JPS5930861B2 - Buried piping construction method - Google Patents
Buried piping construction methodInfo
- Publication number
- JPS5930861B2 JPS5930861B2 JP55087172A JP8717280A JPS5930861B2 JP S5930861 B2 JPS5930861 B2 JP S5930861B2 JP 55087172 A JP55087172 A JP 55087172A JP 8717280 A JP8717280 A JP 8717280A JP S5930861 B2 JPS5930861 B2 JP S5930861B2
- Authority
- JP
- Japan
- Prior art keywords
- buried
- amount
- pipe body
- ground
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Foundations (AREA)
Description
【発明の詳細な説明】
この発明は、埋設配管施工時に、防護矢板の引抜きの際
における管体の不等沈下を防止した埋設配管施工方法に
関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a buried piping construction method that prevents uneven settling of pipe bodies when pulling out protective sheet piles during construction of buried piping.
一般に、地中への埋設配管施工に当っては第1図に断面
図で示す如く、埋設予定管路に沿って、地中に防護用の
矢板1,1を一定の幅でかつ所定深さに打込み、ついで
矢板1,1間の土砂を所定深さに取り除いて埋設溝2を
造り、埋設溝2の溝底2a上に管体3を敷設し管路を形
成した後、埋設溝2内に土砂を埋め戻し、ついで前記矢
板1゜1を引抜き撤去する工法が行なわれている。Generally, when constructing underground piping, as shown in the cross-sectional view in Figure 1, protective sheet piles 1, 1 are placed underground along the pipeline to a certain width and depth. Then, the earth and sand between the sheet piles 1 and 1 is removed to a predetermined depth to create a buried trench 2, and the pipe body 3 is laid on the bottom 2a of the buried trench 2 to form a conduit. The method used is to backfill with earth and sand, and then pull out and remove the 1.1 sheet pile.
上記工法において、矢板1,1は、埋設溝2の形成に当
り、周辺の土砂が崩壊しないように防護するため打込む
ものであるが、埋設配管施工後は、これを引抜き撤去す
ることが条例等で義務づけられている。In the above construction method, the sheet piles 1, 1 are driven in to protect the surrounding earth and sand from collapsing when forming the buried trench 2, but regulations require that they be pulled out and removed after the buried piping is constructed. It is mandatory.
しかるに、前記矢板1,1を引抜くと、引抜き後地中に
矢板の断面積および引抜きにより持去られる土砂の分だ
け空隙が生じ、そしてこのような空隙を埋めるように土
砂が移動する結果、地盤が沈下する。However, when the sheet piles 1, 1 are pulled out, a void is created in the ground after being pulled out by the cross-sectional area of the sheet pile and the soil removed by the pulling out, and as a result, the soil moves to fill such a void. The ground sinks.
上記した地盤の沈下量は、次のようにして算出される。The amount of ground subsidence mentioned above is calculated as follows.
即ち、第2図イの平面説明図、同図口の側面説明図にお
いて、矢板1の断面積Sは、矢板の幅をH1厚さをtと
すると、5=(HXt)となる。That is, in the plan explanatory view of FIG. 2A and the side explanatory view of the opening in the figure, the cross-sectional area S of the sheet pile 1 is 5=(HXt), where the width of the sheet pile is H1 and the thickness is t.
また、左右2枚で1組の矢板を引抜いた後に生ずる空隙
は、
矢板1組当りの空隙=SxLx2x(1+α)但し、S
:矢板l板の断面積
L:地中における矢板の長さ
α:矢板1板に対する土の付着率
となる。In addition, the gap created after pulling out one set of left and right sheet piles is as follows: Gap per set of sheet piles = SxLx2x (1+α) However, S
: Cross-sectional area of 1 sheet pile L: Length of sheet pile in the ground α: Adhesion rate of soil to 1 sheet pile.
従って、沈下量δは、で表わされる。Therefore, the amount of subsidence δ is expressed as.
例えば、5p−n型の矢板につき、上述の式を当てはめ
ると、L : 600cm、 U:300に771.
H: 40cm、 t : 10crrL、 aキ1゜
A=150函であるところから、
となり、地盤の沈下量は16CrrLになる。For example, applying the above formula to a 5p-n type sheet pile, L: 600cm, U: 300, 771.
Since H: 40cm, t: 10crrL, and 1°A = 150 boxes, the amount of ground subsidence will be 16CrrL.
このような地盤の沈下は、必然的に埋設管の沈下を招く
。Such ground subsidence inevitably causes buried pipes to subside.
埋設管の沈下は、管体と地盤とが一様に沈下する場合に
は特に問題は生じないが、第3図に説明図で示す如く、
管体3の一端がピット4等により固定されている部分で
は、地中に点線で示したように埋設されていた管体3が
、実線で示すような不等沈下をおこす結果、この部分の
管体3aに過大な応力が生じ、損傷を起す原因となる。Subsidence of buried pipes does not pose any particular problem if the pipe body and the ground settle uniformly, but as shown in the explanatory diagram in Figure 3,
In the part where one end of the pipe body 3 is fixed by the pit 4 etc., the pipe body 3 buried in the ground as shown by the dotted line causes uneven settlement as shown by the solid line, and as a result, this part Excessive stress is generated in the tube body 3a, causing damage.
この発明は、上述のような観点から、矢板引抜き後にお
いて地盤沈下に伴なう管体の不等沈下が生ずることのな
い埋設配管施工方法を提供するもので、矢板の引抜きに
より生ずる地盤の沈下量を予め予測し、埋設溝に敷設さ
れた管体な、前記地盤の沈下量に見合う分だけ吊上げた
状態で埋設溝内に土砂を埋め戻し、管体の埋設を行なう
ことに特徴を有するものである。From the above-mentioned viewpoint, the present invention provides a buried piping construction method that does not cause uneven settling of the pipe body due to ground subsidence after pulling out the sheet pile. The feature is that the pipe body is buried by predicting the amount in advance and backfilling the trench with earth and sand while lifting the pipe body by an amount corresponding to the amount of ground subsidence. It is.
次に、この発明を実施例により図面と共に説明する。Next, the present invention will be explained with reference to examples and drawings.
第4図乃至第9図には、この発明方法が工程順に示され
ている。4 to 9 show the method of the invention in the order of steps.
各図において、イは埋設管体の正面図、口はイ図のA−
、A線断面図である。In each figure, A is a front view of the buried pipe body, and the opening is A- in figure A.
, is a sectional view taken along line A.
先ず第4図に示す如く、地中に矢板1,1を打込んだ後
、矢板1,1間の土砂を取除いて埋設溝2を造る。First, as shown in FIG. 4, after sheet piles 1, 1 are driven into the ground, earth and sand between the sheet piles 1, 1 is removed to create a burial trench 2.
3aはピット4に固定された管体、3eは他方側の既設
管体である。3a is a pipe fixed to the pit 4, and 3e is an existing pipe on the other side.
次いで、第5図に示すように、既設管体3a、3c間に
、管体3b。Next, as shown in FIG. 5, a tube 3b is placed between the existing tubes 3a and 3c.
3c、3dを敷設し、各管体同士を溶接により接続する
。3c and 3d are laid, and the respective pipe bodies are connected by welding.
管体3b〜3dの長さlは例えば18m、地表から管体
上面までの深さhは例えば1.5m、管体の直径Rは例
えば600群である
しかる後、第6図に示す如く、接続された管体3b、3
c、3dの中間部に、地上のレッカー車5.5から吊降
された吊り具6,6を懸回し、矢板引抜き後に生ずる地
盤沈下量を前述した算式から予測し、その予測沈下量と
見合う量、即ち予測沈下量と同量かあるいはそれよりl
omm程度多い量だけ、前記レッカー車5,5により上
方へ吊上げる。The length l of the pipe bodies 3b to 3d is, for example, 18 m, the depth h from the ground surface to the top surface of the pipe body is, for example, 1.5 m, and the diameter R of the pipe body is, for example, 600 groups.Thereafter, as shown in FIG. Connected pipe bodies 3b, 3
Suspend the hanging tools 6, 6 suspended from the tow truck 5.5 on the ground between c and 3d, predict the amount of ground subsidence that will occur after pulling out the sheet pile using the above formula, and calculate the amount commensurate with the predicted amount of subsidence. , that is, the amount of subsidence equal to or greater than the predicted subsidence.
It is hoisted upward by the tow truck 5, 5 by an amount of about 0.0 mm.
この状態で、第7図に示す如く、管体ib。3c、3d
の下面に生じた空間部に土砂7の埋め戻しを行ない、埋
め戻された土砂7をよ〈締め固める。In this state, as shown in FIG. 7, the tube body ib. 3c, 3d
The space created on the lower surface is backfilled with earth and sand 7, and the backfilled earth and sand 7 is further compacted.
なお、埋め戻す土砂7は、管体の円周方向下半部分12
0°位の範囲rが適当である。Note that the backfilling earth and sand 7 is applied to the lower half portion 12 in the circumferential direction of the pipe body.
A range r of about 0° is appropriate.
ついで、吊り具6,6を取り外して、第8図に示す如く
埋設溝2内の全部に土砂の埋め戻しを行ない、しかる後
矢板1,1を引抜く。Next, the hanging tools 6, 6 are removed, and the entire buried trench 2 is backfilled with earth and sand, as shown in FIG. 8, and after that, the sheet piles 1, 1 are pulled out.
第9図は矢板引抜き後の状態を示したもので、矢板引抜
き後の地盤沈下により、地盤は、矢板引抜き前の点線で
示す状態から、実線で示す状態に沈下する。FIG. 9 shows the state after the sheet pile is pulled out. Due to the ground subsidence after the sheet pile is pulled out, the ground sinks from the state shown by the dotted line before the sheet pile is pulled out to the state shown by the solid line.
この際、予め地盤沈下量に見合う分だけ上方に引き上げ
ておいた点線で示す埋設管体3b、3c、3dは、地盤
沈下と共に沈下して、実線づ示す敷設時の正常な状態に
戻る。At this time, the buried pipes 3b, 3c, and 3d shown by dotted lines, which have been raised in advance by an amount corresponding to the amount of ground subsidence, sink with the ground subsidence and return to the normal state at the time of installation shown by solid lines.
従って地盤沈下により管体が不等沈下を起すことはなく
なる。Therefore, the pipe body will not settle unevenly due to ground subsidence.
上述した説明かられかるように、この発明によれば、埋
設配管施工時に、防護矢板の引抜きに伴って地盤沈下が
発生しても、埋設管体が不等沈下を起し、管体に過大な
応力が発生することはなく、安全適確な管体の埋設を行
なうことができ、矢板引抜きに伴なう地盤沈下に限らず
、他の原因による地盤沈下に対しても有効である等、優
れた効果がもたらされる。As can be seen from the above description, according to the present invention, even if ground subsidence occurs due to the removal of protective sheet piles during construction of buried pipes, the buried pipe bodies will settle unevenly, causing excessive damage to the pipe bodies. This method does not generate any significant stress, allowing pipe bodies to be buried safely and accurately, and is effective not only against ground subsidence caused by pulling out sheet piles, but also against ground subsidence caused by other causes. Excellent effects are brought about.
第1図は埋設配管の施工断面図、第2図は地盤沈下量の
説明図、第3図は埋設配管の不等沈下状態を示す説明図
、第4図乃至第9図はこの発明方法を工程順に示す説明
図である。
図面において、1・・・矢板、2・・・埋設溝、3・・
・管体、4・・・ピット、5・・・レッカー車、6・・
・吊り具、7・・・土砂。Figure 1 is a cross-sectional view of the construction of the buried pipe, Figure 2 is an explanatory diagram of the amount of ground subsidence, Figure 3 is an explanatory diagram showing the state of uneven settlement of the buried pipe, and Figures 4 to 9 show the method of this invention. It is an explanatory diagram showing the order of steps. In the drawing, 1... Sheet pile, 2... Buried trench, 3...
・Pipe body, 4... Pit, 5... Tow truck, 6...
- Hanging equipment, 7...earth and sand.
Claims (1)
れる埋設溝内に管体を敷設し、ついで前記埋設溝内に土
砂を埋め戻した後、前記矢板を引抜くことからなる埋設
配管施工方法において、前記矢板の引抜きにより生ずる
地盤の沈下量を予め予測し、埋設溝内に敷設された管体
な、前記地盤の沈下量に見合う分だけ吊上げた状態で埋
設溝内に土砂を埋め戻し、管体の埋設を行なうことを特
徴とする埋設配管施工方法。1 Buried piping consisting of laying a pipe body in a buried trench formed by sheet piles driven along a pipeline to be buried, then backfilling the buried trench with earth and sand, and then pulling out the sheet piles. In the construction method, the amount of ground subsidence caused by pulling out the sheet pile is predicted in advance, and the pipes laid in the buried trench are lifted by an amount corresponding to the amount of ground subsidence, and earth and sand is buried in the buried trench. A buried pipe construction method characterized by returning the pipe body and burying the pipe body.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP55087172A JPS5930861B2 (en) | 1980-06-26 | 1980-06-26 | Buried piping construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP55087172A JPS5930861B2 (en) | 1980-06-26 | 1980-06-26 | Buried piping construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5712733A JPS5712733A (en) | 1982-01-22 |
| JPS5930861B2 true JPS5930861B2 (en) | 1984-07-30 |
Family
ID=13907561
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP55087172A Expired JPS5930861B2 (en) | 1980-06-26 | 1980-06-26 | Buried piping construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5930861B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2728547B2 (en) * | 1990-06-13 | 1998-03-18 | 株式会社日立製作所 | Diversity receiver |
| JPH0581015U (en) * | 1992-03-02 | 1993-11-02 | 東洋ファイバー株式会社 | Handle |
-
1980
- 1980-06-26 JP JP55087172A patent/JPS5930861B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5712733A (en) | 1982-01-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US2777294A (en) | Method of laying pipe | |
| JPS5930861B2 (en) | Buried piping construction method | |
| CN213839806U (en) | Underground direct buried pipe reinforcing structure | |
| JP2776695B2 (en) | Prevention of settlement of buried pipeline by civil engineering sheet | |
| JP3495412B2 (en) | Pipe laying method | |
| JPS5930862B2 (en) | Buried piping construction method | |
| JPS5914667B2 (en) | How to lay pipes | |
| JPH01174729A (en) | Method for burying pipe | |
| JPS609179B2 (en) | Large diameter pipe buried turning method | |
| JPH02102983A (en) | Pipeline protection method | |
| JPS5840072B2 (en) | How to lay pipes | |
| JPH08261360A (en) | Underground pipe laying method | |
| JPS6133071Y2 (en) | ||
| JPS5833337B2 (en) | How to bury the pipe | |
| JPS6088786A (en) | Formation of shaft pit for propelling embedded pipe in embedded pipe underground propelling method | |
| JPH07119162A (en) | Method for protecting buried pipes under footing foundation | |
| JPH02213538A (en) | Civil work method of underground pipe | |
| JPS61112880A (en) | How to lay large-diameter buried steel pipes | |
| JPS604685A (en) | Method of burying construction of pipe | |
| JPH0681981A (en) | Rib pipe burying method | |
| JPS62127587A (en) | Method for preventing floating of buried pipes | |
| JPH03241196A (en) | Earthwork for underground piping | |
| JPH0814349B2 (en) | Civil engineering method for underground pipes | |
| JPH0123629B2 (en) | ||
| JPH0333584A (en) | How to lay underground pipes |