JP7644038B2 - Landing forecast value management device, landing forecast value management method, and landing forecast value management program - Google Patents
Landing forecast value management device, landing forecast value management method, and landing forecast value management program Download PDFInfo
- Publication number
- JP7644038B2 JP7644038B2 JP2022018212A JP2022018212A JP7644038B2 JP 7644038 B2 JP7644038 B2 JP 7644038B2 JP 2022018212 A JP2022018212 A JP 2022018212A JP 2022018212 A JP2022018212 A JP 2022018212A JP 7644038 B2 JP7644038 B2 JP 7644038B2
- Authority
- JP
- Japan
- Prior art keywords
- value
- cost
- planned
- unassigned
- yen
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Financial Or Insurance-Related Operations Such As Payment And Settlement (AREA)
Description
本発明は、着地予想値管理装置、着地予想値管理方法、及び、着地予想値管理プログラムに関する。 The present invention relates to a landing prediction value management device, a landing prediction value management method, and a landing prediction value management program.
今日において、ソフトウェア又はシステムの開発、保守、運用における委託契約の一種であり、特定の業務に対して技術者の労働を提供するSES(システムエンジニアリングサービス)が知られている。 Today, there is a type of contract for the development, maintenance, and operation of software or systems, known as SES (System Engineering Services), which provides the labor of engineers for specific tasks.
また、特許文献1(特開2020-013600号公報)には、経営分析におけるユーザの手間を軽減し且つ経営改善に十分に資することを目的とした経営管理補助システムが開示されている。この経営管理補助システムの場合、複数のユーザが利用する複数のユーザ端末と、複数のユーザ端末と通信する中継サーバと、複数のユーザ端末及び中継サーバと通信する解析サーバとを備える。 Patent Document 1 (JP Patent Publication No. 2020-013600) discloses a business management support system that aims to reduce the user's workload in business analysis and to fully contribute to business improvement. This business management support system includes multiple user terminals used by multiple users, a relay server that communicates with the multiple user terminals, and an analysis server that communicates with the multiple user terminals and the relay server.
ユーザ端末は、ユーザの店舗における営業実績に関する情報及びユーザの店舗におけるコスト管理に関する情報を含むユーザ情報を中継サーバへ送信する。中継サーバは、ユーザ情報のうち特定のユーザ情報を解析サーバへ送信する。また、解析サーバは、特定のユーザ情報を所定の分析ルールに基づいて分析することにより、ユーザの店舗に関する経営管理情報を取得して複数のユーザ端末へ送信する。そして、ユーザ端末は、ユーザの指示に基づいて経営管理情報を階層的に表示する。 The user terminal transmits user information, including information on the sales performance of the user's store and information on cost management of the user's store, to the relay server. The relay server transmits specific user information from the user information to the analysis server. The analysis server also analyzes the specific user information based on predetermined analysis rules to obtain business management information on the user's store and transmits it to multiple user terminals. The user terminal then displays the business management information hierarchically based on the user's instructions.
また、この特許文献1の経営管理補助システムは、タイルは、解析サーバにおいて所定のルールに沿って算出された当月末時点での売上累計、原価率、及び人件費率の予測値(着地予想)を示し、それらの下方に、タイルに表示された当月の売上目標(売上計画)の日推移に対する当日までの売上実績の日推移を示す折れ線面グラフの拡大図を表示する。
In addition, in the business management support system of
ここで、ERP(Enterprise Resources Planning)等により、受注確度に応じた引合案件、又は、正式に契約が締結した受注案件等の情報は、担当する技術者のアサイン情報を関連付けて管理できる。また、引合又は受注の各予算に基づいて、案件の収支を積算することで、着地予想値を算出できる。 Here, by using ERP (Enterprise Resources Planning) or the like, information on inquiries based on the probability of receiving an order, or on orders for which a contract has been officially concluded, can be managed by linking it to the assignment information of the engineers in charge. In addition, the expected value can be calculated by accumulating the income and expenditure of the case based on the budget for each inquiry or order.
しかし、引合にも満たない将来発生する受注案件、及び、必要となる労務費等のコスト(=未アサイン原価)は、発生が予想されるにも関わらず、着地予想値に反映させることは困難であった。このため、算出される着地予想値が不正確な値となり、正確な案件管理に支障を来す問題があった。 However, it was difficult to reflect future orders that did not even meet the quotation and the necessary costs such as labor costs (= unassigned costs) in the final forecast, even though these were expected to occur. This resulted in inaccurate final forecasts, which hindered accurate project management.
本発明は、上述の課題に鑑みてなされたものであり、未アサイン原価を反映させた着地予想値を算出して、正確な案件管理を可能とした着地予想値管理装置、着地予想値管理方法、及び、着地予想値管理プログラムの提供を目的とする。 The present invention has been made in consideration of the above-mentioned problems, and aims to provide a forecasted final value management device, a forecasted final value management method, and a forecasted final value management program that calculates a forecasted final value that reflects unassigned costs, enabling accurate project management.
上述の課題を解決し、目的を達成するために、本発明に係る着地予想値管理装置は、案件に対する所定期間の費用として業務オペレータにより入力された費用の、未アサイン原価加算前における予定値である仮予定値を生成する仮予定値生成部と、所定期間における予定人工数を減算処理した値である未アサイン人工に月平均予定時間を乗算処理した乗算処理結果に時間単価を乗算処理することで、案件に対する費用としてアサインされていない費用である未アサイン原価を算出する未アサイン原価算出部と、仮予定値及び未アサイン原価を加算処理した値を、案件の所定期間における費用の予定値として生成する予定値生成部と、所定期間において確定した費用の実績値、及び、実績値が確定した時点以降の予定値の合計値を、通期における費用の予定値に対応する着地予想値として算出する着地予想値算出部と、費用の予定値に対応する着地予想値を出力する出力制御部と、を有する。 In order to solve the above-mentioned problems and achieve the object, the estimated final value management device of the present invention has a tentative planned value generation unit that generates a tentative planned value, which is a planned value before adding unassigned costs, of expenses input by a business operator as expenses for a specified period for a project ; an unassigned cost calculation unit that calculates unassigned costs, which are expenses not assigned as expenses for a project, by multiplying the unassigned labor, which is a value obtained by subtracting the planned labor force for the specified period, by the monthly average planned time and multiplying the result by the hourly rate; a planned value generation unit that generates a value obtained by adding the tentative planned value and the unassigned cost as a planned value of expenses for the specified period for the project; a planned final value calculation unit that calculates the sum of the actual value of expenses confirmed for the specified period and the planned value after the actual value was confirmed as a final forecast value corresponding to the planned value of expenses for the entire period; and an output control unit that outputs the forecast value corresponding to the planned value of expenses.
また、上述の課題を解決し、目的を達成するために、本発明に係る着地予想値管理方法は、仮予定値生成部が、案件に対する所定期間の費用として業務オペレータにより入力された費用の、未アサイン原価加算前における予定値である仮予定値を生成する仮予定値生成ステップと、未アサイン原価算出部が、所定期間における予定人工数を減算処理した値である未アサイン人工に月平均予定時間を乗算処理した乗算処理結果に時間単価を乗算処理することで、案件に対する費用としてアサインされていない費用である未アサイン原価を算出する未アサイン原価算出ステップと、予定値生成部が、仮予定値及び未アサイン原価を加算処理した値を、案件の所定期間における費用の予定値として生成する予定値生成ステップと、着地予想値算出部が、所定期間において確定した費用の実績値、及び、実績値が確定した時点以降の予定値の合計値を、通期における費用の予定値に対応する着地予想値として算出する着地予想値算出ステップと、出力制御部が、費用の予定値に対応する着地予想値を出力する出力制御ステップと、を有する。 In order to solve the above-mentioned problems and achieve the object, the estimated final value management method according to the present invention includes a provisional planned value generation step in which a provisional planned value generation unit generates a provisional planned value, which is a planned value before adding unassigned costs, of expenses input by a business operator as expenses for a specified period for a project ; an unassigned cost calculation step in which an unassigned cost calculation unit calculates unassigned costs, which are expenses not assigned as expenses for a project, by multiplying an unassigned labor-time, which is a value obtained by subtracting a planned labor-time number for the specified period, by a monthly average planned time, and multiplying the result by an hourly rate; a planned value generation step in which a planned value generation unit generates a value obtained by adding the provisional planned value and the unassigned cost, as a planned value of expenses for the specified period for the project; a final expected value calculation step in which a final expected value calculation unit calculates the sum of an actual value of expenses confirmed for the specified period and a planned value after the actual value is confirmed, as a final expected value corresponding to the planned value of expenses for the entire period; and an output control step in which an output control unit outputs the estimated value corresponding to the planned value of expenses.
また、上述の課題を解決し、目的を達成するために、本発明に係る着地予想値管理プログラムは、コンピュータを、案件に対する所定期間の費用として業務オペレータにより入力された費用の、未アサイン原価加算前における予定値である仮予定値を生成する仮予定値生成部と、所定期間における予定人工数を減算処理した値である未アサイン人工に月平均予定時間を乗算処理した乗算処理結果に時間単価を乗算処理することで、案件に対する費用としてアサインされていない費用である未アサイン原価を算出する未アサイン原価算出部と、仮予定値及び未アサイン原価を加算処理した値を、案件の所定期間における費用の予定値として生成する予定値生成部と、所定期間において確定した費用の実績値、及び、実績値が確定した時点以降の予定値の合計値を、通期における費用の予定値に対応する着地予想値として算出する着地予想値算出部と、費用の予定値に対応する着地予想値を出力する出力制御部として機能させること、を特徴とする。 In addition, in order to solve the above-mentioned problems and achieve the object, the estimated final value management program of the present invention causes a computer to function as a tentative planned value generation unit that generates a tentative planned value, which is a planned value before adding unassigned costs, of expenses input by a business operator as expenses for a specified period for a project ; an unassigned cost calculation unit that calculates unassigned costs, which are expenses not assigned as expenses for a project, by multiplying the unassigned labor, which is a value obtained by subtracting the planned labor force for the specified period, by the monthly average planned time and multiplying the result by the hourly rate; a planned value generation unit that generates a value obtained by adding the tentative planned value and the unassigned cost as a planned value of expenses for the specified period for the project; a final forecast value calculation unit that calculates the sum of the actual value of expenses confirmed for the specified period and the planned value after the actual value was confirmed as a final forecast value corresponding to the planned value of expenses for the entire period; and an output control unit that outputs the estimated value corresponding to the planned value of expenses.
本発明によれば、未アサイン原価を反映させた着地予想値を算出して、正確な案件管理を行うことができるという効果を奏する。 The present invention has the effect of enabling accurate project management by calculating a projected end value that reflects unassigned costs.
以下、本発明を適用した実施の形態となる業務管理装置を、図面に基づいて詳細に説明する。なお、本実施形態により本発明が限定されるものではない。 Below, a business management device according to an embodiment of the present invention will be described in detail with reference to the drawings. Note that the present invention is not limited to this embodiment.
(ハードウェア構成)
図1は、実施の形態の業務管理装置1のハードウェア構成を示すブロック図である。この図1に示すように、業務管理装置1は、記憶部2、制御部3、通信インターフェース部4及び入出力インターフェース部5を備えている。
(Hardware configuration)
1 is a block diagram showing the hardware configuration of a
入出力インターフェース部5には、入力装置6及び出力装置7が接続されている。出力装置7としては、モニタ装置(家庭用テレビを含む)等の表示部を用いることができる。 An input device 6 and an output device 7 are connected to the input/output interface unit 5. The output device 7 can be a display unit such as a monitor device (including a home television).
入力装置6としては、キーボード装置及びマウス装置、及びマイクロホン装置の他、マウス装置と協働してポインティングデバイス機能を実現するモニタ装置を用いることができる。 As the input device 6, a keyboard device, a mouse device, a microphone device, or a monitor device that cooperates with the mouse device to realize a pointing device function can be used.
記憶部2としては、例えばROM(Read Only Memory)、RAM(Random Access Memory)、HDD(Hard Disk Drive)又はSSD(Solid State Drive)等の記憶装置を用いることができる。記憶部2には、それぞれ記憶領域である、原価要素マスタ11、予定単価マスタ12、部署マスタ13、及び、社員マスタ14が形成されている。また、記憶部2には、それぞれ記憶領域である、原価要素テーブル15、予定単価テーブル16、部署テーブル17、社員テーブル18、直接プロジェクトテーブル(直接PJテーブル)19、予算テーブル20、及び、仮想PJテーブル21が形成されている。また、記憶部2には、それぞれ記憶領域である組織別着地予想テーブル22、要員管理テーブル23、未アサインテーブル24、売上テーブル25、及び、経費テーブル26が形成されている。
The
(業務管理装置の機能構成)
また、記憶部2には、業務管理プログラムが記憶されている。制御部3は、この業務管理プログラムを実行することで、マスタ設定部31、入力処理部32、データ生成部33、記憶制御部34、演算部35、及び、表示制御部36として機能する。データ生成部33は、仮予定値生成部、予定値生成部及び計画値生成部の一例である。また、演算部35は、未アサイン原価算出部、及び、着地予想値算出部の一例である。また、表示制御部36は、出力制御部の一例である。
(Functional configuration of the business management device)
Furthermore, a business management program is stored in the
マスタ設定部31は、原価要素マスタ11、予定単価マスタ12、部署マスタ13、及び、社員マスタの設定を行う。入力処理部32は、マスタ設定時等に業務オペレータの入力操作に対応するコマンド等を取得する。データ生成部33は、プロジェクト(案件)に対する収支の計画値又は予定値等を生成する。記憶制御部34は、各種マスタ11~14及び各種テーブル15~26に対する各種データの記憶及び読み出し制御を行う。演算部35は、未アサイン原価を反映させた予定値、及び、着地予想値等を算出する。表示制御部36は、着地予想値等を表示部の一例である出力装置7を介して表示する。
The master setting unit 31 sets the cost element master 11, planned
(用語の定義)
次に、以下の各用語は、主に、以下に示す意味で用いることとする。
(Definition of terms)
Next, the following terms are primarily used in the following sense.
・計画値:期首等に計画される組織別の目標値等の売上、原価の計画数値、
・予定値:各案件の実行予算等の積み上げから算出される売上、原価の予定数値、
・実績値:実際に売上検収又は稼働時間等の発生原価により発生する売上、原価の実績数値。
・Planned values: Sales and cost targets for each organization planned at the beginning of the fiscal year, etc.
・Expected value: The estimated sales and cost figures calculated from the sum of the execution budgets of each project, etc.
・Actual value: The actual sales and costs incurred based on sales inspection, operating hours, etc.
・要員管理登録:受注等の案件に技術者をアサインして、予定されている1人月等の人工を登録すること、
・アサイン労務費:受注などの案件にアサインされている人毎の労務費原価。ランク又は契約形態によって金額が決まる、
・未アサイン原価:案件にアサインされていないが、将来的に発生が見込まれている人毎の労務費原価。自社社員及び協力会社社員共に発生する。ランク又は契約形態によって金額が決まる。
・ Personnel management registration: Assigning engineers to orders and other projects and registering the planned man-months, etc.
・Assigned labor cost: Labor cost for each person assigned to a project such as an order. The amount is determined by rank or contract type.
・Unassigned cost: Labor cost for each person who is not assigned to a project but is expected to be incurred in the future. It is incurred by both the company's own employees and employees of partner companies. The amount is determined by rank or contract type.
・実行予算:案件毎に引合又は受注のタイミングで見積られる売上、原価予定の収支計画、
・着地予想値:実績値が確定した当月までの実績値、及び、翌月以降の予定値の合計値で示される、通期の予想収支の値、
・直接プロジェクト(直接PJ):引合又は受注案件等のように、実際に売上又は費用が発生する案件、
・仮想プロジェクト(仮想PJ):組織別に集計した仮想的な案件。
・Working budget: Sales and cost forecast income and expenditure plan estimated at the time of inquiry or order for each project,
・Forecasted value: The forecasted income and expenditure for the full fiscal year, calculated by adding up the actual values up to the current month for which the actual values have been confirmed, and the forecast values for the following month and thereafter.
Direct projects (direct PJ): Projects that actually generate sales or expenses, such as inquiries or orders.
- Virtual Project (Virtual PJ): A hypothetical case aggregated by organization.
(着地予想値の概要)
図2は、着地予想値の概要を示す図である。この図2に示すように着地予想値としては、プロジェクトの「売上」の着地予想値、「直接費」の着地予想値、「間接費」の着地予想値、「販売管理費(販管費)」の着地予想値が算出される。
(Summary of expected landing value)
2 is a diagram showing an overview of the estimated values. As shown in this figure, the estimated values calculated are the estimated value of "sales", the estimated value of "direct costs", the estimated value of "indirect costs", and the estimated value of "selling and administrative expenses (SG&A expenses)" of the project.
例えば、「売上」における計画値の着地予想値は、期首~基準年月(=過去)における計画値の合計額と、基準年月の翌月~期末(=未来)における計画値の合計額とを加算処理して算出される。また、「売上」における予定値の着地予想値は、期首~基準年月(=過去)における実際の売上額の合計額と、基準年月の翌月~期末(=未来)における予定値の合計額とを加算処理して算出される。 For example, the estimated end value of the planned value for "Sales" is calculated by adding together the total of the planned values from the beginning of the period to the base month (= past) and the total of the planned values from the month following the base month to the end of the period (= future). Similarly, the estimated end value of the planned value for "Sales" is calculated by adding together the total of the actual sales amounts from the beginning of the period to the base month (= past) and the total of the planned values from the month following the base month to the end of the period (= future).
また、詳しくは後述するが、実施の形態の業務管理装置1の場合、未アサイン原価は、間接費に対して加算するようになっている。このため、「間接費」における予定値の着地予想値は、「期首~基準年月(=過去)における実際の売上額の合計額と未アサイン原価を加算処理した額」と、「基準年月の翌月~期末(=未来)における予定値の合計額と未アサイン原価を加算処理した額」との合計額として算出される。
In addition, as will be described in more detail later, in the case of the
一例ではあるが、労務費に関して、要員管理で登録されていない未アサイン担当者の予定原価を含めて見込み原価の出力が可能となっている(抽出条件の期首会計年月から1年分)。すなわち、基準年月の月末日で社員マスタ14を参照することで、未アサイン担当者として、例えば「田中さん」を検出する。また、社員マスタ14から、例えば「システム1部」等の所属部署の部署コードを取得する。また、社員マスタ14から、田中さんの予定単価コード、及び、例えば「160時間」等の、田中さんの月平均労働時間を取得する。また、社員マスタ14から取得した田中さんの予定単価コードに基づいて、予定単価マスタを参照し、例えば「5000円」等の時間単価を検出する。
As an example, it is possible to output estimated costs for labor costs, including the planned costs of unassigned personnel not registered in personnel management (for one year from the beginning accounting month of the extraction conditions). That is, by referencing the
そして、田中さんの時間単価に、田中さんの月平均労働時間を乗算処理することで、田中さんの労務費が算出される(5000円×160時間=労務費80万円)。 Tanaka's hourly rate is then multiplied by his average monthly working hours to calculate his labor costs (5,000 yen x 160 hours = labor costs of 800,000 yen).
次に、基準年月翌月~期末の月毎に、要員管理の未割当工数(1-割当工数)から未割当工数金額(未アサイン原価)を算出する。例えば基準年月が12月の場合において、1月の割当工数が「0.7」の場合、「労務費80万円×(1-0.7)=未アサイン原価24万円」となる。同様に、2月の割当工数が「0」の場合、「労務費80万円×(1-0)=未アサイン原価80万円」となる。同様に、3月の割当工数が「0」の場合、「労務費80万円×(1-0)=未アサイン原価80万円」となる。 Next, for each month from the month following the base month through the end of the period, the unallocated man-hours amount (unassigned cost) is calculated from the unallocated man-hours (1 - assigned man-hours) in personnel management. For example, if the base month is December, and the assigned man-hours for January are "0.7", then "labor cost 800,000 yen x (1 - 0.7) = unassigned cost 240,000 yen." Similarly, if the assigned man-hours for February are "0", then "labor cost 800,000 yen x (1 - 0) = unassigned cost 800,000 yen." Similarly, if the assigned man-hours for March are "0", then "labor cost 800,000 yen x (1 - 0) = unassigned cost 800,000 yen."
次に、基準年月翌月~期末までの労務費見込みに未アサイン原価を加算処理し、社員原価(見込み)を算出する。例えば、基準年月が12月の場合において、1月の直接PJの予算(労務費)が120万円の場合、この120万円に、1月の未アサイン原価である24万円を加算処理することで、1月の社員原価(見込み)として144万円を算出する。同様に、2月の直接PJの予算(労務費)が140万円の場合、この140万円に、2月の未アサイン原価である80万円を加算処理することで、2月の社員原価(見込み)として220万円を算出する。同様に、3月の直接PJの予算(労務費)が30万円の場合、この30万円に、3月の未アサイン原価である80万円を加算処理することで、3月の社員原価(見込み)として110万円を算出する。 Next, the unassigned cost is added to the estimated labor cost from the month following the base month to the end of the term to calculate the employee cost (estimate). For example, if the base month is December and the direct project budget (labor cost) for January is 1.2 million yen, the unassigned cost for January of 240,000 yen is added to this 1.2 million yen to calculate the employee cost (estimate) for January of 1.44 million yen. Similarly, if the direct project budget (labor cost) for February is 1.4 million yen, the unassigned cost for February of 800,000 yen is added to this 1.4 million yen to calculate the employee cost (estimate) for February of 2.2 million yen. Similarly, if the direct project budget (labor cost) for March is 300,000 yen, the unassigned cost for March of 800,000 yen is added to this 300,000 yen to calculate the employee cost (estimate) for March of 1.1 million yen.
図3は、間接費の通期の予定値に対して未アサイン原価を反映させた組織別着地予想表の一例を示す図である。この図3の例では、一見、売上見通しが、計画よりも+60万となっており、直接費の見通しも+15万なので、順調そうに見える。しかしながら、実際は、未アサイン技術者のコスト増加が見込まれており、それに伴い間接費及び販管費が増加して、営業利益は-90万の着地予想となる。 Figure 3 shows an example of a forecast table by organization that reflects unassigned costs against the planned overhead for the entire year. In the example of Figure 3, at first glance, the sales forecast is +600,000 compared to the plan, and the direct costs are also +150,000, so things look good. However, in reality, an increase in the costs of unassigned engineers is expected, which will lead to increases in overhead and selling and administrative expenses, resulting in a forecast operating profit of -900,000.
もし、未アサイン原価を含めずに着地予想値を算出すると、間接費の着地予想値が少なくなる(予定間接費30万→20万)。この結果、利益が出るように誤った判断が行われる(営業利益150万→240万)。実施の形態の業務支援装置1は、未アサイン原価を加算処理して着地予想値を算出しているため、このような誤った判断を防止して、プロジェクトの正確な管理が可能となっている。
If the estimated final value is calculated without including unassigned costs, the estimated final value of indirect costs will be lower (planned indirect costs: 300,000 → 200,000). This will result in an erroneous judgment that a profit will be made (operating profit: 1.5 million → 2.4 million). The
(各種マスタに対する設定動作)
図4は、各種マスタに対して設定されるデータを説明するための図である。このうち、図4(a)は、原価要素マスタ11に対して設定されるデータを示す図である。この図4(a)に示すように、原価要素マスタ11には、例えば「G01:直接費」、「G02:間接費」、「G90:販管費」等の原価要素コード及び原価要素名が設定(登録)される。なお、原価要素マスタ11の代わりに原価要素テーブル15を設け、この原価要素テーブル15に、上述の原価要素コード及び原価要素名を設定してもよい。
(Settings for various masters)
Fig. 4 is a diagram for explaining data set for various masters. Of these, Fig. 4(a) is a diagram showing data set for the cost element master 11. As shown in Fig. 4(a), cost element codes and cost element names such as "G01: direct cost", "G02: indirect cost", "G90: selling and general administrative cost" are set (registered) in the cost element master 11. Note that a cost element table 15 may be provided instead of the cost element master 11, and the above-mentioned cost element codes and cost element names may be set in this cost element table 15.
図4(b)は、予定単価マスタ12に対して設定されるデータを示す図である。この図4(b)に示すように、予定単価マスタ12には、例えば「YT01」、「YT02」等の予定単価コード、「部長単価」、「課長単価」等の予定単価名、「G01」等の原価要素コード、及び、「5000円」、「4000円」等の時間単価が設定(登録)される。なお、予定単価マスタ12の代わりに予定単価テーブル16を設け、この予定単価テーブル16に、上述の予定単価コード及び時間単価等を設定してもよい。
Figure 4(b) is a diagram showing data set in the planned
図4(c)は、部署マスタ13に対して設定されるデータを示す図である。この図4(c)に示すように、部署マスタ13には、例えば「S01:システム1部」、「S02:システム2部」等の部署コード及び部署名が設定(登録)される。なお、部署マスタ13の代わりに部署テーブル17を設け、この部署テーブル17に、上述の部署コード及び部署名を設定してもよい。
Figure 4(c) is a diagram showing data set in the
図4(d)は、社員マスタ14に対して設定されるデータを示す図である。この図4(d)に示すように、社員マスタ14には、例えば「SH01」、「SH02」等の社員コード、「田中」、「鈴木」等の社員名、「S01」等の部署コード、「YT01」、「YT02」等の予定単価コード、及び、「160時間」等の月平均予定時間が設定(登録)される。なお、社員マスタ14の代わりに社員テーブル18を設け、この社員テーブル14に、上述の社員コード及び月平均予定時間を設定してもよい。
Figure 4(d) is a diagram showing data set in the
(着地予想管理動作)
以下、実施の形態の業務支援装置1における着地予想管理動作を説明する。
(Landing prediction management operation)
The landing prediction management operation in the
(期首時点での組織別計画予算の登録)
まず、例えば2021年4月等の期首時点において、組織別(部署毎)に形成される仮想的な案件である仮想PJに対して計画予算の登録を行う。図5は、この仮想PJに対する計画予算の登録動作の流れを示すフローチャートである。
(Registering planned budgets by organization at the beginning of the period)
First, a planned budget is registered for a virtual project, which is a hypothetical project formed by organization (department), at the beginning of a term, such as April 2021. FIG. 5 is a flowchart showing the flow of the operation of registering a planned budget for this virtual project.
仮想PJの形成時となると、業務オペレータは、仮想PJを担当する部署の部署コード、部署名、及び、期間を入力する。入力処理部32は、このような入力データを取得し、データ生成部33は、取得された入力データに基づいて、図6に例示する「KP001」等の仮想プロジェクト番号、「S01」等の部署コード、「システム1部」等の部署名、及び、「2021年4月~2022年3月」等の期間を含む仮想PJデータを生成する。このうち、仮想プロジェクト番号は、業務管理装置1側で自動採番される。記憶制御部34は、生成された仮想PJデータを、仮想PJテーブル21に記憶する(ステップS1)。
When it is time to create a virtual project, the business operator inputs the department code, department name, and period of the department in charge of the virtual project. The input processing unit 32 acquires such input data, and the
次に、業務オペレータは、仮想プロジェクト番号に関連付けて、要素、及び、期首である4月から、期末である翌年3月の間の予算をそれぞれ入力する。具体的には、予算データとしては、上述の期間の月毎に、売上、直接費、間接費、販管費及び営業利益の各予算が入力される。入力処理部32は、このような入力データを取得し、データ生成部33は、取得された入力データに基づいて、図7に例示する予算データを生成する。記憶制御部34は、生成された予算データを予算テーブル20に記憶する(ステップS2)。
Next, the business operator inputs the elements and the budget from April, which is the start of the term, to March of the following year, which is the end of the term, in association with the virtual project number. Specifically, the budget data includes the budgets for sales, direct costs, indirect costs, selling and general administrative expenses, and operating profit for each month of the above-mentioned period. The input processing unit 32 acquires this input data, and the
次に、データ生成部33は、図8に例示するように、仮想PJテーブル21に記憶された仮想PJデータに対して、上述の期間内における引合又は受注案件等の、実際に売上又は費用が発生した直接PJの直接プロジェクト番号を関連付けする(ステップS3:仮想プロジェクトの更新処理)。この期首の時点では、直接PJは発生していないため、この時点では、データ生成部33は、仮想プロジェクトの更新処理は行わない。
Next, as shown in FIG. 8, the
次に、業務オペレータにより仮想PJの着地予想確認が指定されると、演算部35は、売上、直接費、間接費、販管費、及び、営業利益の各計画値の各月の予算の合計額を算出する。データ生成部33は、演算部35により算出された、売上、直接費、間接費、販管費、及び、営業利益の各計画値の各月の予算の合計額を、売上、直接費、間接費、販管費、及び、営業利益の各計画値の着地予想値として、組織別予想テーブル22に記憶する。また、表示制御部36は、図9に示すように、売上、直接費、間接費、販管費、及び、営業利益の計画値の着地予想値、各月の計画値及び合計額を反映させた組織別着地予想表を、出力装置7に表示する(ステップS5)。
Next, when the business operator specifies confirmation of the virtual project's final forecast, the
なお、この期首の時点では、引合又は受注案件等は発生していないため、予定値の着地予想値及び実績値の着地予想値は算出されず、また、組織別着地予想表には表示されない。 Note that, since there are no inquiries or orders at the beginning of this period, the estimated planned value and the estimated actual value have not been calculated, and are not displayed in the estimated value by organization table.
(直接PJの受注処理)
次に、図10は、仮想PJの形成後に、実際に受注された直接プロジェクトの処理の流れを示すフローチャートである。この場合、受注された直接プロジェクトの登録処理がデータ生成部33により行われる(ステップS11)。具体的には、例えば図11に示すように「600万円」のプロジェクトを受注したとすると、業務オペレータの入力に基づいて、データ生成部33により、例えば「P001」等のプロジェクト番号、「システム1部」等の部署名、「600万円」等の契約金額、「受注」等の受注区分、及び、4月~6月分としてそれぞれ「200万円」が割り当てられた売上予定金額を含む直接PJデータが生成される。記憶制御部34は、この直接PJデータを、直接PJテーブル19に記憶する。
(Direct project order processing)
Next, Fig. 10 is a flow chart showing the flow of processing of a direct project that has actually been received after the formation of a virtual project. In this case, the
次に、4月~6月のプロジェクトを担当する社員の割り当て処理である要員管理登録処理が行われる(ステップS12)。具体的には、業務オペレータは、図12に示すように社員マスタ14及び予定単価マスタ12を参照することで、4月~6月のプロジェクトを担当する社員を選択する。図12の例は、4月~6月のプロジェクトの担当者として、「田中さん」が選択された例である。また、業務オペレータは、社員マスタ14に記憶されている田中さんの月平均予定時間に基づいて、4月~6月の予定人工を入力する。図12の例は、田中さんの4月の人工として「0.7人月」が入力され、5月及び6月の人工としてそれぞれ「1人月」が入力された例である。
Next, the personnel management registration process is performed, which is the process of assigning employees to be in charge of the April to June projects (step S12). Specifically, the business operator selects employees to be in charge of the April to June projects by referring to the
データ生成部33は、業務オペレータの入力に基づいて、図12に示すように「P001」等のプロジェクト番号、「田中」等の社員名、「4月」等の月、及び、「0.7人月」又は「1人月」等の予定人工を含む要員管理データを生成する。
Based on the input from the business operator, the
また、演算部35は、図12に示すように、田中さんの月平均予定時間(=160時間)を社員マスタ14から検出すると共に、田中さんの時間単価(=5000円)を検出する。そして、演算部35は、以下の演算を行うことで、4月~6月の直接費を算出する。
As shown in FIG. 12, the
4月分→160時間×0.7人月×5000円=560000円
5月分→160時間×1.0人月×5000円=800000円
6月分→160時間×1.0人月×5000円=800000円
April → 160 hours x 0.7 man-months x 5,000 yen = 560,000 yen May → 160 hours x 1.0 man-months x 5,000 yen = 800,000 yen June → 160 hours x 1.0 man-months x 5,000 yen = 800,000 yen
記憶制御部34は、このように算出された4月~6月の直接費を、要員管理データに関連付けて要員管理テーブル23に記憶する。
The
次に、図13に示すように、業務オペレータにより、案件別予算登録画面を介して、直接PJの予算情報の登録処理が行われる(ステップS13)。具体的には、業務オペレータは、この案件別予算登録画面に対して、上述の「600万円」の直接プロジェクトに対応する、4月~6月の各月の売上予定金額として「200万円」の売上予定金額を入力する。また、業務オペレータは、案件別予算登録画面に対して、4月~6月の月毎の間接費としてそれぞれ「20万円」を入力すると共に、間接費の合計額である「60万円」を入力する。また、業務オペレータは、案件別予算登録画面に対して、4月の販管費として「14万円」を入力し、5月及び6月の販管費としてそれぞれ「20万円」を入力する。 Next, as shown in FIG. 13, the business operator registers the budget information for the direct project via the project-specific budget registration screen (step S13). Specifically, the business operator inputs a projected sales amount of "2 million yen" for each month from April to June, which corresponds to the above-mentioned "6 million yen" direct project, into this project-specific budget registration screen. The business operator also inputs "200,000 yen" for each month of April to June into the project-specific budget registration screen, as well as "600,000 yen" as the total amount of overhead. The business operator also inputs "140,000 yen" as the selling and general administrative expenses for April, and "200,000 yen" for the selling and administrative expenses for May and June into the project-specific budget registration screen.
なお、図12を用いて説明したように、「56万円」、「80万円」及び「80万円」の、4月~6月の月毎の直接費及び各月の合計額(216万円)は、記憶制御部34により、要員管理テーブル23から読み出され、案件別予算登録画面に自動的に入力される。
As explained using FIG. 12, the direct costs for each month from April to June of "560,000 yen," "800,000 yen," and "800,000 yen," as well as the total amount for each month (2,160,000 yen), are read from the personnel management table 23 by the
また、演算部35は、月毎に「売上-(直接費+間接費+販管費)」の演算を行うことで、4月分は「110万円」、5月分は「80万円」及び6月分は「80万円」の営業利益を算出する。また、演算部35は、4月~6月の営業利益を加算処理することで、「270万円」の営業利益の合計額を算出する。表示制御部34は、演算部35により算出された各月の営業利益及び合計額を案件別予算登録画面に表示する。
The
記憶制御部34は、このような売上、直接費、間接費、販管費及び営業利益の予算データを、案件別予算データとして予算テーブル20に記憶する。
The
このように、受注したプロジェクトに対応する直接PJデータ及び案件別予算データの登録処理が行われると、データ生成部33は、図14に示すように、仮想PJテーブル21に記憶されている仮想PJデータに対して、図11を用いて説明した直接PJデータのプロジェクト番号(P001)を登録する(ステップS14:仮想PJの更新処理)。これにより、仮想PJと直接PJとが関連付けされる。
In this way, when the registration process of the direct project data and case-specific budget data corresponding to the received project is performed, the
次に、実施の形態の業務管理装置1は、プロジェクトに対してアサインされていないが、将来的に発生が見込まれている人毎の労務費原価である未アサイン原価を反映させない状態の組織別着地予想表、又は、未アサイン原価を反映させた状態の組織別着地予想表を選択して表示可能となっている。
Next, the
すなわち、業務オペレータにより、未アサイン原価を反映させない状態の組織別着地予想表の表示が選択されると、図10のフローチャートのステップS15(Yes)及びステップS16(No)を介して処理がステップS18に進む。そして、表示制御部36により、未アサイン原価を反映させない状態の組織別着地予想表が生成されて表示される。
That is, when the business operator selects to display the organization-specific forecasted outcome table without reflecting the unassigned costs, the process proceeds to step S18 via step S15 (Yes) and step S16 (No) in the flowchart of FIG. 10. Then, the
具体的には、図15は、未アサイン原価を反映させずに生成した組織別着地予想表の一例を示す図である。この場合、記憶制御部34は、図9を用いて説明した売上、直接費、間接費、販管費、及び、営業利益の計画値の着地予想値が記憶されている組織別着地予想テーブル22に、予算テーブル20に記憶されている案件別予算データ(図13参照)で示される、4月~6月の、売上、直接費、間接費、販管費、及び、営業利益の予定値、予定値の合計値、及び、予定値の合計額に相当する着地予想値を登録する。
Specifically, FIG. 15 is a diagram showing an example of an organization-specific forecast table generated without reflecting unassigned costs. In this case, the
図15の例は、図9を用いて説明した売上、直接費、間接費、販管費、及び、営業利益の計画値の着地予想値が記憶されている組織別着地予想テーブル22に、4月~6月の売上の予定値としてそれぞれ「200万円」が登録された例である。また、図15の例は、上述の組織別着地予想テーブル22に、4月~6月の直接費の予定値としてそれぞれ「56万円」、「80万円」、「80万円」が登録された例である。 The example in FIG. 15 is an example in which "2 million yen" is registered as the planned value for sales from April to June in the organization-specific forecast table 22, which stores the forecast values for planned values of sales, direct costs, indirect costs, selling and general administrative expenses, and operating profit explained using FIG. 9. Also, the example in FIG. 15 is an example in which "560,000 yen," "800,000 yen," and "800,000 yen" are registered as the planned values for direct costs from April to June in the organization-specific forecast table 22 described above.
また、図15の例は、上述の組織別着地予想テーブル22に、4月~6月の間接費の予定値としてそれぞれ「20万円」、「20万円」、「20万円」が登録され、販管費の予定値として「14万円」、「20万円」、「20万円」が登録された例である。また、図15の例は、4月~6月の営業利益の予定値として、演算部35により「110万円」、「80万円」、「80万円」が算出され、記憶制御部34により、上述の組織別着地予想テーブル22に登録された例である。
The example in FIG. 15 is an example in which "200,000 yen", "200,000 yen", and "200,000 yen" are registered as the planned values of overhead for April to June, and "140,000 yen", "200,000 yen", and "200,000 yen" are registered as the planned values of selling and general administrative expenses in the above-mentioned organization-specific forecast table 22.
The example in FIG. 15 is an example in which "1,100,000 yen", "800,000 yen", and "800,000 yen" are calculated by the
表示制御部36は、このように組織別着地予想テーブル22に登録されている売上、直接費、間接費、販管費、及び、営業利益の各着地予想値を読み出して、未アサイン原価を反映させない状態の組織別着地予想表を生成し、出力装置7に表示する。
The
一方、業務オペレータにより、未アサイン原価を反映させた状態の組織別着地予想表の表示が選択されると、図10のフローチャートのステップS15(Yes)及びステップS16(Yes)を介して処理がステップS17に進む。そして、表示制御部36により、未アサイン原価を反映させた状態の組織別着地予想表が表示される。
On the other hand, when the business operator selects to display the organization-specific forecasted end result table reflecting the unassigned costs, the process proceeds to step S17 via step S15 (Yes) and step S16 (Yes) in the flowchart of FIG. 10. Then, the
具体的には、演算部35は、図16に示すように社員マスタ14を参照し、社員マスタ14に登録されている各社員である、例えば田中さん、鈴木さん、及び、佐藤さんの月平均予定時間を検出する。また、演算部35は、予定単価マスタ12を参照し、田中さん、鈴木さん、及び、佐藤さんの時間単価を検出する。そして、演算部35は、「未アサイン人工×月平均予定時間×時間単価」の演算を行うことで「未アサイン労務費原価(未アサイン原価)」を算出する。
Specifically, as shown in FIG. 16, the
具体的には、図12に示したように、田中さんの4月における予定人工は「0.7人月」である。このため、田中さんの4月における未アサイン人工は、図16に示すように「0.3人月」となる。この場合、演算部35は、「0.3人月×160時間×5000円=24万円」の演算を行うことで、4月における田中さんの未アサイン原価を算出する。また、図12に示したように、田中さんの5月及び6月における予定人工は「1人月」である。このため、田中さんの5月及び6月における未アサイン人工は、図16に示すように「0人月」となる。この場合、演算部35は、「0人月×160時間×5000円=0万円」の演算を行うことで、5月及び6月における田中さんの未アサイン原価を算出する。
Specifically, as shown in FIG. 12, Tanaka's planned man-months in April are "0.7 man-months". Therefore, Tanaka's unassigned man-months in April are "0.3 man-months" as shown in FIG. 16. In this case, the
また、この時点で受注している直接PJは、図11に示したように4月~6月分として受注した「P001」のプロジェクトである。このため、田中さんの7月~翌年3月までの間の予定人工は「0人月」となる。このため、演算部35は、「1人月×160時間×5000円=80万円」の演算を行うことで、7月~翌年3月における田中さんの未アサイン原価を算出する。
The direct project that has been received at this point is project "P001", which has been received for April to June, as shown in Figure 11. Therefore, Tanaka's planned man-months from July to March of the following year are "0 man-months". Therefore, the
これに対して、鈴木さんの時間単価は「4000円」である。このため、演算部35は、「1人月×160時間×4000円=64万円」の演算を行うことで、4月~翌年3月における鈴木さんの未アサイン原価を算出する。同様に、佐藤さんの時間単価は「3000円」である。このため、演算部35は、「1人月×160時間×3000円=48万円」の演算を行うことで、4月~翌年3月における佐藤さんの未アサイン原価を算出する。
In contrast, Suzuki's hourly rate is "4,000 yen." Therefore, the
次に、演算部35は、図16に示すように田中さん、鈴木さん及び佐藤さんの月毎の未アサイン原価を加算処理し、各月の未アサイン原価の合計額を算出する。例えば、4月における田中さん、鈴木さん及び佐藤さんの未アサイン原価は、それぞれ「24万円」、「64万円」及び「48万円」である。このため、演算部35は、「24万円+64万円+48万円」の演算を行うことで「計136万円」を、4月分の未アサイン原価として算出する。
Next, as shown in FIG. 16, the
また、5月分の及び6月分は、田中さんの未アサイン原価が「0万円」であるため、演算部35は、「0万円+64万円+48万円」の演算を行うことで「計112万円」を、5月分及び6月分の未アサイン原価として算出する。また、7月~翌年3月は、この時点では直接PJ受注していないため、演算部35は、「80万円+64万円+48万円」の演算を行うことで「計192万円」を、7月~翌年3月の各月の未アサイン原価として算出する。
Furthermore, since Tanaka's unassigned costs for May and June are "0 yen," the
ここで、プロジェクトの受注が無く、未アサインの状態でその月を終えた場合、プロジェクトに関連する直接原価ではなく、間接原価として計上されるため、演算部35は、未アサイン原価を、図17の矢印に示すように、その所属組織の間接労務費(間接費)の予定値に加算する。
If there are no orders for the project and the month ends with the work unassigned, it is recorded as an indirect cost rather than a direct cost related to the project, so the
すなわち、未アサイン原価を反映させない場合、図15に示すように4月~6月における間接費の予定値は、それぞれ「20万円」、「20万円」及び「20万円」であり、合計額は「60万円」であった。未アサイン原価を反映させる場合、演算部35は、「20万円」、「20万円」及び「20万円」の間接費の予定値に、上述のように算出した4月分~6月分の未アサイン原価である「136万円」、「112万円」及び「112万円」を加算処理する。
In other words, when the unassigned costs are not reflected, the planned overhead costs for April to June are "200,000 yen," "200,000 yen," and "200,000 yen," respectively, totaling "600,000 yen," as shown in FIG. 15. When the unassigned costs are reflected, the
これにより、図17に示すように、4月~6月に対する、未アサイン原価を含めた間接費の予定値として、「20万円+136万円=156万円」、「20万円+112万円=132万円」、「20万円+112万円=132万円」の予定値を得ることができる。また、プロジェクトが受注されていない7月~翌年3月に対する、未アサイン原価を含めた間接費の予定値としては、「0万円+192万円=192万円」の予定値とすることができる。 As a result, as shown in Figure 17, the planned overhead costs, including unassigned costs, for April to June can be calculated as "200,000 yen + 1,360,000 yen = 1,560,000 yen," "200,000 yen + 1,120,000 yen = 1,320,000 yen," and "200,000 yen + 1,120,000 yen = 1,320,000 yen." In addition, the planned overhead costs, including unassigned costs, for the period from July to March of the following year, when no project has been received, can be calculated as "0 yen + 1,920,000 yen = 1,920,000 yen."
演算部35は、4月~翌年3月までの、未アサイン原価を含めた間接費の予定値の合計額(図17の例の場合は、2148万円)を算出し、この合計額を、未アサイン原価を含めた間接費の予定値の着地予想値とする。また、演算部35は、売上、直接費、間接費、販管費の予定値をそれぞれ加算処理することで、営業利益の予定値を算出する。具体的には、4月分の営業利益の予定値は、「200万円+56万円+(-156万円)+14万円=-26万円」とのように算出され、5月分及び6月分の営業利益の予定値は、「200万円+80万円+(-132万円)+20万円=-32万円」とのように算出される。そして、演算部35は、4月~6月の営業利益の予定値を加算処理することで「-192万円」の営業利益の予定値の合計額を算出し、この「-192万円」を営業利益の予定値の着地予想値とする。
The
記憶制御部34は、このような未アサイン原価を含めたかたちの着地予想値を組織別着地予想テーブル22に記憶する。表示制御部36は、組織別着地予想テーブル22に登録されている売上、直接費、間接費、販管費、及び、営業利益の各着地予想値を読み出して、図17に示すように、未アサイン原価を含めた状態の組織別着地予想表を出力装置7に表示する。
The
このように、未アサイン原価を組織別の将来原価に組み込んで表示することで、将来の未アサイン原価を、事務コストを掛けずに把握することができる(事務労力の軽減)。これにより組織別の事業計画において、日々変動する着地予想数字の正確性を向上させることができる。 In this way, by incorporating unassigned costs into future costs by organization and displaying them, future unassigned costs can be understood without incurring administrative costs (reducing administrative labor). This makes it possible to improve the accuracy of forecast figures, which fluctuate daily, in business plans by organization.
また、プロジェクトの受注が無く、未アサインの状態でその月を終えた場合、プロジェクトに関連する費用は、直接原価ではなく、間接原価として計上される。このため、実施の形態の業務管理装置1では、未アサイン原価を、その所属組織の間接労務費(間接費)の予定値に加算している。これにより、組織別の直接費/間接費の比率等も容易に把握可能とすることができ、単なる組織別の事業計画に対する達成/未達との評価だけでなく、同じ売上額、営業利益の組織であっても、各プロジェクトの直接原価が高く、売上利益率が悪い(=利益の低い労働集約型のプロジェクトが多い)のか、間接原価が高く、各プロジェクトの利益は高いが、アサインが適切に行われていないため、営業利益を効率的に得られない等の分析を可能とすることができる。
In addition, if there is no order for a project and the month ends with the project unassigned, the costs related to the project are recorded as indirect costs, not direct costs. For this reason, in the
図3の例を用いて、再度説明すると、図3の例の場合、4月~6月の売上の実績値が「90万円+90万円+90万円=270万円」である。この実績値に、7月~翌年3月の売上の予定値である「110万円×9か月分=990万円」を加算処理すると、合計額及び着地予想値が「1260万円」となる。この「1260万円」という着地予想値は、当初の売上の計画値が「100万円×12か月で「1200万円」であったため、6月の時点で売上の着地予想値が「+60万円」となり、売上は順調である。また、直接費の費用も、当初計画した「600万円」に対して、6月の時点で「(40万円×3か月)+(55万円×9か月)=615万円」の着地予想値であり、当初の予定よりも「15万円」分、多くの経費が発生しているが、こちらも略順調であると言える。 To explain again using the example of Figure 3, in the example of Figure 3, the actual sales value from April to June is "900,000 yen + 900,000 yen + 900,000 yen = 2.7 million yen". If the planned sales value from July to March of the following year, "1.1 million yen x 9 months = 9.9 million yen", is added to this actual value, the total amount and the expected value is "12.6 million yen". This expected value of "12.6 million yen" is because the initial planned sales value was "1 million yen x 12 months = 12 million yen", so the expected sales value as of June is "+600,000 yen", and sales are going well. In addition, the expected direct expenses as of June are "(400,000 yen x 3 months) + (550,000 yen x 9 months) = 6.15 million yen" compared to the initially planned "6 million yen", and although expenses have been incurred by "150,000 yen" more than initially planned, this can also be said to be approximately good.
しかし、間接費の当初の計画値は、「20万円×12か月=240万円」であったが、「10万円×3か月=30万円」の実績値に、未アサイン原価を加算した予定値である「30万円×9か月=270万円」を加算処理すると、実績値の着地予想値が「300万円」となる。これは、当初の計画よりも「60万円」分、多い額の間接費を要することを意味しており、プロジェクトは計画通りに順調に進んでいるとは言えないことが分かる。 However, while the initial planned value for overhead was "200,000 yen x 12 months = 2.4 million yen," when the actual value of "100,000 yen x 3 months = 300,000 yen" is added to the planned value of "300,000 yen x 9 months = 2.7 million yen" by adding the unassigned costs, the expected actual value becomes "3 million yen." This means that overhead costs will be "600,000 yen" more than originally planned, and it can be said that the project is not progressing smoothly as planned.
また、このような間接費の増加に伴い、販管費も、当初の計画よりも「75万円」分の増加となっている((10万円×12か月)-(20万円×3か月)+(15万円×9か月))。 In addition, due to this increase in overhead costs, selling and administrative expenses have also increased by 750,000 yen from the initial plan ((100,000 yen x 12 months) - (200,000 yen x 3 months) + (150,000 yen x 9 months)).
そして、このようなことから未アサイン原価を含めると、6月時点での営業利益の着地予想値は「150万円」となり、当初の計画であった「240万円」よりも、「90万円」分、少ないことが分かる。 And because of this, if unassigned costs are included, the estimated final operating profit as of June is 1.5 million yen, which is 900,000 yen less than the initial plan of 2.4 million yen.
もし、未アサイン原価を含めなかった場合、図15に示したように、間接費の予定値が「20万円」となり、未アサイン原価を含めた間接費の予定値である「30万円」よりも少ない金額となる。このため、未アサイン原価を含めなかった場合、営業利益の着地予想値が「240万円」となる。従って、未アサイン原価を含めなかった場合には、当初の計画どおりの利益が得られるとの、誤った認識がされる。 If unassigned costs are not included, as shown in Figure 15, the planned overhead cost will be "200,000 yen," which is less than the planned overhead cost including unassigned costs, which is "300,000 yen." For this reason, if unassigned costs are not included, the expected final operating profit will be "2.4 million yen." Therefore, if unassigned costs are not included, it will be mistakenly believed that the profit will be as originally planned.
しかし、未アサイン原価を含めた場合には、上述のように、将来的に発生する間接費及びそれに伴い発生する販管費等を反映させることができるため、正確な着地予想値を得ることができ、プロジェクトの計画の見直し及び経費削減等の修正措置を取ることができる。 However, if unassigned costs are included, as mentioned above, it is possible to reflect future indirect costs and associated selling and general administrative expenses, etc., resulting in an accurate forecast value, which allows for revisions to the project plan and corrective measures such as cost reductions.
(プロジェクトの売上の計上動作)
次に、図18は、上述の直接PJに対する売上の登録処理の流れを示すフローチャートである。例えば、図19に示すように、上述の受注した直接プロジェクトの4月分の売上として、当初予定していた200万円の売上予定金額に対して、250万円の売上金額が得られたとする。この場合、業務オペレータは、250万円の売上入力を行う。データ生成部33は、売上月が4月分で250万円の売上の売上データを生成する。記憶制御部34は、この売上データを、売上テーブル25に記憶する(ステップS21)。
(Project sales recording operation)
Next, Fig. 18 is a flow chart showing the flow of the registration process of sales for the above-mentioned direct project. For example, as shown in Fig. 19, assume that the sales amount for April of the above-mentioned received direct project is 2.5 million yen, compared to the initially planned sales amount of 2 million yen. In this case, the business operator inputs the sales amount of 2.5 million yen. The
次に、業務オペレータは、図20に示すように、4月に、実際に発生した直接費、間接費及び販管費の入力を行う。この図20の例は、4月において、「60万円」の直接費が発生し、「130万円」の間接費が発生し、「20万円」の販管費が発生した例である。データ生成部33は、このような4月に発生した直接費、間接費及び販管費の経費データを生成する。記憶制御部34は、この経費データを経費テーブル26に記憶する(ステップS22)。
Next, the business operator inputs the direct costs, indirect costs, and selling and general administrative expenses that were actually incurred in April, as shown in FIG. 20. In the example of FIG. 20, direct costs of "600,000 yen" were incurred in April, indirect costs of "1.3 million yen" were incurred, and selling and administrative expenses of "200,000 yen" were incurred. The
次に、経費データが経費テーブル26に記憶された後に組織別着地予想表の表示が指定されると(ステップS23:Yes)、表示制御部36は、ステップS24において、売上テーブル25に記憶されている上述の売上データ、及び、経費テーブル26に記憶されている上述の経費データを反映させた、図21に例示する組織別着地予想表を表示する。この図21の例の場合、4月の売上の実績値に対して、上述の「250万円」が反映され、4月の直接費、間接費、及び、販管費に、それぞれ「60万円」、「130万円」、及び、「20万円」が反映された例である。表示制御部36は、4月の売上が計上された時点における売上、直接費、間接費、及び、販管費の実績値の合計額である「250万円」、「60万円」、「130万円」、及び、「20万円」を組織別着地予想表に反映させる。
Next, when the display of the organization-specific forecast table is specified after the expense data is stored in the expense table 26 (step S23: Yes), the
また、演算部35は。売上における「250万円」の実績値に、「200万円×11か月=2200万円」の予定値を加算処理することで「2450万円」の着地予想値を算出する。表示制御部36は、この「2450万円」の売上の着地予想値を、組織別着地予想表に反映させる。
The
また、演算部35は、4月分の間接費の実績値である「130万円」に、5月分の未アサイン原価を反映させた間接費の予定値である「132万円」、及び、6月分の未アサイン原価を反映させた間接費の予定値である「132万円」を加算処理することで「394万円」を算出する。また、演算部35は、7月~翌年3月の未アサイン原価を反映させた間接費の予定値の合計額(192万円×9か月=1728万円)を算出する。そして、「394万円+1728万円」の演算を行うことで「2122万円」を算出する。表示制御部36は、この「2122万円」を、間接費の実績値の着地予想値として組織別着地予想表に表示する。
The
また、演算部35は、4月分の販管費の実績値である「20万円」に、5月分の販管費の予定値である「20万円」、及び、6月分の販管費の予定値である「20万円」を加算処理して「60万円」を算出する。表示制御部36は、この「60万円」を、販管費の実績値の着地予想値として組織別着地予想表に表示する。
The
また、この例の場合、演算部35は、4月分の売上、直接費、間接費、及び、販管費の実績値に基づいて、「250万円-60万円-130万円-20万円」の演算を行うことで、4月分の営業利益の実績値として「-40万円」を算出する。表示制御部36は、この「-40万円」を、4月分の営業利益の実績値の着地予想値として組織別着地予想表に表示する。
In this example, the
また、この例の場合、演算部35は、売上、直接費、間接費、及び、販管費の各実績値の着地予想値に基づいて「2450万円-220万円-2122万円-60万円」の演算を行うことで、「48万円」の営業利益の着地予想値を算出する。表示制御部36は、この「40万円」を、営業利益の実績値の着地予想値として組織別着地予想表に表示する。
In this example, the
(新たな新規プロジェクト受注時の動作)
次に、新規プロジェクトを新たに受注した際における、実施の形態の業務管理装置1の動作を、図22のフローチャートを用いて説明する。一例ではあるが、例えば図23に示すように、契約金額が「800万円」で、受注区分が「引合」の新規プロジェクトを新たに受注すると、図22のフローチャートのステップS31からステップS32に処理が進む。このような新規プロジェクトを新たに受注すると、業務オペレータは、図23に示すように「システム1部」等の部署、「800万円」等の契約金額、及び、「引合」等の受注区分を入力操作する。なお、「P002」等のプロジェクト番号は、業務支援装置1により自動採番される。
(Operation when receiving a new project)
Next, the operation of the
また、業務オペレータは、図23に示すように、受注した新規プロジェクトの売上予定月、及び、売上予定金額を入力操作する。図23の例は、「800万円」の契約金額のうち、5月に「400万円」を売り上げ、残り「400万円」を6月に売り上げる予定とした例である。 The business operator also inputs the expected sales month and expected sales amount of the new project that has been received, as shown in Figure 23. The example in Figure 23 shows that, of the contract amount of "8 million yen," "4 million yen" is to be sold in May, and the remaining "4 million yen" is to be sold in June.
データ生成部33は、このような業務オペレータの入力操作に対応して、図23に示した内容の直接PJデータを生成する。記憶制御部34は、この直接PJデータを、直接PJテーブル19に記憶する(ステップS32)。
The
次に、5月及び6月のプロジェクトを担当する社員の割り当て処理である要員管理登録処理が行われる(ステップS33)。具体的には、業務オペレータは、図24に示すように社員マスタ14及び予定単価マスタ12を参照することで、5月及び6月のプロジェクトを担当する社員を選択する。図24の例は、5月及び6月のプロジェクトの担当者として、「鈴木さん」が選択された例である。また、業務オペレータは、社員マスタ14に記憶されている鈴木さんの月平均予定時間に基づいて、5月及び6月の予定人工を入力する。図24の例は、鈴木さんの5月及び6月の予定人工として「0.8人月」がそれぞれ入力された例である。
Next, the personnel management registration process is performed, which is the process of assigning employees to be in charge of the May and June projects (step S33). Specifically, the business operator selects the employees to be in charge of the May and June projects by referring to the
データ生成部33は、業務オペレータの入力に基づいて、図24に示すように「P002」等のプロジェクト番号、「鈴木」等の社員名、「5月」等の月、及び、「0.8人月」等の予定人工を含む要員管理データを生成する。
Based on the input from the business operator, the
また、演算部35は、図24に示すように、鈴木さんの月平均予定時間(=160時間)を社員マスタ14から検出すると共に、鈴木さんの時間単価(=4000円)を検出する。そして、演算部35は、以下の演算を行うことで、4月及び6月の直接費を算出する。
As shown in FIG. 24, the
5月分→160時間×0.8人月×4000円=512000円
6月分→160時間×0.8人月×4000円=512000円
May: 160 hours x 0.8 man-months x 4,000 yen = 512,000 yen June: 160 hours x 0.8 man-months x 4,000 yen = 512,000 yen
記憶制御部34は、このように算出された5月及び6月の直接費を、要員管理データに関連付けて要員管理テーブル23に記憶する。
The
次に、図25に示すように、業務オペレータにより、案件別予算登録画面を介して、直接PJの予算情報の登録処理が行われる(ステップS34)。具体的には、業務オペレータは、この案件別予算登録画面に対して、上述の「800万円」の直接プロジェクトに対応する5月及び6月の売上予定金額として、「400万円」の売上予定金額をそれぞれ入力する。また、業務オペレータは、案件別予算登録画面に対して、5月及び6月の月毎の間接費として、それぞれ「20万円」を入力すると共に、間接費の合計額である「40万円」を入力する。また、業務オペレータは、案件別予算登録画面に対して、5月及び6月の販管費として、それぞれ「20万円」を入力する。 Next, as shown in FIG. 25, the business operator registers the budget information for the direct project via the project-specific budget registration screen (step S34). Specifically, the business operator inputs a planned sales amount of "4 million yen" into the project-specific budget registration screen as the planned sales amount for May and June corresponding to the above-mentioned "8 million yen" direct project. The business operator also inputs "200,000 yen" into the project-specific budget registration screen as the monthly overhead for May and June, and inputs "400,000 yen" as the total overhead amount. The business operator also inputs "200,000 yen" into the project-specific budget registration screen as the selling and general administrative expenses for May and June.
なお、図24を用いて説明したように、それぞれ「512000円」である、5月及び6月の月毎の直接費及び各月の合計額(1024000円)は、記憶制御部34により、要員管理テーブル23から読み出され、案件別予算登録画面に自動的に入力される。
As explained using FIG. 24, the direct costs for May and June, which are "512,000 yen" each, and the total amount for each month (1,024,000 yen) are read from the personnel management table 23 by the
また、演算部35は、月毎に「売上-(直接費+間接費+販管費)」の演算を行うことで、5月分は「296万円」及び6月分も「296万円」の営業利益を算出する。また、演算部35は、5月及び6月の営業利益を加算処理することで、「592万円」の営業利益の合計額を算出する。表示制御部34は、演算部35により算出された各月の営業利益及び合計額を案件別予算登録画面に表示する。
The
記憶制御部34は、このような売上、直接費、間接費、販管費及び営業利益の予算データを、案件別予算データとして予算テーブル20に記憶する。
The
このように、受注したプロジェクトに対応する直接PJデータ及び案件別予算データの登録処理が行われると、データ生成部33は、図26に示すように、仮想PJテーブル21に記憶されている仮想PJデータに対して、図23を用いて説明した直接PJデータのプロジェクト番号(P002)を登録する(ステップS35:仮想PJへの自動反映処理)。これにより、仮想PJに対して、前回受注した「P001」のプロジェクト番号の直接PJ、及び、今回受注した「P002」のプロジェクト番号の直接PJが、それぞれ関連付けされる。
In this way, when the registration process of the direct project data and case-specific budget data corresponding to the received project is performed, the
次に、実施の形態の業務管理装置1は、プロジェクトに対してアサインされていないが、将来的に発生が見込まれている人毎の労務費原価である未アサイン原価を反映させない状態の組織別着地予想表、又は、未アサイン原価を反映させた状態の組織別着地予想表を選択して表示可能となっている。
Next, the
すなわち、業務オペレータにより、未アサイン原価を反映させない状態の組織別着地予想表の表示が選択されると、図22のフローチャートのステップS36(Yes)及びステップS37(No)を介して処理がステップS39に進む。そして、表示制御部36により、図27に模式的に示すように、予算テーブル20aに記憶されている「P001」のプロジェクト番号の直接PJ、及び、予算テーブル20bに記憶されている「P002」のプロジェクト番号の直接PJに対応する、未アサイン原価を反映させない状態の組織別着地予想表が生成されて表示される。
That is, when the business operator selects to display the organization-specific forecasted outcome table without reflecting the unassigned costs, the process proceeds to step S39 via step S36 (Yes) and step S37 (No) in the flowchart of FIG. 22. Then, the
具体的には、組織別着地予想表に対して未アサイン原価を反映させるか否かは、図28に示す抽出画面で選択可能となっている。実施の形態の業務管理装置1の場合、この抽出画面において、所望の基準年月及び部門コードを指定し、受注(含む/含まない)、引合(含む/含まない)及び未アサイン原価(含む/含まない)を選択可能となっている。図28の抽出画面の例は、受注を「含む」、引合を「含む」、未アサイン原価を「含まない」として選択した例である。
Specifically, whether or not to reflect unassigned costs in the organization-specific forecast table can be selected on the extraction screen shown in FIG. 28. In the case of the
このように未アサイン原価を含まない場合、表示制御部36は、図27に示す4月分の売上、直接費、間接費、販管費及び営業利益は、上述の「P001」のプロジェクト番号の直接PJの4月分の売上、直接費、間接費、販管費及び営業利益を、組織別着地予想表にそのまま反映させる。これにより、組織別着地予想表の4月分の売上の計画値、予定値及び実績値は、それぞれ「300万円」、「200万円」及び「250万円」のように表示される。また、4月分の直接費の計画値、予定値及び実績値は、それぞれ「150万円」、「56万円」及び「60万円」のように表示される。4月分の間接費の計画値、予定値及び実績値は、それぞれ「50万円」、「136万円」及び「130万円」のように表示される。また、4月分の販管費の計画値、予定値及び実績値は、それぞれ「50万円」、「14万円」及び「20万円」のように表示される。4月分の営業利益の計画値、予定値及び実績値は、それぞれ「50万円」、「-26万円」及び「40万円」のように表示される。
In this way, when unassigned costs are not included, the
また、演算部35は、図27に示す「P001」のプロジェクト番号の直接PJの5月分の売上、直接費、間接費、販管費、営業利益と、「P002」のプロジェクト番号の直接PJの5月分の売上、直接費、間接費、販管費、営業利益とを加算処理する。表示制御部36は、このように算出された5月分の売上、直接費、間接費、販管費、営業利益の加算金額を、図28に示すように組織別着地予想表の5月の売上、直接費、間接費、販管費、営業利益の予定値として表示する。これにより、組織別着地予想表の5月の売上、直接費、間接費、販管費、営業利益の予定値として、それぞれ「600万円」、「131.2万円」、「40万円」、「40万円」、「476万円」がそれぞれ表示される。
The
同様に、演算部35は、図27に示す「P001」のプロジェクト番号の直接PJの6月分の売上、直接費、間接費、販管費、営業利益と、「P002」のプロジェクト番号の直接PJの6月分の売上、直接費、間接費、販管費、営業利益とを加算処理する。表示制御部36は、このように算出された6月分の売上、直接費、間接費、販管費、営業利益の加算金額を、図28に示すように組織別着地予想表の5月の売上、直接費、間接費、販管費、営業利益の予定値として表示する。これにより、組織別着地予想表の6月の売上、直接費、間接費、販管費、営業利益の予定値として、それぞれ「600万円」、「131.2万円」、「40万円」、「40万円」、「476万円」がそれぞれ表示される。
Similarly, the
また、演算部35は、4月分の売上の実績値である「250万円」に、5月の売上の予定値である「600万円」及び6月の売上の予定値である「600万円」を加算処理することで「1450万円」の着地予想値を算出する。表示制御部36は、この「1450万円」の着地予想値を、売上の着地予想値として組織別着地予想表に表示する。
The
また、演算部35は、4月分の直接費の実績値である「60万円」に、5月の直接費の予定値である「131.2万円」及び6月の直接費の予定値である「131.2万円」を加算処理することで「322.4万円」の着地予想値を算出する。表示制御部36は、この「322.4万円」の着地予想値を、直接費の着地予想値として組織別着地予想表に表示する。
The
また、演算部35は、4月分の間接費の実績値である「130万円」に、5月の間接費の予定値である「40万円」及び6月の間接費の予定値である「40万円」を加算処理することで「210万円」の着地予想値を算出する。表示制御部36は、この「210万円」の着地予想値を、間接費の着地予想値として組織別着地予想表に表示する。
The
また、演算部35は、4月分の販管費の実績値である「20万円」に、5月の販管費の予定値である「40万円」及び6月の販管費の予定値である「40万円」を加算処理することで「100万円」の着地予想値を算出する。表示制御部36は、この「100万円」の着地予想値を、販管費の着地予想値として組織別着地予想表に表示する。
The
また、演算部35は、売上の実績値の着地予想値から、直接費、間接費及び販管費の実績値の着地予想値を減算処理することで(1450万円-322.4万円-210万円-100万円)、「817.6万円」の着地予想値を算出する。表示制御部36は、この「817.6万円」の着地予想値を、営業利益の実績値の着地予想値として組織別着地予想表に表示する。
The
一方、業務オペレータにより、未アサイン原価を反映させた状態の組織別着地予想表の表示が選択されると、図22のフローチャートのステップS36(Yes)及びステップS37(Yes)を介して処理がステップS38に進む。そして、表示制御部36により、未アサイン原価を反映させた状態の組織別着地予想表が表示される。
On the other hand, when the business operator selects to display the organization-specific forecasted end result table reflecting the unassigned costs, the process proceeds to step S38 via step S36 (Yes) and step S37 (Yes) in the flowchart of FIG. 22. Then, the
具体的には、演算部35は、図29に示すように社員マスタ14を参照し、社員マスタ14に登録されている各社員である、例えば田中さん、鈴木さん、及び、佐藤さんの月平均予定時間を検出する。また、演算部35は、予定単価マスタ12を参照し、田中さん、鈴木さん、及び、佐藤さんの時間単価を検出する。そして、演算部35は、「未アサイン人工×月平均予定時間×時間単価」の演算を行うことで、5月分及び6月分の「未アサイン労務費原価(未アサイン原価)」を算出する。なお、4月分及び7月分~翌年3月分の未アサイン原価は、「P001」のプロジェクト番号の直接プロジェクトを受注した際に、計算済みである(図16参照)。
Specifically, as shown in FIG. 29, the
田中さんの5月及び6月の未アサイン人工は、上述のようにそれぞれ「0人月」であるため、演算部35は、5月及び6月の未アサイン原価として、それぞれ「0万円」を算出する。
Since Tanaka's unassigned man-hours for May and June are "0 man-months" as described above, the
鈴木さんの5月及び6月の予定人工は、図24に示したように「0.8人月」であるため、未アサイン人工は「0.2人月」となる。このため、演算部35は、「0.2人月×160時間×4000円」の演算を行うことで、鈴木さんの5月及び6月の未アサイン原価として「12.8万円」を算出する。また、鈴木さんの7月以降の予定人工は「0人月」であるため、未アサイン人工は「1人月」となる。このため、演算部35は、「1人月×160時間×4000円」の演算を行うことで、鈴木さんの7月以降の未アサイン原価として「64万円」を算出する。
As shown in FIG. 24, Suzuki's planned man-hours for May and June are "0.8 man-months", so the unassigned man-hours are "0.2 man-months". Therefore, the
佐藤さんの5月及び6月の予定人工は、「0人月」であるため、未アサイン人工は「1人月」となる。このため、演算部35は、「1人月×160時間×3000円」の演算を行うことで、佐藤さんの5月及び6月の未アサイン原価として「48万円」を算出する。また、鈴木さんの7月以降の予定人工も「0人月」であるため、未アサイン人工は「1人月」となる。このため、演算部35は、「1人月×160時間×3000円」の演算を行うことで、鈴木さんの7月以降の未アサイン原価として「48万円」を算出する。
Because Sato's planned man-hours for May and June are "0 man-months," the unassigned man-hours are "1 man-month." Therefore, the
次に、演算部35は、図29に示すように田中さん、鈴木さん及び佐藤さんの未アサイン原価を、月毎に加算処理することで、未アサイン原価の月毎の合計額を算出する。図29の例の場合、田中さん、鈴木さん及び佐藤さんの5月分の未アサイン原価は、それぞれ「0万円」、「12.8万円」、「48万円」であるため、演算部35は、これらを加算処理し、5月分の未アサイン原価として「60.8万円」を算出する。同様に、田中さん、鈴木さん及び佐藤さんの6月分の未アサイン原価は、それぞれ「0万円」、「12.8万円」、「48万円」であるため、演算部35は、これらを加算処理し、6月分の未アサイン原価として「60.8万円」を算出する。なお、この時点でプロジェクト受注されていない7月以降の未アサイン原価の月毎の合計額は、上述のように「192万円」となる。
Next, the
次に、図30は、未アサイン原価を含む組織別着地予想表の表示を指定した上述の抽出画面の一例、及び、未アサイン原価を反映させた組織別着地予想表の一例を示す図である。記憶制御部34は、上述の未アサイン原価を含めた状態の着地予想値を組織別着地予想テーブル22に記憶する。表示制御部36は、組織別着地予想テーブル22に登録されている売上、直接費、間接費、販管費、及び、営業利益の各着地予想値を読み出して、図30に示すように、未アサイン原価を含めた状態の組織別着地予想表を出力装置7に表示する。
Next, FIG. 30 shows an example of the above-mentioned extraction screen in which the display of the organization-specific forecast table including unassigned costs is specified, and an example of the organization-specific forecast table reflecting the unassigned costs. The
具体的には、演算部35は、5月分の間接費の予定値である「40万円(図28参照)」に、図29を用いて説明した5月分の「60.8万円」の未アサイン原価を加算処理することで、5月分の間接費の予定値として「100.8万円」を算出する。同様に、演算部35は、6月分の間接費の予定値である「40万円(図28参照)」に、図29を用いて説明した6月分の「60.8万円」の未アサイン原価を加算処理することで、6月分の間接費の予定値として「100.8万円」を算出する。
Specifically, the
表示制御部36は、図30に示すように、組織別着地予想表の5月分及び6月分の間接費の予定値として、それぞれ未アサイン原価を反映させた「100.8万円」を表示する。また、表示制御部36は、組織別着地予想表の7月以降の間接費の予定値としては、未アサイン原価を反映させて算出した「192万円(図29参照)」を表示する。
As shown in FIG. 30, the
また、演算部35は、間接費の実績値である「130万円」に、5月分の間接費の予定値である「100.8万円」、6月分の間接費の予定値である「100.8万円」を加算処理する。また、演算部35は、7月~翌年3月の計9か月分の間接費の予定値である「192万円×9=1728万円」を算出する。そして、「130万円+100.8万円+100.8万円+1728万円」の演算を行うことで、間接値の実績値の着地予想値として「2059.6万円」を算出する。表示制御部36は、この「2059.6万円」を、未アサイン原価が反映された間接値の実績値の着地予想値として組織別着地予想表に表示する。
The
また、演算部35は、売上の実績値である「1450万円」から、直接費の実績値である「348万円」を減算処理し、間接費の実績値である「2059.6万円」を減算処理し、販管費の実績値である「100万円」を減算処理することで、「-1057.6万円」の営業利益の着地予想値を算出する。表示制御部36は、この「-1057.6万円」を、未アサイン原価が反映された営業利益の実績値の着地予想値として組織別着地予想表に表示する。
The
(実施の形態の効果)
以上の説明から明らかなように、実施の形態の業務管理装置1は、未アサイン原価を組織別の将来原価に組み込んで表示することで、将来の未アサイン原価を、事務コストを掛けずに把握することができる(事務労力の軽減)。これにより組織別の事業計画において、日々変動する着地予想数字の正確性を向上させることができる。
(Effects of the embodiment)
As is clear from the above explanation, the
また、プロジェクトの受注が無く、未アサインの状態でその月を終えた場合、プロジェクトに関連する直接原価ではなく、間接原価として計上される。このため、未アサイン原価を、その所属組織の間接労務費(間接費)の予定値に加算する。これにより、組織別の直接費/間接費の比率等も容易に把握可能とすることができ、単なる組織別の事業計画に対する達成/未達との評価だけでなく、同じ売上額、営業利益の組織であっても、各プロジェクトの直接原価が高く、売上利益率が悪い(=利益の低い労働集約型のプロジェクトが多い)のか、間接原価が高く、各プロジェクトの利益は高いが、アサインが適切に行われていないため、営業利益を効率的に得られない等の分析を可能とすることができる。 Also, if there are no orders for projects and the month ends with the project unassigned, it is recorded as an indirect cost rather than a direct cost related to the project. For this reason, the unassigned cost is added to the planned indirect labor cost (indirect cost) of the organization to which it belongs. This makes it easy to understand the ratio of direct cost/indirect cost by organization, and not only can it be used to evaluate whether the business plan of each organization has been achieved or not, but it is also possible to analyze whether the direct cost of each project is high and the sales profit margin is poor (= there are many labor-intensive projects with low profits) even in organizations with the same sales amount and operating profit, or whether the indirect cost is high and the profit of each project is high, but the assignment is not done properly, so operating profit is not efficiently obtained.
[国連が主導する持続可能な開発目標(SDGs)への貢献]
本実施形態により、業務効率化や企業の適切な経営判断を推進することに寄与することができるので、SDGsの目標8及び目標9に貢献することが可能となる。
[Contribution to the United Nations-led Sustainable Development Goals (SDGs)]
This embodiment can contribute to improving business efficiency and promoting appropriate management decisions by companies, thereby making it possible to contribute to Goals 8 and 9 of the SDGs.
また、本実施形態により、廃棄ロス削減や、ペーパレス・電子化を推進することに寄与することができるので、SDGsの目標12、目標13及び目標15に貢献することが可能となる。
In addition, this embodiment can contribute to reducing waste and promoting paperless and electronic systems, which can contribute to the achievement of
また、本実施形態により、統制、ガバナンス強化に寄与することができるので、SDGsの目標16に貢献することが可能となる。
In addition, this embodiment can contribute to strengthening control and governance, making it possible to contribute to
[他の実施の形態]
本発明は、上述した実施形態以外にも、特許請求の範囲に記載した技術的思想の範囲内において種々の異なる実施形態にて実施されてよいものである。
[Other embodiments]
The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.
例えば、実施形態において説明した各処理のうち、自動的に行われるものとして説明した処理の全部又は一部を手動的に行うこともでき、或いは、手動的に行われるものとして説明した処理の全部または一部を公知の方法で自動的に行うこともできる。 For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using a known method.
また、本明細書中や図面中で示した処理手順、制御手順、具体的名称、各処理の登録データや検索条件等のパラメータを含む情報、画面例、データベース構成については、特記する場合を除いて任意に変更することができる。 In addition, the processing procedures, control procedures, specific names, registered data for each process, information including parameters such as search conditions, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.
また、業務管理装置1に関して、図示の各構成要素は機能概念的なものであり、必ずしも図示の如く物理的に構成されていることを要しない。
Furthermore, with regard to the
例えば、業務管理装置1が備える処理機能、特に制御部3及び制御部3にて行われる各処理機能については、その全部又は任意の一部を、CPU(Central Processing Unit)および当該CPUにて解釈実行されるプログラムにて実現してもよく、また、ワイヤードロジックによるハードウェアとして実現してもよい。なお、プログラムは、本実施形態で説明した処理を情報処理装置に実行させるためのプログラム化された命令を含む一時的でないコンピュータ読み取り可能な記録媒体に記録されており、必要に応じて業務管理装置1に機械的に読み取られる。すなわち、ROM又はHDD等の記憶部等には、OSと協働してCPUに命令を与え、各種処理を行うためのコンピュータプログラムが記録されている。このコンピュータプログラムは、RAMにロードされることによって実行され、CPUと協働して制御部3を構成する。
For example, the processing functions of the
また、この業務管理装置1の業務管理プログラムは、業務管理装置1に対して任意のネットワークを介して接続された他のサーバ装置に記憶されていてもよく、必要に応じてその全部又は一部をダウンロードすることも可能である。
In addition, the business management program of this
また、本実施形態で説明した処理を実行するための業務管理プログラムを、一時的でないコンピュータ読み取り可能な記録媒体に格納してもよく、また、プログラム製品として構成することもできる。ここで、この「記録媒体」とは、メモリーカード、USB(Universal Serial Bus)メモリ、SD(Secure Digital)カード、フレキシブルディスク、光磁気ディスク、ROM、EPROM(Erasable Programmable Read Only Memory)、EEPROM(登録商標)(Electrically Erasable and Programmable Read Only Memory)、CD-ROM(Compact Disk Read Only Memory)、MO(Magneto-Optical Disk)、DVD(Digital Versatile Disk)、及び、Blu-ray(登録商標) Disc等の任意の「可搬用の物理媒体」を含むものとする。 The business management program for executing the processes described in this embodiment may be stored in a non-transitory computer-readable recording medium, or may be configured as a program product. Here, the term "recording medium" includes any "portable physical medium" such as a memory card, a Universal Serial Bus (USB) memory, a Secure Digital (SD) card, a flexible disk, a magneto-optical disk, a ROM, an Erasable Programmable Read Only Memory (EPROM), an Electrically Erasable and Programmable Read Only Memory (EEPROM (registered trademark)), a Compact Disk Read Only Memory (CD-ROM), a Magneto-Optical Disk (MO), a Digital Versatile Disk (DVD), and a Blu-ray (registered trademark) Disc.
また、「プログラム」とは、任意の言語または記述方法にて記述されたデータ処理方法であり、ソースコード又はバイナリコード等の形式を問わない。なお、「プログラム」は必ずしも単一的に構成されるものに限られず、複数のモジュールやライブラリとして分散構成されるものや、OSに代表される別個のプログラムと協働してその機能を達成するものをも含む。なお、実施の形態に示した業務管理装置1において記録媒体を読み取るための具体的な構成および読み取り手順ならびに読み取り後のインストール手順等については、周知の構成や手順を用いることができる。
A "program" is a data processing method written in any language or description method, and may be in any format, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a distributed configuration consisting of multiple modules or libraries, and a program that works in conjunction with a separate program, such as an OS, to achieve its function. Note that the specific configuration and reading procedure for reading a recording medium in the
記憶部2は、RAM、ROM等のメモリ装置、ハードディスク等の固定ディスク装置、フレキシブルディスク、及び、光ディスク等のストレージ手段であり、各種処理やウェブサイト提供に用いる各種のプログラム、テーブル、データベース、及び、ウェブページ用ファイル等を格納する。
The
また、業務管理装置1は、既知のパーソナルコンピュータ装置又はワークステーション等の情報処理装置で構成してもよく、また、任意の周辺装置が接続された情報処理装置で構成してもよい。また、情報処理装置は、本実施形態で説明した処理を実現させるソフトウェア(プログラム又はデータ等を含む)を実装することにより実現してもよい。
The
さらに、装置の分散・統合の具体的形態は図示するものに限られず、その全部又は一部を、各種の付加等に応じて又は機能付加に応じて、任意の単位で機能的又は物理的に分散・統合して構成することができる。すなわち、上述した実施形態を任意に組み合わせて実施してもよく、実施形態を選択的に実施してもよい。 Furthermore, the specific form of distribution and integration of the devices is not limited to that shown in the figures, and all or part of them can be functionally or physically distributed and integrated in any unit depending on various additions or function additions. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively.
本発明は、例えばシステムエンジニアリングサービスを行うIT(Information Technology)メディア業界の業務等に有用である。 The present invention is useful, for example, in operations in the IT (Information Technology) media industry providing system engineering services.
1 業務管理装置
2 記憶部
3 制御部
4 通信インターフェース部
5 入出力インターフェース部
6 入力装置
7 出力装置
11 原価要素マスタ
12 予定単価マスタ
13 部署マスタ
14 社員マスタ
15 原価要素テーブル
16 予定単価テーブル
17 部署テーブル
18 社員テーブル
19 直接PJテーブル
20 予算テーブル
21 仮想PJテーブル
22 組織別着地予想テーブル
23 要員管理テーブル
24 未アサインテーブル
25 売上テーブル
26 経費テーブル
31 マスタ設定部
32 入力処理部
33 データ生成部
34 記憶制御部
35 演算部
36 表示制御部
LIST OF
Claims (7)
前記所定期間における予定人工数を減算処理した値である未アサイン人工に月平均予定時間を乗算処理した乗算処理結果に時間単価を乗算処理することで、前記案件に対する費用としてアサインされていない費用である未アサイン原価を算出する未アサイン原価算出部と、
前記仮予定値及び前記未アサイン原価を加算処理した値を、前記案件の所定期間における費用の予定値として生成する予定値生成部と、
前記所定期間において確定した費用の実績値、及び、前記実績値が確定した時点以降の前記予定値の合計値を、通期における費用の予定値に対応する着地予想値として算出する着地予想値算出部と、
費用の予定値に対応する前記着地予想値を出力する出力制御部と、
を有する着地予想値管理装置。 a tentative schedule value generating unit that generates a tentative schedule value, which is a schedule value before adding an unassigned cost, of the cost input by the business operator as the cost for a predetermined period for the case ;
an unassigned cost calculation unit that calculates an unassigned cost, which is an expense not assigned as an expense for the case, by multiplying an unassigned labor-time, which is a value obtained by subtracting a planned labor-time in the predetermined period, by a monthly average planned time, and multiplying the result by an hourly rate;
a planned value generating unit that generates a value obtained by adding the tentative planned value and the unassigned cost as a planned value of the cost for a predetermined period of the project;
a forecasted cost calculation unit that calculates a total value of the actual cost value determined in the specified period and the planned cost value after the actual cost value is determined as a forecasted cost value corresponding to the planned cost value for the entire period;
an output control unit that outputs the estimated landing value corresponding to the scheduled cost value;
A landing prediction value management device having the above-mentioned.
前記出力制御部は、費用の予定値に対応する前記着地予想値、及び、費用の計画値に対応する前記着地予想値を出力すること、
を特徴とする請求項1に記載の着地予想値管理装置。 The estimated value calculation unit calculates the estimated value as a total value of the planned values of the expenses for each predetermined period stored in the storage unit, and as an estimated value corresponding to the planned value of the expenses for the entire period before the actual value occurs;
The output control unit outputs the predicted landing value corresponding to the scheduled value of the cost and the predicted landing value corresponding to the planned value of the cost;
2. The landing prediction value management device according to claim 1,
を特徴とする請求項1又は請求項2に記載の着地予想値管理装置。 the forecasted landing value calculation unit calculates the forecasted landing value for each group in charge of the case;
3. The landing prediction value management device according to claim 1 or 2, characterized in that
前記仮予定値生成部は、前記業務オペレータによる前記間接費の入力に基づいて前記仮予定値を生成し、
前記未アサイン原価算出部は、前記所定期間における予定人工数を減算処理した値である未アサイン人工に月平均予定時間を乗算処理した乗算処理結果に時間単価を乗算処理することで、前記間接費に対応する未アサイン原価を算出し、
前記予定値生成部は、前記間接費の仮予定値及び前記間接費の未アサイン原価を加算処理した値を、前記間接費の予定値として生成すること、
を特徴する請求項1から請求項3のうち、いずれか一項に記載の着地予想値管理装置。 the forecasted value calculation unit calculates the forecasted values corresponding to the sales, direct costs, indirect costs, selling and administrative expenses, and operating profit of the project, respectively;
the provisional schedule value generating unit generates the provisional schedule value based on an input of the overhead by the business operator;
The unassigned cost calculation unit calculates unassigned costs corresponding to the overhead by multiplying the unassigned labor, which is a value obtained by subtracting the planned labor force in the predetermined period, by a monthly average planned time, and multiplying the result by an hourly rate;
the planned value generating unit generates a value obtained by adding the tentative planned value of the overhead and the unassigned cost of the overhead as the planned value of the overhead;
The landing prediction value management device according to any one of claims 1 to 3,
前記出力制御部は、前記未アサイン原価の加算処理を行った前記着地予想値、及び、前記未アサイン原価の加算処理を行わない着地予想値のうち、選択された方の前記着地予想値を出力すること、
を特徴とする請求項1から請求項4のうち、いずれか一項に記載の着地予想値管理装置。 The estimated landing value calculation unit calculates the estimated landing value after adding the unassigned cost and the estimated landing value without adding the unassigned cost,
the output control unit outputs a selected one of the forecasted landing value to which the unassigned cost has been added and the forecasted landing value to which the unassigned cost has not been added;
5. The landing prediction value management device according to claim 1, wherein:
未アサイン原価算出部が、前記所定期間における予定人工数を減算処理した値である未アサイン人工に月平均予定時間を乗算処理した乗算処理結果に時間単価を乗算処理することで、前記案件に対する費用としてアサインされていない費用である未アサイン原価を算出する未アサイン原価算出ステップと、
予定値生成部が、前記仮予定値及び前記未アサイン原価を加算処理した値を、前記案件の所定期間における費用の予定値として生成する予定値生成ステップと、
着地予想値算出部が、前記所定期間において確定した費用の実績値、及び、前記実績値が確定した時点以降の前記予定値の合計値を、通期における費用の予定値に対応する着地予想値として算出する着地予想値算出ステップと、
出力制御部が、費用の予定値に対応する前記着地予想値を出力する出力制御ステップと、
を有する着地予想値管理方法。 a tentative schedule value generating step in which a tentative schedule value generating unit generates a tentative schedule value, which is a schedule value before addition of unassigned costs, of the cost input by the business operator as the cost for a predetermined period for the case ;
an unassigned cost calculation step in which an unassigned cost calculation unit multiplies an unassigned labor-time, which is a value obtained by subtracting a planned labor-time in the predetermined period, by a monthly average planned time, and multiplies the result by an hourly rate to calculate an unassigned cost, which is a cost not assigned as a cost for the project;
a planned value generating step in which a planned value generating unit generates a value obtained by adding the tentative planned value and the unassigned cost as a planned value of the cost for a predetermined period of the project;
a forecasted cost calculation step in which a forecasted cost calculation unit calculates a total value of the actual cost value determined in the predetermined period and the planned cost value after the actual cost value is determined as a forecasted cost value corresponding to the planned cost value for the entire period;
an output control step in which an output control unit outputs the estimated landing value corresponding to a scheduled value of the cost;
A landing forecast value management method having the above-mentioned features.
案件に対する所定期間の費用として業務オペレータにより入力された費用の、未アサイン原価加算前における予定値である仮予定値を生成する仮予定値生成部と
前記所定期間における予定人工数を減算処理した値である未アサイン人工に月平均予定時間を乗算処理した乗算処理結果に時間単価を乗算処理することで、前記案件に対する費用としてアサインされていない費用である未アサイン原価を算出する未アサイン原価算出部と、
前記仮予定値及び前記未アサイン原価を加算処理した値を、前記案件の所定期間における費用の予定値として生成する予定値生成部と、
前記所定期間において確定した費用の実績値、及び、前記実績値が確定した時点以降の前記予定値の合計値を、通期における費用の予定値に対応する着地予想値として算出する着地予想値算出部と、
費用の予定値に対応する前記着地予想値を出力する出力制御部として機能させること、
を特徴とする着地予想値管理プログラム。 Computer,
a tentative planned value generating unit that generates a tentative planned value, which is a planned value before adding unassigned costs, of the costs input by the business operator as costs for a specified period for the case ; an unassigned cost calculating unit that calculates unassigned costs, which are costs not assigned as costs for the case, by multiplying the unassigned man-hours, which is a value obtained by subtracting the planned man-hours for the specified period, by the monthly average planned time, and multiplying the result by the hourly rate;
a planned value generating unit that generates a value obtained by adding the tentative planned value and the unassigned cost as a planned value of the cost for a predetermined period of the project;
a forecasted cost calculation unit that calculates a total value of the actual cost value determined in the specified period and the planned cost value after the actual cost value is determined as a forecasted cost value corresponding to the planned cost value for the entire period;
functioning as an output control unit that outputs the estimated landing value corresponding to the scheduled cost value;
A landing forecast management program that features:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2022018212A JP7644038B2 (en) | 2022-02-08 | 2022-02-08 | Landing forecast value management device, landing forecast value management method, and landing forecast value management program |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2022018212A JP7644038B2 (en) | 2022-02-08 | 2022-02-08 | Landing forecast value management device, landing forecast value management method, and landing forecast value management program |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2023115800A JP2023115800A (en) | 2023-08-21 |
| JP7644038B2 true JP7644038B2 (en) | 2025-03-11 |
Family
ID=87576522
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2022018212A Active JP7644038B2 (en) | 2022-02-08 | 2022-02-08 | Landing forecast value management device, landing forecast value management method, and landing forecast value management program |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7644038B2 (en) |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001109834A (en) | 1999-10-13 | 2001-04-20 | Noboru Isobe | Processing method of management accounting type financial accounting system |
| JP2002215865A (en) | 2001-01-16 | 2002-08-02 | Baasu Engineering:Kk | System for creating materials for business plan |
| JP2007257145A (en) | 2006-03-22 | 2007-10-04 | Nec Corp | System, program, and recording medium for household budget management |
| JP2008158600A (en) | 2006-12-21 | 2008-07-10 | Chugoku Electric Power Co Inc:The | Budget/result management support system and budget/result management support method |
| JP2019021081A (en) | 2017-07-19 | 2019-02-07 | 株式会社スリー・シー・コンサルティング | Budget accounting system, program and recording medium |
| WO2021132603A1 (en) | 2019-12-27 | 2021-07-01 | 株式会社覚王山総研 | Information processing device, information processing method, and program |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH11259562A (en) * | 1998-03-09 | 1999-09-24 | Team Ai:Kk | Estimation method and system for settlement of accounts using computer and computer readable recording medium recording settlement-of-accounts estimation program |
-
2022
- 2022-02-08 JP JP2022018212A patent/JP7644038B2/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001109834A (en) | 1999-10-13 | 2001-04-20 | Noboru Isobe | Processing method of management accounting type financial accounting system |
| JP2002215865A (en) | 2001-01-16 | 2002-08-02 | Baasu Engineering:Kk | System for creating materials for business plan |
| JP2007257145A (en) | 2006-03-22 | 2007-10-04 | Nec Corp | System, program, and recording medium for household budget management |
| JP2008158600A (en) | 2006-12-21 | 2008-07-10 | Chugoku Electric Power Co Inc:The | Budget/result management support system and budget/result management support method |
| JP2019021081A (en) | 2017-07-19 | 2019-02-07 | 株式会社スリー・シー・コンサルティング | Budget accounting system, program and recording medium |
| WO2021132603A1 (en) | 2019-12-27 | 2021-07-01 | 株式会社覚王山総研 | Information processing device, information processing method, and program |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2023115800A (en) | 2023-08-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN113793086A (en) | Spare capacity determination method and device, computer storage medium and electronic equipment | |
| JP7569462B2 (en) | Project management device, project management method, and project management program | |
| JP6370757B2 (en) | Profit / loss prediction apparatus and profit / loss prediction program | |
| Franz | Project management with SAP project system | |
| JP7445713B2 (en) | Allocation work support device, allocation work support method, and allocation work support program | |
| Shafieezadeh et al. | A system dynamics simulation model to evaluate project planning policies | |
| JP2024017968A (en) | Business support device, business support method, and business support program | |
| JP7492399B2 (en) | Grade management device, grade management method, and grade management program | |
| US8046252B2 (en) | Sales plan evaluation support system | |
| JP7780408B2 (en) | Income and expenditure management device, income and expenditure management method, and income and expenditure management program | |
| US20140379417A1 (en) | System and Method for Data Quality Business Impact Analysis | |
| JP7644038B2 (en) | Landing forecast value management device, landing forecast value management method, and landing forecast value management program | |
| JP7618617B2 (en) | Inventory management device, inventory management method, and inventory management program | |
| JP7485751B2 (en) | Work-related information management support device, work-related information management support method, and work-related information management support program | |
| JP6830792B2 (en) | Sales management equipment, sales management methods and sales management programs | |
| JP7791133B2 (en) | Landing prediction device, landing prediction method, and landing prediction program | |
| JP7542027B2 (en) | Output management device, output management method, and output management program | |
| JP7280931B2 (en) | Information processing device, information processing method, and information processing program | |
| JP7550712B2 (en) | Planned start and end date calculation device, planned start and end date calculation method, and planned start and end date calculation program | |
| Karvonen | Computer supported changes in project management | |
| JP7517912B2 (en) | Hourly rate acquisition device, hourly rate acquisition method, and hourly rate acquisition program | |
| JP7554788B2 (en) | Business support device, business support method, and business support program | |
| JP7593961B2 (en) | Business support device, business support method, and business support program | |
| JP2016184250A (en) | Profit/loss prediction device and profit/loss prediction program | |
| JP7636057B1 (en) | Information processing system, information processing method, and program |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20240517 |
|
| A871 | Explanation of circumstances concerning accelerated examination |
Free format text: JAPANESE INTERMEDIATE CODE: A871 Effective date: 20240524 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20240709 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20240909 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20241105 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20241218 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20250204 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20250227 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7644038 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |