JPS5930862B2 - Buried piping construction method - Google Patents
Buried piping construction methodInfo
- Publication number
- JPS5930862B2 JPS5930862B2 JP55089189A JP8918980A JPS5930862B2 JP S5930862 B2 JPS5930862 B2 JP S5930862B2 JP 55089189 A JP55089189 A JP 55089189A JP 8918980 A JP8918980 A JP 8918980A JP S5930862 B2 JPS5930862 B2 JP S5930862B2
- Authority
- JP
- Japan
- Prior art keywords
- buried
- pipe body
- solidifying agent
- sheet pile
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Foundations (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【発明の詳細な説明】
この発明は、埋設配管施工時に、防護矢板の引抜きの際
における管体の不等沈下を防止した埋設配管施工方法に
関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a buried piping construction method that prevents uneven settling of pipe bodies when pulling out protective sheet piles during construction of buried piping.
一般に、地中への埋設配管施工に当っては、第1図に断
面図で示す如く、埋設予定管路に沿って、地中に防護用
の矢板1,1を一定の幅で、かつ所定深さに打込み、つ
いで矢板1,1間の土砂を所定深さに取り除いて埋設溝
2を造り、埋設溝2の溝底2a上に管体3を敷設し管路
を形成した後、埋設溝2内に土砂を埋め戻し、ついで前
記矢板1゜1を引抜き撤去する工法が行なわれている。Generally, when constructing underground piping, as shown in the cross-sectional view in Figure 1, protective sheet piles 1, 1 are laid underground with a certain width and at a predetermined location along the pipeline to be buried. After driving to a certain depth, the earth and sand between the sheet piles 1 and 1 is removed to a predetermined depth to create a buried trench 2. After laying the pipe body 3 on the bottom 2a of the buried trench 2 to form a conduit, A construction method is used in which earth and sand is backfilled into the 2nd floor, and then the sheet pile 1.1 is pulled out and removed.
上記工法において、矢板1,1は、埋設溝2の形成に当
り、周辺の土砂が崩壊しないように防護するため打込む
ものであるが、埋設配管施工後は、これを引抜き撤去す
ることが条例等で義務づけられている。In the above construction method, the sheet piles 1, 1 are driven in to protect the surrounding earth and sand from collapsing when forming the buried trench 2, but regulations require that they be pulled out and removed after the buried piping is constructed. It is mandatory.
しかるに、前記矢板1,1を引抜くと、引抜き後地中に
矢板の断面積および引抜きにより持去られる土砂の分だ
け空隙が生じ、そしてこのような空隙を埋めるように土
砂が移動する結果、地盤が沈下する。However, when the sheet piles 1, 1 are pulled out, a void is created in the ground after being pulled out by the cross-sectional area of the sheet pile and the soil removed by the pulling out, and as a result, the soil moves to fill such a void. The ground sinks.
上記した地盤の沈下量は、次のようにして算出される。The amount of ground subsidence mentioned above is calculated as follows.
即ち、第2図イの平面説明図、同図口の側面説明図にお
いて、矢板1の断面積Sは、矢板の幅をH1厚さをtと
すると、5=(Hxt )となる。That is, in the plan explanatory view of FIG. 2A and the side explanatory view of the opening in the figure, the cross-sectional area S of the sheet pile 1 is 5=(Hxt), where the width of the sheet pile is H1 and the thickness is t.
また、左右2枚で1組の矢板を引抜いた後に生ずる空隙
は、
矢板1組当りの空隙=SxLx2x(1+α)但し、S
:矢板1枚の断面積
L:地中における矢板の長さ
α:矢板1枚に対する土の付着率
となる。In addition, the gap created after pulling out one set of left and right sheet piles is as follows: Gap per set of sheet piles = SxLx2x (1+α) However, S
: Cross-sectional area of one sheet pile L: Length of the sheet pile in the ground α: Adhesion rate of soil to one sheet pile.
従って、沈下量δは、で表わされる。Therefore, the amount of subsidence δ is expressed as.
例えば、5p−tr型の矢板につき、上述の式を当ては
めると、L:600CWl、L’:300cn1.H:
40cm、t :10C?71.αf:1.#=150
Crnであるところから、
となり、地盤の沈下量は16cmになる。For example, applying the above formula to a 5p-tr type sheet pile, L: 600CWl, L': 300cn1. H:
40cm, t:10C? 71. αf:1. #=150
Since Crn, the amount of ground subsidence becomes 16 cm.
このような地盤の沈下は、必然的に埋設管の沈下を招く
、埋設管の沈下は、管体と地盤とが一様に沈下する場合
には特に問題は生じないが、第3図に説明図で示す如く
、管体3の一端がピット4等により固定されている部分
では、地中に点線で示したように埋設されていた管体3
が、実線で示すような不等沈下をおこす結果、この部分
の管体3aに過大な応力が生じ、損傷を起す原因となる
。Such subsidence of the ground inevitably causes subsidence of the buried pipe.Subsidence of the buried pipe does not cause any particular problem if the pipe body and the ground subside uniformly, but this is explained in Figure 3. As shown in the figure, in the part where one end of the pipe 3 is fixed by the pit 4 etc., the pipe 3 buried underground as shown by the dotted line
However, as a result of uneven settlement as shown by the solid line, excessive stress is generated in the pipe body 3a in this part, causing damage.
この発明は、上述のような観点から、矢板引抜き後にお
いて地盤沈下に伴なう管体の不等沈下が生ずることのな
い埋設配管施工方法を提供するもので前記矢板の引抜き
に自力、埋設溝内に敷設された管体を、予め水平状態に
吊持せしめた上でこれを行ない、ついで、前記矢板の引
抜きによる地盤沈下の結果生じた管体下面の空隙内に、
流動性固化剤を注入し、しかる後前記管体の吊持を解除
することに特徴を有するものである。From the above-mentioned viewpoint, the present invention provides a buried pipe construction method that does not cause uneven settling of the pipe body due to ground subsidence after pulling out the sheet pile. This is done by suspending the pipe laid in the pipe in a horizontal state in advance, and then inserting it into the void on the bottom surface of the pipe, which was created as a result of ground subsidence due to the pulling out of the sheet pile.
This method is characterized in that a fluid solidifying agent is injected and then the suspension of the tube is released.
次に、この発明を実施例によシ図面と共に説明する。Next, the present invention will be explained based on examples and drawings.
第4図には、この発明による施工方法の一例が平面図に
より、第5図には管体の吊持ち部分の断面図により示さ
れている。FIG. 4 shows a plan view of an example of the construction method according to the present invention, and FIG. 5 shows a cross-sectional view of the hanging portion of the tube.
図面において、1,1は地中に所定幅を保って打込まれ
た矢板で、前記矢板1,1により形成された埋設溝2内
に管体3を敷設することは、従来の方法と同じである。In the drawing, reference numerals 1 and 1 are sheet piles driven into the ground with a predetermined width maintained, and laying the pipe body 3 in the burial trench 2 formed by the sheet piles 1 and 1 is the same as the conventional method. It is.
この発明においては、管体3の敷設に当力、管体3に予
め所定間隔で流動性固化剤注入用のホース4と、空気抜
き用のホース5とを、その一方端が管体3の下面に臨み
、他方端が地面上にあるように立上げた状態で取付けた
上、敷設する。In this invention, when laying the tube body 3, a hose 4 for injecting a fluid solidifying agent and a hose 5 for air venting are connected to the tube body 3 at predetermined intervals, one end of which is connected to the bottom surface of the tube body 3. Install it in an upright position so that the other end is on the ground, and then lay it.
前記ホース4,5は、図示の実施例では例えば直径50
mm程度のゴムホースを使用し、第4図に示す如く、流
動性固化剤注入用のホース4,4・・・の間の管体反対
側に、空気抜き用のホース5,5・・・・・・を位置せ
しめ、各ホース間の間隔を3〜4mとした。The hoses 4, 5 have a diameter of, for example, 50 mm in the illustrated embodiment.
As shown in Fig. 4, use a rubber hose with a diameter of about mm, and connect air vent hoses 5, 5, etc. to the opposite side of the tube between the fluid solidifying agent injection hoses 4, 4, etc.・The distance between each hose was 3 to 4 m.
6は矢板1,1をまたぎ、地上に適宜の間隔で立設され
た管体吊持ち用の枠体で支柱6a 、 6aと、支柱6
a、6aの上端間に横架された梁6bとからなってお〃
、梁6bにはフック7を介してチエンブロック8が取付
けられている。Reference numeral 6 denotes a frame body for suspending pipes, which straddles the sheet piles 1 and 1 and is erected on the ground at appropriate intervals, and includes pillars 6a, 6a, and pillars 6.
It consists of a beam 6b suspended horizontally between the upper ends of 6a and 6a.
A chain block 8 is attached to the beam 6b via a hook 7.
一方、埋設溝2内に敷設された管体3の上面には、前記
枠体6の立設位置に、吊上げ用フック9を取付けておき
、管体3の敷設後、吊上げ用フック9に前記チエンブロ
ック8のワイヤ8aを係合させ、管体3を前記チエンブ
ロック8により、水平状態に吊持せしめた状態としてお
く。On the other hand, a lifting hook 9 is attached to the upper surface of the pipe body 3 laid in the buried trench 2 at the upright position of the frame body 6, and after the pipe body 3 is laid, the lifting hook 9 is attached to the The wire 8a of the chain block 8 is engaged, and the pipe body 3 is suspended horizontally by the chain block 8.
なお図示の実施例では、ワイヤ8aの先端に、落錘フッ
ク10が取付けられ、吊上げ用フック9との係脱を容易
にしである。In the illustrated embodiment, a falling weight hook 10 is attached to the tip of the wire 8a to facilitate engagement and disengagement with the lifting hook 9.
10aは落錘フック10の操作用ひもである。10a is a string for operating the falling weight hook 10.
管体3を上述した状態となした後、埋設溝2内に土砂1
1を埋め戻し、ついて矢板1,1を引抜き撤去する。After the pipe body 3 is in the above-mentioned state, soil 1 is placed in the buried trench 2.
1 is backfilled, and then the sheet piles 1 and 1 are pulled out and removed.
矢板1,1の引抜きにより、前述した如く土砂が移動し
、地盤の沈下が発生するが、管体3は上述した如く、枠
体6にチエンブロック8で吊持され、水平状態に保たれ
る。When the sheet piles 1 and 1 are pulled out, the earth and sand move as described above, causing ground subsidence, but as described above, the pipe body 3 is suspended by the chain block 8 on the frame body 6 and kept in a horizontal state. .
ついで、第6図に示す如く、管体3に取付けられた流動
性固化剤注入用のホース4の地上に突出している端部を
、コンクリート注入用のポンプ12に接続し、地盤沈下
によシ生じた管体3下面の空隙13内に、前記ポンプ1
2の作動によって、エアーモルタルの如き流動性固化剤
14を注入する。Next, as shown in Fig. 6, the end of the hose 4 for injecting a fluid solidifying agent attached to the pipe body 3, which protrudes above the ground, is connected to the pump 12 for injecting concrete to prevent ground subsidence. The pump 1 is inserted into the created gap 13 on the lower surface of the tube body 3.
2, a fluid solidifying agent 14 such as air mortar is injected.
この際空隙13内に存在する空気は、地下水があるとき
は地下水も共に空気抜き用ホース5から排出され、この
空気の排出状態によって、空隙13への流動性固化剤注
入状態を把握することができる。At this time, the air existing in the voids 13 and, if there is groundwater, are also discharged from the air venting hose 5, and the state of injection of the fluid solidifying agent into the voids 13 can be determined from the state of this air discharge. .
上述のようにして、管体3下面の空隙13に対する流動
性固化剤14の注入が完了した後は、流動性固化剤注入
用ホース4および空気抜き用ホース5を夫々流動性固化
剤14の注入を行ないながら、作業員が地上よシ引抜き
撤去する。After the injection of the fluid solidifying agent 14 into the gap 13 on the lower surface of the tube body 3 is completed as described above, the fluid solidifying agent injection hose 4 and the air venting hose 5 are connected to each other for injection of the fluid solidifying agent 14. While doing so, workers pulled it out from the ground and removed it.
上記した流動性固化剤14の硬化によ〃、管体3は安定
した水平埋設状態となるから、管体3の吊上げ用フック
9の取付は部分を掘削して、前記吊上げ用フック9に係
合されているチェンブロック8のワイヤ8a先端部に取
付けられた落錘フック10を取外し、チエンブロック8
の取付けられた枠体6を撤去する。Due to the hardening of the fluid solidifying agent 14 described above, the pipe body 3 is placed in a stable horizontally buried state, so that the lifting hook 9 of the pipe body 3 can be installed by excavating a portion and attaching the lifting hook 9 to the pipe body 3. Remove the falling weight hook 10 attached to the tip of the wire 8a of the chain block 8 that has been fitted, and
The frame body 6 to which is attached is removed.
ついで、上記した掘削部分を補修し、工事を完了する。Next, the excavated area mentioned above will be repaired and the construction work will be completed.
第1図には、この発明方法における流動性固化剤注入工
程の他の実施例が側面図により、第8図には第1図A−
A線断面図により示されている。FIG. 1 shows a side view of another embodiment of the flowable solidifying agent injection step in the method of the present invention, and FIG.
It is shown by a cross-sectional view taken along line A.
この実施例においては、管体3が取付けられたピット1
5の壁体16における管体3の取付は位置の下部に、流
動性固化剤注入用ホース4の挿通孔17と、空気抜き用
ホース5の挿通孔18とを設け、前記挿通孔17には、
流動性固化剤注入用ホース4を挿通し、管体3の軸線方
向に沿って、管体3下面の空隙部13内に進入させ、ま
た挿通孔18には、空気抜き用ホース5を挿入しておく
。In this embodiment, a pit 1 to which a pipe body 3 is attached
5, an insertion hole 17 for the fluid solidifying agent injection hose 4 and an insertion hole 18 for the air venting hose 5 are provided at the lower part of the wall 16 of the tube 3.
The fluid solidifying agent injection hose 4 is inserted into the cavity 13 on the lower surface of the tube 3 along the axial direction of the tube 3, and the air purge hose 5 is inserted into the insertion hole 18. put.
ついで、流動性固化剤注入用ホース4から、空隙部13
内にエアーモルタルの如き流動性固化剤14を注入しつ
つ、前記ホース4を徐々に引抜いて後退させ、かくして
空隙部13内に流動性固化剤が充満された後、これを挿
通孔11から抜きと力撤去する。Next, from the fluid solidifying agent injection hose 4, the cavity 13 is
While injecting a fluid solidifying agent 14 such as air mortar into the space, the hose 4 is gradually pulled out and moved back, and after the cavity 13 is filled with the fluid solidifying agent, it is pulled out from the insertion hole 11. and remove the force.
また空気抜き用ホース5も同様に撤去する。The air venting hose 5 is also removed in the same manner.
以下の工程は、前述した実施例と同様である。The following steps are similar to those in the embodiment described above.
・上述した説明かられかるように、この発明によ
れば、埋設配管施工時に、防護矢板の引抜きに伴って地
盤沈下が発生しても、埋設管体が不等沈下を起し、管体
に過大な応力が発生することはなく、安全適確な管体の
埋設を行なうことができ、矢板引抜きに伴なう地盤沈下
に限らず、他の原因による地盤沈下に対しても有効であ
る等、優れた効果がもたらされる。- As can be seen from the above explanation, according to the present invention, even if ground subsidence occurs due to the removal of protective sheet piles during construction of buried pipes, the buried pipe body will undergo uneven settlement, and the pipe body will not be damaged. Excessive stress is not generated, pipe bodies can be buried safely and accurately, and it is effective not only against ground subsidence caused by pulling out sheet piles, but also against ground subsidence caused by other causes. , an excellent effect is brought about.
第1図は埋設配管の施工説明図、第2図は地盤沈下量の
説明図、第3図は埋設管体の不等沈下を示す説明図、第
4図はこの発明による施工工法の一例を示す平面図、第
5図は管体の吊持ち部分を示す断面図、第6図は流動性
固化剤の注入状態を示す説明図、第7図は流動性固化剤
注入方法の他の実施例を示す側面図、第8図は第7図の
A−A線断面図である。
図面において、1・・・冬板、2・・・埋設溝、3・・
・管体、4,5・・・ホー、2.、@・・・枠体、7・
・・フック、8°°°チエンブロツク、9・・・吊上げ
用フック、10・・・落錘フック、11・・・土砂、1
2・・・ポンプ、13・・・空隙、14・・・流動性固
化剤、15・・・ピット、16・・・壁体、17゜18
・・・挿通孔。Figure 1 is an explanatory diagram of the construction of buried pipes, Figure 2 is an explanatory diagram of the amount of ground subsidence, Figure 3 is an explanatory diagram of uneven settlement of buried pipes, and Figure 4 is an example of the construction method according to the present invention. FIG. 5 is a cross-sectional view showing the hanging portion of the pipe body, FIG. 6 is an explanatory diagram showing the injection state of the fluid solidifying agent, and FIG. 7 is another embodiment of the fluid solidifying agent injection method. FIG. 8 is a sectional view taken along line A--A in FIG. 7. In the drawing, 1...winter board, 2...buried trench, 3...
・Pipe body, 4, 5... Ho, 2. , @...frame body, 7.
... Hook, 8°°° chain block, 9 ... Lifting hook, 10 ... Falling weight hook, 11 ... Earth and sand, 1
2...Pump, 13...Gap, 14...Fluid solidifying agent, 15...Pit, 16...Wall, 17°18
...Insertion hole.
Claims (1)
れる埋設溝内に管体を敷設し、ついで前記埋設溝内に土
砂を埋め戻した後、前記矢板を引抜(ことからなる埋設
配管施工方法において、前記矢板の引抜きに当り、埋設
溝内に敷設された管体を、予め水平状態に吊持せしめた
上でこれを行ない、ついで、前記矢板の引抜きによる地
盤沈下の結果生じた管体下面の空隙内に、流動性固化剤
を注入し、しかる後前記管体の吊持を解除することを特
徴とする埋設配管施工方法。1 The pipe body is laid in a buried trench formed by sheet piles driven along the pipeline to be buried, and then, after backfilling the buried trench with earth and sand, the sheet pile is pulled out. In the buried piping construction method, when pulling out the sheet pile, the pipe body laid in the buried trench is suspended in a horizontal state in advance, and then the pipe body is suspended as a result of ground subsidence due to the pulling out of the sheet pile. A method of constructing buried piping, which comprises injecting a fluid solidifying agent into the gap on the lower surface of the pipe body, and then releasing the suspension of the pipe body.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP55089189A JPS5930862B2 (en) | 1980-07-02 | 1980-07-02 | Buried piping construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP55089189A JPS5930862B2 (en) | 1980-07-02 | 1980-07-02 | Buried piping construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5715731A JPS5715731A (en) | 1982-01-27 |
| JPS5930862B2 true JPS5930862B2 (en) | 1984-07-30 |
Family
ID=13963771
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP55089189A Expired JPS5930862B2 (en) | 1980-07-02 | 1980-07-02 | Buried piping construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5930862B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4049306B2 (en) * | 2002-08-27 | 2008-02-20 | ライト工業株式会社 | Subsidence method of underground structure |
-
1980
- 1980-07-02 JP JP55089189A patent/JPS5930862B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5715731A (en) | 1982-01-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7095997B2 (en) | How to join concrete members | |
| US2777294A (en) | Method of laying pipe | |
| JPS5930862B2 (en) | Buried piping construction method | |
| CN116045077B (en) | Large-diameter direct-buried pipeline installation method | |
| JP2776695B2 (en) | Prevention of settlement of buried pipeline by civil engineering sheet | |
| JP2006022551A (en) | Continuous underground wall and mountain retaining method | |
| JP7671124B2 (en) | How to build a tunnel | |
| KR101342180B1 (en) | Hybrid shoe member for extracting pile and extracting method using thereof | |
| JP2576945B2 (en) | Construction method of manhole combined sinking pit and cutting edge to promote sinking | |
| JP3418144B2 (en) | Connection method between human hole and pipe | |
| JP3923482B2 (en) | Underground conduit construction method | |
| JP3483398B2 (en) | Shaft construction method | |
| CN221399292U (en) | Inspection well for pipeline | |
| JPS5914667B2 (en) | How to lay pipes | |
| JPS5930861B2 (en) | Buried piping construction method | |
| JPS6245370B2 (en) | ||
| JP3066293B2 (en) | Earth retaining method in excavation works | |
| JPH11323887A (en) | Pipeline burial method and its equipment | |
| JPH09170259A (en) | How to prevent resin manholes from rising | |
| SU1733571A1 (en) | Method of laying drainage pipes in quicksand soil | |
| JP3080840B2 (en) | How to remove underground pipes | |
| TWI637094B (en) | Continuous wall construction method | |
| JPH0314998B2 (en) | ||
| JP2003027885A (en) | Underground tunnel method and underground tunnel | |
| JP2556415B2 (en) | Construction method of self-supporting retaining wall |