュータなどの携帯型情報処理装置であってもよい。
The
プロジェクト管理装置100は、制御部102と通信インターフェース部104と記憶部106と入出力インターフェース部108と、を備えている。プロジェクト管理装置100が備えている各部は、任意の通信路を介して通信可能に接続されている。
The
通信インターフェース部104は、ルータ等の通信装置および専用線等の有線または無線の通信回線を介して、プロジェクト管理装置100をネットワーク300に通信可能に接続する。通信インターフェース部104は、他の装置と通信回線を介してデータを通信する機能を有する。ここで、ネットワーク300は、プロジェクト管理装置100とサーバ200とを相互に通信可能に接続する機能を有し、例えばインターネットやLAN(Local Area Network)等である。
The
入出力インターフェース部108には、入力装置112および出力装置114が接続されている。出力装置114には、モニタ(タッチパネルを含む)の他、スピーカやプリンタを用いることができる。入力装置112には、キーボード、マウス、およびマイクの他、マウスと協働してポインティングデバイス機能を実現するモニタを用いることができる。なお、以下では、出力装置114をモニタ114またはプリンタ114とし、入力装置112をキーボード112またはマウス112として記載する場合がある。また、「出力」とは、出力装置114で出力すること等をいい、例えば、モニタ114への表示出力やプリンタ114での印刷出力することの他、外部にデータを送信することを含む。
The input/
記憶部106には、各種のデータベース、テーブル、およびファイルなどが格納される。記憶部106には、OS(Operating System)と協働してCPU(Central Processing Unit)に命令を与えて各種処理を行うためのコンピュータプログラムが記録される。記憶部106として、例えば、RAM(Random Access Memory)・ROM(Read Only Memory)等のメモリ装置、ハードディスクのような固定ディスク装置、フレキシブルディスク、および光ディスク等を用いることができる。また、記憶部106は、プロジェクト原価科目区分マスタ106aと、原価分類マスタ106bと、品番マスタ106cと、プロジェクト種別マスタ106dと、データファイル106eとを備えている。図4は、プロジェクト原価科目区分マスタ106a、原価分類マスタ106b、品番マスタ106c、及びプロジェクト種別マスタ106dの構成例を示す図である。図5は、プロジェクト原価科目区分マスタ106a、原価分類マスタ106b、及びプロジェクト種別マスタ106dの設定例を示す図である。
The
プロジェクト原価科目区分マスタ106aは、原価分類をさらに細かく分類したマスタである。プロジェクト原価科目区分マスタ106aは、図4に示すように、プロジェクト原価科目区分、プロジェクト原価科目区分名、原価分類コード、原価分類名のデータを関連づけて登録するためのテーブル等で構成することができる。原価科目区分は、図5に示すように、例えば、主要材料費、補助材料費、賃金給与、雑給、外注費等である。プロジェクト原価科目区分マスタ106aの原価分類コードを元に、原価分類マスタ106bの原価予想分類を指定する。
The project cost
原価分類マスタ106bは、原価要素(例えば、材料、外注、労務、経費)の原価予想分類を規定したマスタである。原価分類マスタ106bは、図4に示すように、原価分類コード、原価分類名、原価分類種別、原価予想分類のデータを関連づけて登録するためのテーブル等で構成することができる。原価分類は、例えば、図5に示すように、材料費、外注費、労務費、経費、機械費等である。
The
品番マスタ106cは、品番コード、品番名、プロジェクト種別コード、プロジェクト原価科目区分のデータを関連づけて登録するためのテーブル等で構成することができる。指定した品番からプロジェクト原価科目区分、プロジェクト種別を紐づける。 The product number master 106c can be configured with a table for registering data on product number codes, product number names, project type codes, and project cost item classifications in association with each other. The specified product number is linked to the project cost item classification and project type.
プロジェクト種別マスタ106dは、予算種別、実行予算など原価の種類を設定したマスタである。プロジェクト種別マスタ106dは、図4に示すように、プロジェクト種別コード、プロジェクト種別名のデータを関連づけて登録するためのテーブル等で構成することができる。プロジェクト種別は、図5に示すように、例えば、舗装工事、建築一式、電気工事、管工事、舗装工事等である。 The project type master 106d is a master that sets the type of cost, such as budget type and execution budget. As shown in FIG. 4, the project type master 106d can be configured with a table or the like for registering data on project type codes and project type names in association with each other. As shown in FIG. 5, the project types are, for example, paving work, general building construction, electrical work, piping work, paving work, etc.
データファイル106eは、契約情報、実行予算情報、発注情報、着地予想登録情報等の各種データを格納するためのテーブルである。 Data file 106e is a table for storing various data such as contract information, working budget information, order information, and arrival forecast registration information.
契約情報は、プロジェクト受注ヘッダと、プロジェクト受注明細で構成されている(図7参照)。プロジェクト受注ヘッダは、プロジェクト番号、受注番号、得意先コード、伝票売上本体金額、伝票売上消費税額、伝票原価金額、伝票粗利金額を含んでいてもよい。プロジェクト受注明細は、受注番号、受注行番号、商品コード、商品名、債権科目区分、消費税率区分、受注数、売上単価、売上本体単価、売上本体金額、売上消費税額、原価単価、原価金額、粗利金額を含んでいてもよい。 The contract information consists of a project order header and project order details (see Figure 7). The project order header may include the project number, order number, customer code, invoice sales amount, invoice sales consumption tax amount, invoice cost amount, and invoice gross profit amount. The project order details may include the order number, order line number, product code, product name, credit account category, consumption tax rate category, order quantity, unit sales price, unit sales price, sales amount, sales consumption tax amount, unit cost price, cost amount, and gross profit amount.
実行予算情報は、プロジェクト予算ヘッダと、プロジェクト予算明細で構成されている(図8参照)。プロジェクト予算ヘッダは、プロジェクト番号、受注番号、受注行番号、予算変更回数、会計年月、登録日、プロジェクト予算単位区分、伝票予算金額を含んでいてもよい。また、プロジェクト予算明細は、プロジェクト番号、受注番号、受注行番号、プロジェクト予算行番号、予算変更回数、プロジェクト種別コード、プロジェクト予算金額を含んでいてもよい。 The execution budget information consists of a project budget header and project budget details (see Figure 8). The project budget header may include the project number, order number, order line number, number of budget changes, accounting year and month, registration date, project budget unit category, and voucher budget amount. The project budget details may include the project number, order number, order line number, project budget line number, number of budget changes, project type code, and project budget amount.
発注情報は、プロジェクト発注ヘッダと、プロジェクト発注明細で構成されている(図10参照)。プロジェクト発注ヘッダは、発注番号、発注日、会計年月、仕入先、伝票仕入金額、プロジェクト番号、受注番号、受注行番号を含んでいてもよい。プロジェクト発注明細は、発注番号、発注行番号、品番コード、品番名、発注数量、発注単価、発注金額、仕入予定日を含んでいてもよい。 The order information consists of a project order header and project order details (see Figure 10). The project order header may include the order number, order date, accounting year and month, supplier, invoice purchase amount, project number, order number, and order line number. The project order details may include the order number, order line number, product code, product name, order quantity, order price, order amount, and scheduled purchase date.
着地予想登録情報は、プロジェクト予想原価ヘッダと、プロジェクト予想原価明細とで構成されている(図12参照)。プロジェクト予想原価ヘッダは、会計年月、プロジェクト番号、受注番号、受注行番号、契約金額を含んでいてもよい。プロジェクト予想原価明細は、会計年月、プロジェクト番号、受注番号、受注行番号、プロジェクト予定原価行番号、プロジェクト種別コード、プロジェクト原価科目区分、予算金額、発生済原価金額、当月発生原価金額、今後予定原価金額、最終着地予想原価金額(累計発生原価+今後予想原価)、予算実績差異金額を含んでいてもよい。 The estimated final cost registration information consists of a project estimated cost header and project estimated cost details (see Figure 12). The project estimated cost header may include the accounting year and month, project number, order number, order line number, and contract amount. The project estimated cost details may include the accounting year and month, project number, order number, order line number, project planned cost line number, project type code, project cost item category, budget amount, cost amount already incurred, cost amount incurred this month, future planned cost amount, final estimated final cost amount (cumulative incurred costs + future estimated costs), and budget-actual variance amount.
制御部102は、プロジェクト管理装置100を統括的に制御するCPU等である。制御部102は、OS等の制御プログラム・各種の処理手順等を規定したプログラム・所要データなどを格納するための内部メモリを有し、格納されているこれらのプログラムに基づいて種々の情報処理を実行する。制御部102は、機能概念的に、マスタメンテ部102aと、実行予算登録部102bと、発注登録部102cと、原価予定金額算出部102dと、収益予定金額算出部102eと、画面表示制御部102fと、月次着地予想金額登録部102gとを備えている。
The control unit 102 is a CPU or the like that controls the
マスタメンテ部102aは、例えば、モニタ114に表示される不図示のマスタメンテ画面上でのオペレータの操作等に応じて、プロジェクト原価科目区分マスタ106a、原価分類マスタ106b、品番マスタ106c、及びプロジェクト種別マスタ106dのデータの追加・削除・変更等の編集を行うためのものである。
The master maintenance section 102a is used to perform editing such as adding, deleting, and changing data in the project cost
実行予算登録部102bは、例えば、モニタ114に表示される実行予算登録画面(図6参照)上でのオペレータの操作等に応じて、対象のプロジェクトについて、予算金額、複数の原価科目、各原価科目の内部予算金額を含む実行予算情報を入力して、データファイル106eに登録する。また、実行予算登録部102bは、対象のプロジェクトについて、契約情報を入力して、データファイル106eに登録する。プロジェクトは、建設業界、IT業界、又は機械業界に関するものとしてもよい。 The execution budget registration unit 102b inputs execution budget information including the budget amount, multiple cost items, and internal budget amount for each cost item for the target project in response to, for example, an operator's operation on the execution budget registration screen (see FIG. 6) displayed on the monitor 114, and registers it in the data file 106e. The execution budget registration unit 102b also inputs contract information for the target project and registers it in the data file 106e. The project may be related to the construction industry, the IT industry, or the machinery industry.
発注登録部102cは、例えば、モニタ114に表示される発注登録画面(図9参照)上でのオペレータの操作等に応じて、対象のプロジェクトについて、各原価科目の発注金額及び仕入予定日を含む発注情報を入力して、データファイル106eに登録する。 The order registration unit 102c, for example, inputs order information including the order amount and planned purchase date for each cost item for the target project in response to an operator's operation on the order registration screen (see FIG. 9) displayed on the monitor 114, and registers the information in the data file 106e.
月次着地予想金額登録部102gは、例えば、モニタ114に表示される着地予想登録画面(図11参照)上でのオペレータの操作等に応じて、対象のプロジェクトについて、着地予想登録情報を入力して、データファイル106eに登録する。 The monthly estimated landing amount registration unit 102g inputs estimated landing amount registration information for the target project in response to, for example, an operator's operation on the estimated landing amount registration screen (see FIG. 11) displayed on the monitor 114, and registers the information in the data file 106e.
原価予定金額算出部102dは、原価科目毎に規定される原価予想分類に基づいて、各原価科目に期末時原価予定金額を算出する。材料費及び外注費の原価予想分類は、時点原価予想を使用して、仕入予定月に原価を発生させてもよい。労務費、経費については、経過原価予想し、月次時点での原価発生金額と実行予算額から今後原価発生額を月割して計算することにしてもよい。 The estimated cost calculation unit 102d calculates the estimated cost amount at the end of the period for each cost item based on the estimated cost classification defined for each cost item. The estimated cost classification for material costs and subcontract costs may use a current cost forecast, with costs incurred in the planned month of purchase. For labor costs and expenses, historical costs may be forecast, and future costs may be calculated on a monthly basis based on the estimated cost amount at the monthly point in time and the actual budget amount.
収益予定金額算出部102eは、各原価科目の期末時原価予定金額に基づいて、原価比例により対象プロジェクトの期末時収益予定金額を算出する。また、収益予定金額算出部102eは、算出した各原価科目の期末時原価予定金額及び期末時収益予定金額に基づいた対象プロジェクトの収支予想データを出力してもよい(図15参照)。 The planned revenue calculation unit 102e calculates the planned revenue at the end of the period for the target project in proportion to the cost, based on the planned cost at the end of the period for each cost item. The planned revenue calculation unit 102e may also output income and expenditure forecast data for the target project based on the calculated planned cost at the end of the period and the planned revenue at the end of the period for each cost item (see FIG. 15).
画面表示制御部102fは、モニタ114に表示する各種画面(例えば、マスタメンテ画面、実行予算登録画面、発注登録画面、着地予想登録画面等)の表示及びその入力を制御する。 The screen display control unit 102f controls the display and input of various screens (e.g., master maintenance screen, working budget registration screen, order registration screen, arrival forecast registration screen, etc.) displayed on the monitor 114.
[3.具体例]
図2~図15を参照して、本実施の形態におけるプロジェクト管理装置100の処理の具体例を説明する。まず、図2を参照して、本実施の形態におけるプロジェクト管理装置100の全体の処理の概略を説明する。図2は、本実施の形態におけるプロジェクト管理装置100の全体の処理の一例を説明するためのフローを示す図である。
3. Specific Examples
A specific example of the processing of
図2において、マスタメンテ部102aは、マスタ設定処理を実行する(ステップS1)。具体的には、マスタ設定処理では、マスタメンテ部102aは、例えば、モニタ114に表示される不図示のマスタメンテ画面上でのオペレータの操作等に応じて、プロジェクト原価科目区分マスタ106a、原価分類マスタ106b、品番マスタ106c、及びプロジェクト種別マスタ106dのデータの設定を行う。
In FIG. 2, the master maintenance unit 102a executes a master setting process (step S1). Specifically, in the master setting process, the master maintenance unit 102a sets data for the project cost
実行予算登録部102bは、実行予算登録処理を実行する(ステップS2)。具体的には、実行予算登録処理では、実行予算登録部102bは、例えば、モニタ114に表示される実行予算登録画面(図6参照)上でのオペレータの操作等に応じて、対象のプロジェクトについて、予算金額、複数の原価科目、各原価科目の内部予算金額を含む実行予算情報を入力して、データファイル106eに登録する。 The execution budget registration unit 102b executes the execution budget registration process (step S2). Specifically, in the execution budget registration process, the execution budget registration unit 102b inputs execution budget information including the budget amount, multiple cost items, and the internal budget amount of each cost item for the target project in response to, for example, the operator's operation on the execution budget registration screen (see FIG. 6) displayed on the monitor 114, and registers it in the data file 106e.
発注登録部102cは、発注登録処理を実行する(ステップS3)。具体的には、発注登録処理では、発注登録部102cは、例えば、モニタ114に表示される発注登録画面(図9参照)上でのオペレータの操作等に応じて、対象のプロジェクトについて、各原価科目の発注金額及び仕入予定日を含む発注情報を入力して、データファイル106eに登録する。 The order registration unit 102c executes the order registration process (step S3). Specifically, in the order registration process, the order registration unit 102c inputs order information including the order amount and the planned purchase date for each cost item for the target project in response to, for example, an operator's operation on the order registration screen (see FIG. 9) displayed on the monitor 114, and registers the information in the data file 106e.
月次着地予想金額登録部102gは、月次着地予想金額登録処理を実行する(ステップS4)。具体的には、月次着地予想金額登録処理では、月次着地予想金額登録部102gは、例えば、モニタ114に表示される着地予想登録画面(図11参照)上でのオペレータの操作等に応じて、対象のプロジェクトについて、着地予想登録情報を入力して、データファイル106eに登録する。 The monthly estimated landing amount registration unit 102g executes the monthly estimated landing amount registration process (step S4). Specifically, in the monthly estimated landing amount registration process, the monthly estimated landing amount registration unit 102g inputs estimated landing amount registration information for the target project in response to, for example, the operator's operation on the estimated landing amount registration screen (see FIG. 11) displayed on the monitor 114, and registers it in the data file 106e.
原価予定金額算出部102d及び収益予定金額算出部102eは、期末時着地予想処理を実行する(ステップS5)。具体的には、期末時着地予想処理では、原価予定金額算出部102dは、原価科目毎に規定される原価予想分類に基づいて、各原価科目に期末時原価予定金額を算出する。材料費及び外注費の原価予想分類は、時点原価予想を使用し、仕入予定月に原価を発生させてもよい。また、労務費、経費については、経過原価予想を使用し、月次時点での原価発生金額と実行予算額から今後原価発生額を月割して計算することにしてもよい。 The estimated cost calculation unit 102d and the estimated revenue calculation unit 102e execute end-of-period forecast processing (step S5). Specifically, in the end-of-period forecast processing, the estimated cost calculation unit 102d calculates the estimated end-of-period cost amount for each cost item based on the estimated cost classification defined for each cost item. The estimated cost classification for material costs and subcontract costs may use a current cost forecast, and costs may be incurred in the planned month of purchase. In addition, for labor costs and expenses, a historical cost forecast may be used, and future costs may be calculated on a monthly basis based on the cost amount incurred at the monthly point in time and the actual budget amount.
期末時着地予想処理では、収益予定金額算出部102eは、期末時原価予定金額に基づいて、原価比例により対象のプロジェクトについて期末時収益予定金額を算出する。また、期末時着地予想処理では、収益予定金額算出部102eは、算出した各原価科目の期末時原価予定金額及び期末時収益予定金額に基づいた対象プロジェクトの収支予想データを出力してもよい(図15参照)。 In the end-of-period final forecast process, the planned revenue calculation unit 102e calculates the planned end-of-period revenue for the target project in proportion to the cost, based on the planned end-of-period cost amount. In addition, in the end-of-period final forecast process, the planned revenue calculation unit 102e may output income/expense forecast data for the target project based on the calculated planned end-of-period cost amount and planned end-of-period revenue amount for each cost item (see FIG. 15).
つぎに、図3~図15を参照して、本実施の形態におけるプロジェクト管理装置100の処理の具体例を説明する。
Next, a specific example of the processing of the
(S1:マスタ設定処理)
図3~図5を参照して、マスタ設定処理を詳細に説明する。図3は、原価分類毎の原価予想分類を示す図である。図4は、プロジェクト原価科目区分マスタ106a、原価分類マスタ106b、品番マスタ106c、及びプロジェクト種別マスタ106dの構成例を示す図である。図5は、プロジェクト原価科目区分マスタ106a、原価分類マスタ106b、及びプロジェクト種別マスタ106dの設定例を示す図である。
(S1: Master setting process)
The master setting process will be described in detail with reference to Figures 3 to 5. Figure 3 is a diagram showing cost forecast classification for each cost classification. Figure 4 is a diagram showing configuration examples of the project cost
マスタメンテ部102aは、マスタメンテ部102aは、例えば、モニタ114に表示される不図示のマスタメンテ画面上でのオペレータの操作等に応じて、プロジェクト原価科目区分マスタ106a、原価分類マスタ106b、品番マスタ106c、及びプロジェクト種別マスタ106dのデータの設定を行う。
The master maintenance unit 102a sets data in the project cost
図3に示すように、「材料費」の原価予想分類は、「時点原価予想」とし、「外注費」の原価予想分類は、「時点原価予想」とし、「労務費」の原価予想分類は、「経過原価予想」とし、「経費」の原価予想分類は、「経過原価予想」とする。材料費や外注費のように、時点原価予想のものは、発注登録の納期情報を元に期末時に原価発生している否かを判断する。 As shown in Figure 3, the cost forecast classification for "material costs" is "current cost forecast," the cost forecast classification for "subcontract costs" is "current cost forecast," the cost forecast classification for "labor costs" is "overtime cost forecast," and the cost forecast classification for "expenses" is "overtime cost forecast." For items with current cost forecasts such as material costs and subcontract costs, a determination is made as to whether costs have been incurred at the end of the period based on delivery date information in the order registration.
図4に示すプロジェクト原価科目区分マスタ106aの例では、PJ原価科目区分「G10」、PJ原価科目区分名「主要材料費」、原価分類コード「1000」、原価分類名「材料費」となっている。
In the example of the project cost
図4に示す原価分類マスタ106bの例では、原価分類コード「1000」、原価分類名「材料費」、原価分類種別「直接原価(材料)」、原価予想分類「時点原価予想」となっている。
In the example of the
図4に示す品番マスタ106cの例では、品番コード「C001001、品番名「塗装-材料」、プロジェクト種別コード「A01」、プロジェクト種別コード「02」、プロジェクト原価科目区分「G10」となっている。 In the example of item number master 106c shown in Figure 4, the item number code is "C001001," the item name is "painting - materials," the project type code is "A01," the project type code is "02," and the project cost item category is "G10."
図4に示すプロジェクト種別マスタ106dの例では、プロジェクト種別コード「A01」、プロジェクト種別名「地業工事」となっている。 In the example of project type master 106d shown in Figure 4, the project type code is "A01" and the project type name is "ground work."
(S2:実行予算登録処理)
図6~図8を参照して、実行予算登録処理を詳細に説明する。図6は、実行予算登録画面の表示例を示す図である。図7は契約情報の構成例を示す図である。図8は、実行情報の構成例を示す図である。データファイル106eには、予め契約情報が登録されているものとして説明する。
(S2: Execution budget registration process)
The working budget registration process will be described in detail with reference to Figures 6 to 8. Figure 6 is a diagram showing an example of the working budget registration screen. Figure 7 is a diagram showing an example of the structure of contract information. Figure 8 is a diagram showing an example of the structure of execution information. The following description will be given on the assumption that contract information has been registered in advance in data file 106e.
実行予算登録部102bは、例えば、モニタ114に表示される実行予算登録画面上でのオペレータの操作等に応じて、対象のプロジェクトについて実行予算情報を入力して、データファイル106eに登録する。 The actual budget registration unit 102b inputs actual budget information for the target project in response to, for example, an operator's operation on the actual budget registration screen displayed on the monitor 114, and registers it in the data file 106e.
図6に示す実行予算登録画面では、プロジェクト種別やプロジェクト原価科目等を指定する。図6に示す予算登録画面には、契約金額、プロジェクト番号、会計年月、受注番号、予算変更回数、登録日が表示されるヘッダエリアと、予算(プロジェクト種別、種別名、予算金額、プロジェクト原価科目、内訳予算額)等の項目が表示される明細エリアを備えている。 The execution budget registration screen shown in Figure 6 allows you to specify the project type, project cost item, etc. The budget registration screen shown in Figure 6 has a header area that displays the contract amount, project number, accounting year and month, order number, number of budget changes, and registration date, and a details area that displays items such as the budget (project type, type name, budget amount, project cost item, detailed budget amount).
ヘッダエリアで、プロジェクト番号を入力すると、プロジェクト番号をキーとして、契約情報から契約金額、プロジェクト番号、会計年月、受注番号等が読み出されて表示される。明細エリアで予算(プロジェクト種別、種別名、予算金額、プロジェクト原価科目、内訳予算額等)の項目を入力して、不図示の登録ボタンを押すと、入力された内容に応じた予算実行情報がデータファイル106eに登録される。 When a project number is entered in the header area, the contract amount, project number, accounting year and month, order number, etc. are read from the contract information using the project number as a key and displayed. When budget items (project type, type name, budget amount, project cost item, detailed budget amount, etc.) are entered in the details area and the register button (not shown) is pressed, the budget execution information according to the entered contents is registered in data file 106e.
図6に示す例では、プロジェクト番号「PJ0001」、契約金額「15,000,000」、会計年度「2020/11」、受注番号「JY0001-01」、登録日「2020/11」となっている。予算については、プロジェクト「02:建築一式」の予算金額は「5,000,000」、「A01:電気工事」の予算金額は、「6,000,000」の合計「11,000,000」となっている。予算の内訳は、プロジェクト種別「02:建築一式」は、主要材料費「3,000,000」、外注費「2,000,000」となっている。プロジェクト種別「A1:電気工事」は、主要材料費「2,000,000」、外注費「1,000,000」、労務費「3,000,000」となっている。 In the example shown in Figure 6, the project number is "PJ0001", the contract amount is "15,000,000", the fiscal year is "2020/11", the order number is "JY0001-01", and the registration date is "2020/11". As for the budget, the budget amount for project "02: Complete construction" is "5,000,000", and the budget amount for "A01: Electrical work" is "6,000,000", totaling "11,000,000". The budget breakdown is as follows: for project type "02: Complete construction", the main material cost is "3,000,000", and the subcontract cost is "2,000,000". For project type "A1: Electrical work", the main material cost is "2,000,000", the subcontract cost is "1,000,000", and the labor cost is "3,000,000".
(S2:発注登録処理)
図9及び図10を参照して、発注登録処理を詳細に説明する。図9は、発注登録画面の表示例を示す図である。図10は、発注情報の構成例を示す図である。
(S2: Order registration process)
The order registration process will be described in detail with reference to Figures 9 and 10. Figure 9 is a diagram showing a display example of an order registration screen. Figure 10 is a diagram showing a configuration example of order information.
発注登録部102cは、例えば、モニタ114に表示される発注登録画面上でのオペレータの操作等に応じて、対象のプロジェクトについて、発注情報を入力して、データファイル106eに登録する。 The order registration unit 102c, for example, inputs order information for the target project in response to an operator's operation on the order registration screen displayed on the monitor 114, and registers the information in the data file 106e.
発注登録画面では、発注登録時に品番を指定する。図10に示す発注登録画面の例では、発注番号、プロジェクト番号、発注日、受注番号、仕入先、会計年月、登録日等が表示されるヘッダエリアと、予算の明細(品番、品番名、発注金額、仕入予定日、原価分類)を入力する明細エリアを備えており、不図示の登録ボタンを押すことで、入力された内容に応じた発注情報がデータファイル106eに登録される。 In the order registration screen, a product number is specified when registering an order. The example order registration screen shown in FIG. 10 has a header area that displays the order number, project number, order date, order number, supplier, accounting year and month, registration date, etc., and a details area for inputting budget details (product number, product number name, order amount, planned purchase date, cost classification), and by pressing a register button (not shown), order information according to the input details is registered in data file 106e.
図9に示す例では、ヘッダエリアは、発注番号「HA0010」、プロジェクト番号「PJ0001」、発注日「2020/12/10」、受注番号「JY0001-01」、仕入先「千葉エンジアリング」、会計年月「2020/11」、登録日「2020/11 」となっている。 In the example shown in Figure 9, the header area contains the order number "HA0010", project number "PJ0001", order date "2020/12/10", order number "JY0001-01", supplier "Chiba Engineering", accounting year and month "2020/11", and registration date "2020/11".
明細エリアは、1行目は、品番「C001001」、品番名「電気工事 材料」、発注金額「2,000,000」、仕入予定日「2020/12/31」、原価分類「材料費」、2行目は、品番「C001002」、品番名「電気工事 外注」、発注金額「1,000,000」、仕入予定日「2020/12/20」、原価分類「外注費」となっている。 The details area has the following on the first line: product number "C001001", product name "Electrical work materials", order amount "2,000,000", planned purchase date "2020/12/31", and cost classification "Materials cost". The second line has the product number "C001002", product name "Electrical work outsourced", order amount "1,000,000", planned purchase date "2020/12/20", and cost classification "Outsourcing cost".
(S4:月次着地予想金額登録処理)
図11及び図12を参照して、月次着地予想金額登録処理を詳細に説明する。図11は、着地予想登録画面の表示例を示す図である。図12は、着地予想登録情報の構成例を示す図である。着地予想登録で工事の最終予想原価を登録する。
(S4: Monthly estimated landing amount registration process)
The monthly estimated cost registration process will be described in detail with reference to Fig. 11 and Fig. 12. Fig. 11 is a diagram showing a display example of an estimated cost registration screen. Fig. 12 is a diagram showing a configuration example of estimated cost registration information. The estimated final cost of the construction is registered in the estimated cost registration.
月次着地予想金額登録部102gは、例えば、モニタ114に表示される着地予想登録画面(図11参照)上でのオペレータの操作等に応じて、対象のプロジェクトについて、着地予想登録情報を入力して、データファイル106eに登録する。 The monthly estimated landing amount registration unit 102g inputs estimated landing amount registration information for the target project in response to, for example, an operator's operation on the estimated landing amount registration screen (see FIG. 11) displayed on the monitor 114, and registers the information in the data file 106e.
図11に示す着地予想登録画面で、プロジェクト種別、プロジェクト原価科目毎に今後発生が予想される原価を登録する。図11に示す着地予想登録画面は、プロジェクト番号、会計年月、受注番号が表示されるヘッダエリアと、工事情報(プロジェクト種別、プロジェクト原価科目、予算金額、発注済原価、累計発生原価、今後予想原価、最終着地予想金額)を入力するための明細エリアとを備えている。不図示の登録ボタンを押すことで、入力された内容に応じた着地予想登録情報がデータファイル106eに登録される。 On the estimated end result registration screen shown in FIG. 11, the costs expected to be incurred in the future are registered for each project type and project cost item. The estimated end result registration screen shown in FIG. 11 has a header area in which the project number, accounting year and month, and order number are displayed, and a details area for entering construction information (project type, project cost item, budget amount, ordered costs, accumulated costs incurred, future expected costs, and final estimated end result). By pressing the register button (not shown), estimated end result registration information corresponding to the contents entered is registered in data file 106e.
最終予想原価は、累計発生原価+今後予想原価で算出される。これは工事進捗基準案件の進捗率計算時の分母の要素となる。 The final estimated cost is calculated by adding the cumulative incurred costs plus the estimated future costs. This is the denominator when calculating the progress rate for construction progress-based projects.
図11に示す着地予想入力画面の例では、ヘッダエリアでは、プロジェクト番号「PJ0001」、会計年月「2020/12」、受注番号「JY0001」が表示されている。明細エリアでは、工事情報の1行目が、プロジェクト種別「建築一式」、プロジェクト原価科目「主要材料費」、予算金額「3,000,000」、発注済原価「1,000,000」、累計発生原価「0」、今後予想原価「1,500,000」、最終着地予想原価「1,500,000」となっている。 In the example of the expected end result input screen shown in FIG. 11, the header area displays the project number "PJ0001", the accounting year and month "2020/12", and the order number "JY0001". In the details area, the first line of the construction information displays the project type "Construction as a whole", project cost item "Major material cost", budget amount "3,000,000", ordered cost "1,000,000", accumulated incurred cost "0", future expected cost "1,500,000", and final expected cost "1,500,000".
(S4:期末時着時予想処理)
図13~図15を参照して、期末時着時予想処理を詳細に説明する。図13は、原価予想分類に基づく月別の原価予定金額の算出方法を説明するための図である。図14は、原価比例法に基づく、収益予定金額の算出方法を説明するための図である。図15は、収支予想データの出力例を示す図である。
(S4: End of period arrival time forecast processing)
The end-of-period arrival forecast process will be described in detail with reference to Figures 13 to 15. Figure 13 is a diagram for explaining a method for calculating a monthly estimated cost amount based on a cost forecast classification. Figure 14 is a diagram for explaining a method for calculating an estimated revenue amount based on the cost proportional method. Figure 15 is a diagram showing an example of output of income and expenditure forecast data.
原価予定金額算出部102dは、原価科目毎に規定される原価予想分類に基づいて、各原価科目の期末時原価予定金額を算出する。材料費及び外注費の原価予想分類は、時点原価予想を使用し、仕入予定月に原価を発生させてもよい。労務費、経費については、経過原価予想し、月次時点での原価発生金額と実行予算額から今後原価発生額を月割して計算することにしてもよい。 The estimated cost calculation unit 102d calculates the estimated cost amount at the end of the period for each cost item based on the estimated cost classification defined for each cost item. The estimated cost classification for material costs and subcontract costs may use a current cost forecast, with costs incurred in the planned month of purchase. For labor costs and expenses, a historical cost forecast may be used, and future costs may be calculated on a monthly basis based on the estimated cost amount at the monthly point in time and the actual budget amount.
また、収益予定金額算出部102eは、契約金額、累積発生原価、原価予定金額に基づいて、原価比例により対象のプロジェクトの期末時収益予定金額を算出する。収益予定金額算出部102eは、算出した期末時原価予定金額及び期末時予定収益金額に基づいた工事収支データ(図15参照)を出力する。 The estimated revenue calculation unit 102e also calculates the estimated end-of-term revenue of the target project in proportion to the cost based on the contract amount, the accumulated incurred costs, and the estimated cost amount. The estimated revenue calculation unit 102e outputs construction income and expenditure data (see FIG. 15) based on the calculated estimated end-of-term cost amount and estimated end-of-term revenue amount.
図13において、(1)原価分類マスタ106bに登録されている原価分類種別に対応する原価予想分類(時点原価予想or経過原価予想)に基づいて、月別に原価予定金額を計算する。
In FIG. 13, (1) the estimated cost amount is calculated for each month based on the cost forecast classification (current cost forecast or historical cost forecast) corresponding to the cost classification type registered in the
(a)材料費、外注費については、時点原価予想を使用する。
時点原価予想の場合は、仕入予定月に原価を発生させる。発注情報については納期月を原価計算対象とし、今後発注予定金額については工期最終月に原価発生金額とする。発注予定金額=(累計発生原価+今後予想原価)-発注済額で算出する。
(a) For material costs and subcontract costs, current cost estimates are used.
In the case of point-in-time cost forecasting, costs are incurred in the planned purchase month. For order information, the delivery month is the subject of cost calculation, and for future planned order amounts, the cost incurred amount is the final month of the construction period. Planned order amount = (cumulative incurred costs + future expected costs) - ordered amount.
(b)労務費、経費については、経過原価予想(出来高査定対象の外注費)を使用する。
経過原価予想の場合は、月次時点での原価発生金額と実行予算額から今後原価発生額を月割して計算する。
(b) For labor costs and expenses, use the estimated historical cost (outsourcing costs subject to performance appraisal).
In the case of a past cost forecast, the future cost to be incurred is calculated on a monthly basis based on the cost to be incurred at the monthly point in time and the actual budget amount.
図13において、工期10ヶ月、労務費予算300万、経過3ヶ月、原価発生90万の場合の残額を月割した例を示している。300万-90万で今後発生210万を残7か月で1か月30万発生予定とする。期末時点2021/3では原価金額180万となる。 Figure 13 shows an example of the remaining amount divided by month when the construction period is 10 months, the labor cost budget is 3 million, 3 months have passed, and costs incurred are 900,000. 3 million - 900,000 = 2.1 million to be incurred in the future, with 300,000 to be incurred per month for the remaining 7 months. At the end of the period, 2021/3, the cost amount will be 1.8 million.
図13に示す例では、「2020/10」、「2020/11」、「2020/12」の原価発生額は、それぞれ、「30万」の計「90万」である。労務費予算「300万」-発生済原価「90万」で今後、発生原価「210万」を、残7か月で1か月30万発生予定として、「2021/1」、「2021/2」、「2020/12」「2020/12」の原価発生額を、それぞれ、「30万」とする。 In the example shown in Figure 13, the costs incurred for "2020/10", "2020/11", and "2020/12" are each "300,000" for a total of "900,000". The labor cost budget of "3 million" minus the costs already incurred of "900,000" will result in future costs of "2.1 million", with 300,000 to be incurred per month over the remaining seven months, and the costs incurred for "2021/1", "2021/2", "2020/12", and "2020/12" will each be "300,000".
図14において、収益着地予想を行い、工事毎に、原価比例により売上進捗率を計算し、売上予定金額を算出する。原価比例法の計算項目要素は、契約金額、累計発生額、原価予定金額である。 In Figure 14, revenue is forecasted, and the sales progress rate is calculated for each project on a cost-proportional basis, and the estimated sales amount is calculated. The calculation items for the cost-proportional method are the contract amount, the accumulated amount incurred, and the estimated cost amount.
工事毎の売上金額の算出例(契約金額500万の場合)を示す。現時点である12月時点で2021/3の売上金額を予想する。売上金額=契約金額×(累計発生額/原価予定金額)である。 An example of calculating the sales amount for each construction project (when the contract amount is 5 million yen) is shown below. As of December, the sales amount for March 2021 is predicted. Sales amount = contract amount x (cumulative amount incurred / estimated cost amount).
図14に示す例では、年月「2020/10」については、売上金額「50万」、売上進捗率「10%」、累計発生額「30万」、原価予定金額「300万」、年月「2020/11」については、売上金額「100万」、売上進捗率「20%」、累計発生額「60万」、原価予定金額「300万」、年月「2020/12」については、売上金額「150万」、売上進捗率「30%」、累計発生額「90万」、原価予定金額「300万」となっている。12月時点で原価比例により、年月「2021/1」、「2021/2」、「2021/3」の進捗率を「40%」、「50%」、「60%」として、売上金額「200万」、「250万」、「300万」を算出する。 In the example shown in FIG. 14, for the year/month "2020/10", the sales amount is "500,000", the sales progress rate is "10%," the accumulated amount incurred is "300,000", and the planned cost amount is "3 million". For the year/month "2020/11", the sales amount is "1 million", the sales progress rate is "20%," the accumulated amount incurred is "600,000", and the planned cost amount is "3 million". For the year/month "2020/12", the sales amount is "1.5 million", the sales progress rate is "30%," the accumulated amount incurred is "900,000", and the planned cost amount is "3 million". As of December, the progress rates for the years/months "2021/1", "2021/2", and "2021/3" are set to "40%, "50%," and "60%" based on the cost ratio, and the sales amounts "2 million", "2.5 million", and "3 million" are calculated.
図15は、収支予想データの出力例を示している。この例では、会計年月「2020年12月」、出力年月「2020/12~2021/03」、プロジェクト「PJ0001」、プロジェクト名「設備建築一式」、契約番号「JYU0001」、契約金額「15,00,000」について、現在会計年月と未来月「2021/1」、「2021/2」、「2021/3」の売上(予定)金額、売上進捗率、累計発生原価、最終着地予想原価のデータが表示されている。売上(予定)金額については、現在会計年月は「3,125,000」、2021/1は「6,000,000」、2021/2は「7,625,000」、2021/3は、「8,000,000」となっている。 Figure 15 shows an example of income/expense forecast data output. In this example, for the accounting month and year "December 2020", output month and year "December 2020 - March 2021", project "PJ0001", project name "Facility Construction Complete", contract number "JYU0001", and contract amount "15,000,000", data on the (planned) sales amount, sales progress rate, cumulative incurred costs, and final estimated cost for the current accounting month and year and future months "January 2021", "February 2021", and "March 2021" is displayed. The (planned) sales amount is "3,125,000" for the current accounting month and year, "6,000,000" for January 2021, "7,625,000" for February 2021, and "8,000,000" for March 2021.
ドリルダウンすることで、プロジェクト種別毎の原価分類の累積発生原価のデータが表示される。さらに、ドリルダウンすることで、伝票種別、伝票番号、発生金額、仕入予定月のデータが表示される。このように、プロジェクト種別毎に、発注予定金額を出力することで原価分類毎の原価予定月の計画を促すことができる。 By drilling down, data on accumulated costs incurred for each cost category by project type is displayed. By drilling down further, data on document type, document number, incurred amount, and planned purchase month is displayed. In this way, outputting the planned order amount for each project type can encourage planning of the planned cost month for each cost category.
プロジェクト種別「電気工事」の例では、原価分類「主要材料費」について、発生金額「2,000,000」、仕入予定月「2021/1」、累計原価発生金額は、現在会計年月は「0」、2021/1は「2,000,000」、2021/2は「2,000,000」、2021/3は、「2,000,000」となっており、仕入予定月「2021/1」に原価が発生している(図9の例のケースで、時点原価予想により仕入予定月に原価発生)。 In the example of the project type "Electrical work", for the cost classification "Major material costs", the incurred amount is "2,000,000", the planned purchase month is "2021/1", and the cumulative incurred costs are "0" for the current accounting month, "2,000,000" for 2021/1, "2,000,000" for 2021/2, and "2,000,000" for 2021/3, with costs incurred in the planned purchase month of "2021/1" (in the case of the example in Figure 9, costs are incurred in the planned purchase month based on the current cost forecast).
また、原価分類「外注費」について、発生金額「1,000,000」、仕入予定月「2020/12」、累計原価発生金額は、現在会計年月は「1,000,000」、2021/1は「1,000,000」、2021/2は「1,000,000」、2021/3は、「1,000,000」となっており、仕入予定月「2020/12」に原価が発生している(図9の例のケースで12月に仕入済み)。 In addition, for the cost category "subcontract expenses," the amount incurred is "1,000,000," the planned purchase month is "2020/12," and the cumulative cost incurred amount is "1,000,000" for the current accounting month, "1,000,000" for 2021/1, "1,000,000" for 2021/2, and "1,000,000" for 2021/3, with costs incurred in the planned purchase month of "2020/12" (in the case of the example in Figure 9, purchases were made in December).
また、原価分類「労務費」について、累計原価発生金額は、現在会計年月は「900,000」、2021/1は「1,200,000」、2021/2は「1,500,000」、2021/3は、「1,800,000」となっている(経過原価予想で300,000ずつ月割されている)。 In addition, for the cost category "Labor costs," the cumulative cost incurred amount is "900,000" for the current accounting year and month, "1,200,000" for January 2021, "1,500,000" for February 2021, and "1,800,000" for March 2021 (divided into monthly increments of 300,000 based on the estimated past costs).
以上説明したように、本実施の形態によれば、対象のプロジェクトについて、予算金額、複数の原価科目、各原価科目の内部予算金額を含む実行予算情報を入力する実行予算登録部102bと、対象のプロジェクトについて、各原価科目の発注金額及び仕入予定日を含む発注情報を入力する発注登録部102cと、前記原価科目毎に規定される原価予想分類に基づいて、各原価科目の期末時原価予定金額を算出する原価予定金額算出部102dと、を備えている。また、前記各原価科目の期末時原価予定金額に基づいて、原価比例により対象のプロジェクトの期末時収益予定金額を算出する収益予定金額算出部102eを備えている。 As described above, according to this embodiment, the system includes an execution budget registration unit 102b for inputting execution budget information including the budget amount, multiple cost items, and internal budget amount of each cost item for the target project, an order registration unit 102c for inputting order information including the order amount and planned purchase date of each cost item for the target project, and a planned cost calculation unit 102d for calculating the planned end-of-period cost amount of each cost item based on the cost forecast classification defined for each cost item. In addition, the system includes a planned revenue calculation unit 102e for calculating the planned end-of-period revenue amount of the target project in proportion to the cost based on the planned end-of-period cost amount of each cost item.
これにより、進行基準を採用する場合に、早期に、期末時原価予定金額及び期末時収益予定金額を予想して、経営リソースを対策することで収益の改善を実現することが可能となる。 This means that when using the percentage of completion method, it is possible to predict the planned costs and revenues at the end of the period early on and improve profits by allocating management resources.
[4.他の実施形態]
本発明は、上述した実施形態以外にも、特許請求の範囲に記載した技術的思想の範囲内において種々の異なる実施形態にて実施されてよいものである。
4. Other embodiments
The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.
例えば、実施形態において説明した各処理のうち、自動的に行われるものとして説明した処理の全部または一部を手動的に行うこともでき、あるいは、手動的に行われるものとして説明した処理の全部または一部を公知の方法で自動的に行うこともできる。 For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using a known method.
また、本明細書中や図面中で示した処理手順、制御手順、具体的名称、各処理の登録データや検索条件等のパラメータを含む情報、画面例、データベース構成については、特記する場合を除いて任意に変更することができる。 In addition, the processing procedures, control procedures, specific names, registered data for each process, information including search conditions and other parameters, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.
また、プロジェクト管理装置100に関して、図示の各構成要素は機能概念的なものであり、必ずしも物理的に図示の如く構成されていることを要しない。
Furthermore, with regard to the
例えば、プロジェクト管理装置100が備える処理機能、特に制御部102にて行われる各処理機能については、その全部または任意の一部を、CPUおよび当該CPUにて解釈実行されるプログラムにて実現してもよく、また、ワイヤードロジックによるハードウェアとして実現してもよい。尚、プログラムは、本実施形態で説明した処理を情報処理装置に実行させるためのプログラム化された命令を含む一時的でないコンピュータ読み取り可能な記録媒体に記録されており、必要に応じてプロジェクト管理装置100に機械的に読み取られる。すなわち、ROMまたはHDD(Hard Disk Drive)などの記憶部などには、OSと協働してCPUに命令を与え、各種処理を行うためのコンピュータプログラムが記録されている。このコンピュータプログラムは、RAMにロードされることによって実行され、CPUと協働して制御部を構成する。
For example, the processing functions of the
また、このコンピュータプログラムは、プロジェクト管理装置100に対して任意のネットワークを介して接続されたアプリケーションプログラムサーバに記憶されていてもよく、必要に応じてその全部または一部をダウンロードすることも可能である。
This computer program may also be stored in an application program server connected to the
また、本実施形態で説明した処理を実行するためのプログラムを、一時的でないコンピュータ読み取り可能な記録媒体に格納してもよく、また、プログラム製品として構成することもできる。ここで、この「記録媒体」とは、メモリーカード、USB(Universal Serial Bus)メモリ、SD(Secure Digital)カード、フレキシブルディスク、光磁気ディスク、ROM、EPROM(Erasable Programmable Read Only Memory)、EEPROM(登録商標)(Electrically Erasable and Programmable Read Only Memory)、CD-ROM(Compact Disk Read Only Memory)、MO(Magneto-Optical disk)、DVD(Digital Versatile Disk)、および、Blu-ray(登録商標) Disc等の任意の「可搬用の物理媒体」を含むものとする。 In addition, the program for executing the processing described in this embodiment may be stored on a non-transitory computer-readable recording medium, or may be configured as a program product. Here, the term "recording medium" refers to a memory card, a USB (Universal Serial Bus) memory, a SD (Secure Digital) card, a flexible disk, a magneto-optical disk, a ROM, an EPROM (Erasable Programmable Read Only Memory), an EEPROM (registered trademark) (Electrically Erasable and Programmable Read Only Memory), a CD-ROM (Compact Disk Read Only Memory), an MO (Magneto-Optical disk), a DVD (Digital Versatile This includes any "portable physical media" such as a Blu-ray (registered trademark) Disc, and a Blu-ray (registered trademark) Disc.
また、「プログラム」とは、任意の言語または記述方法にて記述されたデータ処理方法であり、ソースコードまたはバイナリコード等の形式を問わない。なお、「プログラム」は必ずしも単一的に構成されるものに限られず、複数のモジュールやライブラリとして分散構成されるものや、OSに代表される別個のプログラムと協働してその機能を達成するものをも含む。なお、本実施形態に示した各装置において記録媒体を読み取るための具体的な構成および読み取り手順ならびに読み取り後のインストール手順等については、周知の構成や手順を用いることができる。 A "program" is a data processing method written in any language or description method, and may be in any format, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a distributed configuration consisting of multiple modules or libraries, and a program that works in conjunction with a separate program, such as an OS, to achieve its function. Note that the specific configuration and reading procedure for reading a recording medium in each device shown in this embodiment, as well as the installation procedure after reading, can use well-known configurations and procedures.
記憶部106に格納される各種のデータベース等は、RAM、ROM等のメモリ装置、ハードディスク等の固定ディスク装置、フレキシブルディスク、および、光ディスク等のストレージ手段であり、各種処理やウェブサイト提供に用いる各種のプログラム、テーブル、データベース、および、ウェブページ用ファイル等を格納する。
The various databases stored in the
また、プロジェクト管理装置100は、既知のパーソナルコンピュータまたはワークステーション等の情報処理装置として構成してもよく、また、任意の周辺装置が接続された当該情報処理装置として構成してもよい。また、プロジェクト管理装置100は、当該装置に本実施形態で説明した処理を実現させるソフトウェア(プログラムまたはデータ等を含む)を実装することにより実現してもよい。
The
更に、装置の分散・統合の具体的形態は図示するものに限られず、その全部または一部を、各種の付加等に応じてまたは機能負荷に応じて、任意の単位で機能的または物理的に分散・統合して構成することができる。すなわち、上述した実施形態を任意に組み合わせて実施してもよく、実施形態を選択的に実施してもよい。 Furthermore, the specific form of distribution and integration of the devices is not limited to that shown in the figures, and all or part of them can be functionally or physically distributed and integrated in any unit depending on various additions or functional loads. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively.
100 プロジェクト管理装置
102 制御部
102a マスタメンテ部
102b 実行予算登録部
102c 発注登録部
102d 原価予定金額算出部
102e 収益予定金額算出部
102f 画面表示制御部
102g 月次着地予想金額登録部
104 通信インターフェース部
106 記憶部
106a プロジェクト原価科目区分マスタ
106b 原価分類マスタ
106c 品番マスタ
106d プロジェクト種別マスタ
106e データファイル
108 入出力インターフェース部
112 入力装置
114 出力装置
200 サーバ
300 ネットワーク
100 Project management device 102 Control unit 102a Master maintenance unit 102b Execution budget registration unit 102c Order registration unit 102d Estimated cost amount calculation unit 102e Estimated revenue amount calculation unit 102f Screen display control unit 102g Monthly estimated
Claims (4)
前記制御部は、
対象のプロジェクトについて、予算金額、複数の原価科目、各原価科目の内部予算金額を含む実行予算情報を入力する実行予算入力手段と、
対象のプロジェクトについて、各原価科目の発注金額及び仕入予定日を含む発注情報を入力する発注情報入力手段と、
前記原価科目毎に規定される原価予想分類に基づいて、各原価科目の期末時原価予定金額を算出する原価予定金額算出手段と、
を備え、
(1)規定される原価予想分類が経過原価予想の場合、現在会計年月次時点での累計原価発生金額に、実行予算額から今後原価発生額を月割して計算した金額を、現在会計年月次後から期末までの月数分、順次加算して、期末時原価予定金額を算出し、(2)規定される原価予想分類が時点原価予想の場合、現在会計年月次までの累計発生原価に、現在会計年月次後から期末までに仕入予定月が含まれる発生金額を加算して、期末時原価予定金額を算出することを特徴とするプロジェクト管理装置。 A project management device including a control unit,
The control unit is
an actual budget input means for inputting actual budget information including a budget amount, a plurality of cost items, and an internal budget amount for each cost item for a target project;
An order information input means for inputting order information including an order amount and a planned purchase date for each cost item for a target project;
a cost forecast amount calculation means for calculating a final end cost forecast amount of each cost item based on a cost forecast classification defined for each cost item;
Equipped with
(1) when the cost forecast classification specified is a historical cost forecast, the device calculates the estimated cost at the end of the period by adding the amount calculated by dividing the future cost amount by the execution budget amount by the cumulative cost amount as of the current fiscal year and month, for the number of months from after the current fiscal year and month to the end of the period, in order to calculate the estimated cost amount at the end of the period; and (2) when the cost forecast classification specified is a current cost forecast, the device calculates the estimated cost amount at the end of the period by adding the amount of cost incurred from after the current fiscal year and month to the cumulative cost amount up to the current fiscal year and month, including the planned purchase month.
前記規定される原価予想分類は、前記取得手段で取得したものであること、The cost forecast classification defined is acquired by the acquisition means;
を特徴とする請求項1に記載のプロジェクト管理装置。2. The project management device according to claim 1, wherein:
前記制御部で実行される、Executed by the control unit,
対象のプロジェクトについて、予算金額、複数の原価科目、各原価科目の内部予算金額を含む実行予算情報を入力する実行予算入力工程と、an actual budget input process for inputting actual budget information including a budget amount, a number of cost items, and an internal budget amount for each cost item for a target project;
対象のプロジェクトについて、各原価科目の発注金額及び仕入予定日を含む発注情報を登録する発注情報登録工程と、An order information registration process for registering order information including an order amount and a planned purchase date for each cost item for the target project;
前記原価科目毎に規定される原価予想分類に基づいて、各原価科目の期末時原価予定金額を算出する原価予定金額算出工程と、a cost forecast amount calculation step of calculating a cost forecast amount at the end of a period for each cost item based on a cost forecast classification specified for each cost item;
を含み、Including,
(1)規定される原価予想分類が経過原価予想の場合、現在会計年月次時点での累計原価発生金額に、実行予算額から今後原価発生額を月割して計算した金額を、現在会計年月次後から期末までの月数分、順次加算して、期末時原価予定金額を算出し、(2)規定される原価予想分類が時点原価予想の場合、現在会計年月次までの累計発生原価に、現在会計年月次後から期末までに仕入予定月が含まれる発生金額を加算して、期末時原価予定金額を算出することを特徴とするプロジェクト管理方法。A project management method characterized in that (1) when the specified cost forecast classification is a historical cost forecast, the planned cost at the end of the period is calculated by adding the amount calculated by dividing the future costs to the actual budget amount by the number of months from after the current fiscal year to the end of the period to the accumulated costs incurred up to the current fiscal year, and (2) when the specified cost forecast classification is a point-in-time cost forecast, the planned cost at the end of the period is calculated by adding the amount incurred from after the current fiscal year to the end of the period, including the planned purchase month, to the accumulated costs incurred up to the current fiscal year.
前記制御部において、In the control unit,
対象のプロジェクトについて、予算金額、複数の原価科目、各原価科目の内部予算金額を含む実行予算情報を入力する実行予算入力工程と、an actual budget input process for inputting actual budget information including a budget amount, a number of cost items, and an internal budget amount for each cost item for a target project;
対象のプロジェクトについて、各原価科目の発注金額及び仕入予定日を含む発注情報を登録する発注情報登録工程と、An order information registration process for registering order information including an order amount and a planned purchase date for each cost item for the target project;
前記原価科目毎に規定される原価予想分類に基づいて、各原価科目の期末時原価予定金額を算出する原価予定金額算出工程と、a cost forecast amount calculation step of calculating a cost forecast amount at the end of a period for each cost item based on a cost forecast classification specified for each cost item;
を実行させるためのプログラムであり、This is a program for executing
(1)規定される原価予想分類が経過原価予想の場合、現在会計年月次時点での累計原価発生金額に、実行予算額から今後原価発生額を月割して計算した金額を、現在会計年月次後から期末までの月数分、順次加算して、期末時原価予定金額を算出し、(2)規定される原価予想分類が時点原価予想の場合、現在会計年月次までの累計発生原価に、現在会計年月次後から期末までに仕入予定月が含まれる発生金額を加算して、期末時原価予定金額を算出することを特徴とするプロジェクト管理プログラム。A project management program characterized in that (1) when the specified cost forecast classification is a historical cost forecast, the program adds the amount calculated by dividing future costs by the execution budget amount by the number of months from after the current fiscal year to the end of the fiscal year to calculate the planned cost amount at the end of the fiscal year, in order to the accumulated cost amount as of the current fiscal year and month, for the number of months from after the current fiscal year and month to the end of the fiscal year, in order to calculate the planned cost amount at the end of the fiscal year, and (2) when the specified cost forecast classification is a current cost forecast, the program adds the amount of costs incurred from after the current fiscal year and month to the end of the fiscal year, including the planned purchase month, in order to calculate the planned cost amount at the end of the fiscal year.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2024008921A JP7569462B2 (en) | 2020-07-31 | 2024-01-24 | Project management device, project management method, and project management program |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020131000A JP7428608B2 (en) | 2020-07-31 | 2020-07-31 | Project management device, project management method, and project management program |
| JP2024008921A JP7569462B2 (en) | 2020-07-31 | 2024-01-24 | Project management device, project management method, and project management program |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020131000A Division JP7428608B2 (en) | 2020-07-31 | 2020-07-31 | Project management device, project management method, and project management program |
Publications (3)
| Publication Number | Publication Date |
|---|---|
| JP2024028605A JP2024028605A (en) | 2024-03-04 |
| JP2024028605A5 JP2024028605A5 (en) | 2024-03-11 |
| JP7569462B2 true JP7569462B2 (en) | 2024-10-17 |
Family
ID=80263908
Family Applications (2)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020131000A Active JP7428608B2 (en) | 2020-07-31 | 2020-07-31 | Project management device, project management method, and project management program |
| JP2024008921A Active JP7569462B2 (en) | 2020-07-31 | 2024-01-24 | Project management device, project management method, and project management program |
Family Applications Before (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020131000A Active JP7428608B2 (en) | 2020-07-31 | 2020-07-31 | Project management device, project management method, and project management program |
Country Status (1)
| Country | Link |
|---|---|
| JP (2) | JP7428608B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2023162788A1 (en) | 2022-02-24 | 2023-08-31 | Agc株式会社 | Alkali-free glass and glass sheet |
| JP7791133B2 (en) * | 2023-04-20 | 2025-12-23 | 株式会社オービック | Landing prediction device, landing prediction method, and landing prediction program |
| JP7701411B2 (en) * | 2023-07-11 | 2025-07-01 | 株式会社オービック | Accounting support device, accounting support method, and accounting support program |
| JP2026044034A (en) * | 2024-08-29 | 2026-03-12 | 株式会社オービック | Cost accounting device, cost accounting method, and cost accounting program |
| JP2026053945A (en) * | 2024-09-13 | 2026-03-26 | 株式会社オービック | Sales basis management device, sales basis management method, and sales basis management program |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003296557A (en) | 2002-03-29 | 2003-10-17 | Kawasaki Steel Systems R & D Corp | Cost management system |
| JP2004303039A (en) | 2003-03-31 | 2004-10-28 | Kumagai Gumi Co Ltd | Construction cost management processing program |
-
2020
- 2020-07-31 JP JP2020131000A patent/JP7428608B2/en active Active
-
2024
- 2024-01-24 JP JP2024008921A patent/JP7569462B2/en active Active
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003296557A (en) | 2002-03-29 | 2003-10-17 | Kawasaki Steel Systems R & D Corp | Cost management system |
| JP2004303039A (en) | 2003-03-31 | 2004-10-28 | Kumagai Gumi Co Ltd | Construction cost management processing program |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2022027168A (en) | 2022-02-10 |
| JP7428608B2 (en) | 2024-02-06 |
| JP2024028605A (en) | 2024-03-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7569462B2 (en) | Project management device, project management method, and project management program | |
| JP7308338B1 (en) | Business support device, business support method, and business support program | |
| JP7445713B2 (en) | Allocation work support device, allocation work support method, and allocation work support program | |
| JP7654857B2 (en) | Project management device, project management method, and project management program | |
| JP7780408B2 (en) | Income and expenditure management device, income and expenditure management method, and income and expenditure management program | |
| JP7197989B2 (en) | Progress rate calculation device, progress rate calculation method, and progress rate calculation program | |
| JP7112294B2 (en) | Deposit schedule management device, deposit schedule management method, and deposit schedule management program | |
| JP7720264B2 (en) | Cost management device, cost management method, and cost management program | |
| JP2024085099A (en) | Data creation device, data creation method, and data creation program | |
| JP7791133B2 (en) | Landing prediction device, landing prediction method, and landing prediction program | |
| JP7542027B2 (en) | Output management device, output management method, and output management program | |
| JP7733043B2 (en) | Project management system, project management method, and project management program | |
| JP7280931B2 (en) | Information processing device, information processing method, and information processing program | |
| JP7705336B2 (en) | Progress management device, progress management method, and progress management program | |
| JP7028577B2 (en) | Construction price processing equipment, construction price processing method, and construction price processing program | |
| JP7812824B2 (en) | Cash flow planning device, cash flow planning method, and cash flow planning program | |
| JP7715683B2 (en) | Order entry device, order entry method, and order entry program | |
| JP7733037B2 (en) | Performance management device, performance management method, and performance management program | |
| JP7754873B2 (en) | Project management system, project management method, and project management program | |
| JP7812815B2 (en) | Accounting management device, accounting management method, and accounting management program | |
| JP7300431B2 (en) | Productivity Index Calculation Device, Productivity Index Calculation Method, and Productivity Index Calculation Program | |
| JP2026048255A (en) | Performance forecasting device, performance forecasting method, and performance forecasting program | |
| JP2026044034A (en) | Cost accounting device, cost accounting method, and cost accounting program | |
| JP2025082922A (en) | Project management device, project management method, and project management program | |
| JP2024088064A (en) | Common expense allocation processing device, common expense allocation processing method, and common expense allocation processing program |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20240222 |
|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20240222 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20240910 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20241004 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7569462 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |