JPH0258440B2 - - Google Patents
Info
- Publication number
- JPH0258440B2 JPH0258440B2 JP58084237A JP8423783A JPH0258440B2 JP H0258440 B2 JPH0258440 B2 JP H0258440B2 JP 58084237 A JP58084237 A JP 58084237A JP 8423783 A JP8423783 A JP 8423783A JP H0258440 B2 JPH0258440 B2 JP H0258440B2
- Authority
- JP
- Japan
- Prior art keywords
- precast
- tunnel
- lining
- ring
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 claims description 15
- 239000000463 material Substances 0.000 claims description 9
- 238000000034 method Methods 0.000 claims description 2
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 239000004567 concrete Substances 0.000 description 8
- 239000011435 rock Substances 0.000 description 5
- 239000011378 shotcrete Substances 0.000 description 5
- 238000009415 formwork Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000011210 fiber-reinforced concrete Substances 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000000088 plastic resin Substances 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【発明の詳細な説明】
本発明は、NATM工法によるトンネルの構築
に際して、現場打コンクリートによる2次覆工作
業によらず、工場において製作された薄板製プレ
キヤスト部材によつて順次内張を行うことによつ
てトンネル築造の能率向上および省力化、経済化
を図ることを目的としたものである。[Detailed Description of the Invention] When constructing a tunnel using the NATM construction method, the present invention provides a method for sequentially lining the tunnel with thin plate precast members manufactured in a factory, without performing secondary lining work using cast-in-place concrete. The purpose of this project is to improve efficiency, save labor, and make tunnel construction more economical.
一般に行われているNATM工法によりトンネ
ルを構築する場合の施工順序は大別して、地山の
掘削、1次覆工、2次覆工の3作業からなる。す
なわち地山を掘削した後、地山を補強し、掘削さ
れた空洞を保持するために吹付コンクリート、ロ
ツクボルト、鋼製支保工等の支保によつて1次覆
工を行い、この1次覆工されたトンネルが安定し
た後現場打コンクリートによつて所定断面形態に
2次覆工を施工するものである。 When constructing a tunnel using the commonly used NATM construction method, the construction sequence can be roughly divided into three steps: excavation of the ground, primary lining, and secondary lining. In other words, after excavating the ground, a primary lining is performed using shotcrete, rock bolts, steel shoring, etc. to reinforce the ground and hold the excavated cavity. After the tunnel is stabilized, a secondary lining is constructed using cast-in-place concrete in a predetermined cross-section.
この場合、2次覆工は普通のトンネル構築工法
と同様に、型枠を組立てて覆工コンクリートの打
設を行い、その養生後型枠を撤去して清掃を行
う、という作業の1サイクルとなつているので、
多くの時間と労力を要しかつNATMトンネルの
2次覆工に発生する特有のひび割れに対する施工
管理、品質管理等にも困難がある。またこの2次
覆工は地山岩盤が堅硬で長期的に風化のおそれが
ない場合でも施工上から30cm程度の厚い層に打設
するのが一般的である。 In this case, the secondary lining is similar to ordinary tunnel construction methods, consisting of one cycle of work: assembling the formwork, pouring the lining concrete, and removing the formwork after curing and cleaning. Because I'm getting used to it,
It requires a lot of time and effort, and there are also difficulties in construction management and quality control to deal with the unique cracks that occur in the secondary lining of NATM tunnels. In addition, this secondary lining is generally installed in a thick layer of about 30 cm above the construction site, even if the ground bedrock is solid and there is no risk of long-term weathering.
本発明はこのような実情に鑑みて、NATM工
法によつて施工されたトンネルの2次覆工の施工
に当り、1次覆工(吹付コンクリート、ロツクボ
ルト等の支保)によつて安定したトンネル内面
に、予かじめ工場で製作した大形で薄肉のプレキ
ヤスト板をアンカーボルトによつて設定すること
によつて迅速かつ容易にトンネルの2次覆工作業
を行うことを特徴とする工法に関するものであつ
て、その工法を図面の1実施例について説明すれ
ば、覆工後のトンネル断面形態は第1図に示すよ
うに構成される。すなわちNATM工法によるト
ンネルの1次覆工(地山Xに打設したロツクボル
トa、吹付コンクリートb)と2次覆工となるプ
レキヤスト板A,Bおよびこれを地山に固定する
アンカーボルトC更に両側下端のプレキヤスト板
の固定脚部となる側壁コンクリートdより構成さ
れる。而してこの2次覆工を構成するプレキヤス
ト板Aは第2図に示すように、本体を鉄筋コンク
リート、繊維補強コンクリート、金属、高強度プ
ラスチツク樹脂等より成る板体によつて長辺1、
短辺2よりなる平面形体長方形にして端面形状を
第3図および第5図に示すように例えば山形に形
成し、その長辺1の相対する上縁に凸縁1′,
1′をまた短辺2に相対する上面にも凸縁2′,
2′を設けて一連の周縁を形成し更に長辺1の相
対する凸縁1′,1′間に亘つて適当数のリブ3−
−を設けて補強したものである。なお、この凸縁
および補強リブは本体の内側に設けることもあ
る。またこの長辺1,1の両端部には円周方向に
隣接するプレキヤスト板Aとの接合のためにその
一方の縁の上部には凸縁4をまたその下面には凹
溝5および防水用コーキング溝5′を設け、他方
の縁の下部には前記凹溝5に対応する凸条6を設
けてその上面に凹溝7をそれぞれ長手方向に形成
し、短辺2,2の一方の端面にはリング同士の接
合のためのピンホール8−−を設けると共に他方
の端面にはピン9−−を突設したものである。ま
た前記リブ3には第4図に示すように、運搬組立
用ボルト金具を着脱し得るように上下面に通ずる
取付孔10を適当に設け、組立設定した後この取
付孔を利用して裏込材の注入、打設にも併用し得
るようにしたものである。またこのプレキヤスト
板を地山に締結するためにその上面に適当数のア
ンカー取付孔11−−を設けたものである。また
このプレキヤスト板の内面には必要に応じて既製
の内装材を貼付したり、内表面自体を表面加工し
て内装材としての機能を持たせるものである。 In view of these circumstances, the present invention provides a stable inner surface of the tunnel by the primary lining (supporting with shotcrete, rock bolts, etc.) when constructing the secondary lining of a tunnel constructed using the NATM construction method. This invention relates to a construction method characterized by quickly and easily performing secondary lining work for tunnels by setting large, thin-walled precast plates prefabricated in a factory using anchor bolts. The construction method will be explained with reference to one embodiment of the drawings.The cross-sectional form of the tunnel after lining is constructed as shown in FIG. In other words, the primary lining of the tunnel using the NATM construction method (rock bolts a cast into the ground X, shotcrete b), the precast plates A and B that will serve as the secondary lining, and the anchor bolts C that fix this to the ground, and then on both sides. It is made up of side wall concrete d that serves as the fixed leg of the precast plate at the lower end. As shown in Fig. 2, the precast board A constituting this secondary lining has a main body made of reinforced concrete, fiber reinforced concrete, metal, high-strength plastic resin, etc.
The planar shape is rectangular with short sides 2, and the end faces are formed into, for example, a chevron shape as shown in FIGS.
1' is also provided with a convex edge 2' on the upper surface opposite to the short side 2,
2' to form a series of peripheral edges, and a suitable number of ribs 3-- extending between opposing convex edges 1', 1' on the long side 1.
This is reinforced by adding -. Note that the convex edges and reinforcing ribs may be provided inside the main body. Further, at both ends of the long sides 1, 1, a convex edge 4 is provided at the upper part of one edge for joining with the precast plate A adjacent in the circumferential direction, and a concave groove 5 and a waterproof groove are provided at the lower surface of the edge. A caulking groove 5' is provided, a convex strip 6 corresponding to the concave groove 5 is provided at the lower part of the other edge, a concave groove 7 is formed in the longitudinal direction on the upper surface thereof, and one end surface of the short sides 2, 2 is provided. A pin hole 8 is provided for joining the rings together, and a pin 9 is provided protruding from the other end surface. In addition, as shown in Fig. 4, the rib 3 is appropriately provided with a mounting hole 10 that communicates with the upper and lower surfaces so that bolt fittings for transportation and assembly can be attached and removed. It can also be used for pouring and placing materials. Further, in order to fasten this precast plate to the ground, an appropriate number of anchor attachment holes 11 are provided on the upper surface of the precast plate. Furthermore, if necessary, a ready-made interior material may be attached to the inner surface of this precast board, or the inner surface itself may be surface-treated to provide a function as an interior material.
以上のように構成したプレキヤスト板による2
次覆工作業について説明すれば、先ず地山を掘削
してその地山Xに対してロツクボルトa、吹付コ
ンクリートbの1次覆工を施こし、インバートコ
ンクリートおよび2次覆工材の固定却部となる両
側壁コンクリートd,dを打設する。この側壁コ
ンクリートdはプレキヤスト板A,Bを組立てる
際の基礎となるもので適当な高さに設定し、これ
に第1図に示すように最下部のプレキヤスト板A
またはBの脚部を固定するものである。 2 by the precast board configured as above
To explain the next lining work, first, the ground is excavated, and the first lining of rock bolt a and shotcrete b is applied to the ground Pour concrete d and d on both sides. This side wall concrete d will serve as the foundation for assembling precast plates A and B, and is set at an appropriate height.
Or it is something that fixes the legs of B.
このようにして1次覆工により地山が安定した
後2次覆工材取付用吊下アンカーボルトc−−を
取付け、プレキヤスト板A,Bの組立を行うので
あるが、その組立には第1図に示すようにエレク
ター装置C、作業台D、支保装置Eより成る組立
装置により行うものである。すなわち先ずプレキ
ヤスト板AをエレクターCによつて支持して設定
位置に移動させて第1図に示すように予かじめ地
山岩盤に取りつけたアンカーボルトcに締結して
始めの1枚を設置する。次いで順次同様の組立作
業を第6図に示す要領で円周方向に下方より上方
へと順次行い、最後にクラウン部附近で両側のプ
レキヤスト板A,A間に、キーとなるプレキヤス
ト板B(ハーフサイズ)を軸方向に挿入して閉合
する。このようにして円周方向の一リング分の組
立を行い、次位リングのプレキヤスト板Aおよび
Bの組立は前に設置したリングの端部に設けたピ
ンホール8に対して、次位のプレキヤスト板Aを
軸方向にずらせてその端縁に設けたピン9を嵌入
設定すると共に円周方向に対する両側縁の接合
は、長手方向に設けた掛け合わせ凹溝5と凸条6
を係合させて次位のリングを構成するものであ
る。而してこのリングは直接地山にアンカーボル
トによつて結合することなく、次位のリング組立
まで支保装置E等によつて支持し、このリングに
次いで設定する隣接するリングを前記と同様にし
て組み立ててアンカーボルトによつて地山に結合
した後前者の支保装置Eを撤去する。すなわち一
リング置きに地山に結合することになる。またこ
れ等隣接リングの組立に際してリング構成の最後
に挿入設定するキーとなるプレキヤスト板Bは第
6図に示すように同一位相に位置しないように千
鳥状に配置するものである。なお、上記したよう
にして2次覆工を行つた後必要に応じて各覆工材
に設けた運搬、組立用ボルトの取付孔10を通し
て2次覆工材Aと地山Xとの空間に裏込材を注入
充填することもある。 After the ground has been stabilized by the primary lining in this way, the hanging anchor bolts c-- for attaching the secondary lining material are attached, and the precast plates A and B are assembled. As shown in Figure 1, this is carried out using an assembly device consisting of an erector device C, a workbench D, and a support device E. That is, first, the precast plate A is supported by the erector C and moved to the set position, and as shown in Fig. 1, the first plate is installed by fastening it to the anchor bolt c previously attached to the rock mass. . Next, the same assembly work is sequentially performed in the circumferential direction from the bottom to the top as shown in Fig. 6.Finally, the key precast plate B (half size) in the axial direction and close it. In this way, one ring is assembled in the circumferential direction, and when assembling the precast plates A and B of the next ring, insert the precast plates A and B of the next ring into the pinholes 8 made at the ends of the rings installed before. The plate A is shifted in the axial direction and a pin 9 provided on the edge thereof is inserted and set, and the edges on both sides in the circumferential direction are joined by interlocking grooves 5 and protrusions 6 provided in the longitudinal direction.
The next ring is constructed by engaging the two rings. Therefore, this ring is not directly connected to the ground with anchor bolts, but is supported by supporting device E etc. until the next ring is assembled, and the adjacent ring to be set after this ring is set in the same manner as above. After assembling and connecting to the ground with anchor bolts, the former supporting device E is removed. In other words, every other ring is connected to the ground. Further, when assembling these adjacent rings, the precast plates B, which serve as keys inserted at the end of the ring configuration, are arranged in a staggered manner so as not to be located in the same phase, as shown in FIG. After performing the secondary lining as described above, if necessary, insert holes into the space between the secondary lining material A and the ground X through the mounting holes 10 for transportation and assembly bolts provided in each lining material. Sometimes backfilling material is injected and filled.
以上のように本発明工法においては、NATM
工法によるトンネルの構築に当り、従来の現場打
コンクリートによる2次覆工によらず、薄肉でし
かも平板によつて断面形状山形または曲面でかつ
運搬、坑内での組立作業等に支障のない程度に大
型に作成された内装材を兼ねたプレキヤスト板を
使用することによりトンネル坑内での設定作業が
簡素化されるばかりでなくその併用開始時期も早
めることができる等格段の効果、特徴がある。 As mentioned above, in the construction method of the present invention, NATM
When constructing a tunnel using this construction method, instead of using the conventional secondary lining using cast concrete on-site, we constructed a thin-walled, flat plate with a chevron-shaped or curved cross-section to the extent that it does not hinder transportation, assembly work, etc. in the tunnel. By using a large-sized precast board that also serves as interior material, it not only simplifies the installation work inside the tunnel, but also has remarkable effects and features such as being able to start its combined use earlier.
第1図は本発明工法により設定されたトンネル
および組立態様を示す正面図、第2図はプレキヤ
スト板の一例を示す平面図、第3図は第2図のX
−X′断面図、第4図は第1図のY−Y′断面図、
第5図は斜面図、第6図はプレキヤスト板の配設
態様を示す説明図である。
A……プレキヤスト板、B……キーとなるプレ
キヤスト板、1……プレキヤスト板の長辺、2…
…同短辺、1′,2′……凸縁、3……リブ、4…
…凸縁、5……凹条、5′……コーキング溝、6
……凸条、7……凹条、8……ピンホール、9…
…ピン、10……裏込注入兼ボルト取付孔、11
……アンカー取付孔、a……ロツクボルト、b…
…吹付コンクリート、c……アンカーボルト、d
……側壁コンクリート、x……地山。
Fig. 1 is a front view showing the tunnel set up by the construction method of the present invention and the assembly mode, Fig. 2 is a plan view showing an example of a precast board, and Fig. 3 is the X of Fig. 2.
-X' sectional view, Figure 4 is the Y-Y' sectional view of Figure 1,
FIG. 5 is a perspective view, and FIG. 6 is an explanatory diagram showing the manner in which the precast plates are arranged. A... Precast board, B... Precast board serving as a key, 1... Long side of the precast board, 2...
...same short side, 1', 2'...convex edge, 3...rib, 4...
...Convex edge, 5...Concave line, 5'...Caulking groove, 6
...Convex strip, 7...Concave strip, 8...Pinhole, 9...
...Pin, 10...Back filling injection and bolt mounting hole, 11
...Anchor mounting hole, a... Lock bolt, b...
...Shotcrete, c...Anchor bolt, d
...Side wall concrete, x...ground.
Claims (1)
いは老朽化したトンネルの補修等のような安定し
たトンネル内の1次覆工内面に対して、薄肉の平
板の周縁および内側に補強リブを設けた内装材を
兼ねたプレキヤスト折板部材または曲面部材をア
ンカーボルトによつて円周方向に順次配設して1
リングを形成すると共に、このリングに対して、
次位のプレイキヤスト折板または曲面部材による
リングを端面のピンホールおよびピンによつて組
立構築することを特徴とするプレキヤスト部材に
よるNATM工法におけるトンネル2次覆工の構
築工法。1 For the inner surface of the primary lining in a stable tunnel, such as a tunnel excavated using the NATM construction method or for repairing an old tunnel, a thin flat plate with reinforcing ribs on the periphery and inside can also be used as an interior material. Precast folded plate members or curved surface members are sequentially arranged in the circumferential direction using anchor bolts.
While forming a ring, for this ring,
A method for constructing a secondary tunnel lining in the NATM construction method using precast members, characterized by assembling and constructing a ring made of the next precast folded plate or curved member using pinholes and pins on the end face.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58084237A JPS59210198A (en) | 1983-05-16 | 1983-05-16 | Method of construction of tunnel secondary lining in method of natm construction by precast member |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58084237A JPS59210198A (en) | 1983-05-16 | 1983-05-16 | Method of construction of tunnel secondary lining in method of natm construction by precast member |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS59210198A JPS59210198A (en) | 1984-11-28 |
| JPH0258440B2 true JPH0258440B2 (en) | 1990-12-07 |
Family
ID=13824860
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP58084237A Granted JPS59210198A (en) | 1983-05-16 | 1983-05-16 | Method of construction of tunnel secondary lining in method of natm construction by precast member |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS59210198A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH05111526A (en) * | 1991-08-09 | 1993-05-07 | Noel E Zeller | Medicinal container |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6131599A (en) * | 1984-07-24 | 1986-02-14 | 日本コンクリ−ト工業株式会社 | Tunnel covering construction method |
| JPS6126797U (en) * | 1984-07-24 | 1986-02-18 | 日本コンクリ−ト工業株式会社 | PC board for tunnel lining |
| JPH0598893A (en) * | 1991-10-09 | 1993-04-20 | Fujita Corp | Tunnel lining construction method |
| JP7288301B2 (en) * | 2018-12-27 | 2023-06-07 | 日鉄建材株式会社 | Underground structure construction method and underground structure |
| JP7420644B2 (en) * | 2020-05-22 | 2024-01-23 | 地中空間開発株式会社 | Segment disassembly and assembly equipment, tunnel excavation machine and segment disassembly and assembly method |
-
1983
- 1983-05-16 JP JP58084237A patent/JPS59210198A/en active Granted
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH05111526A (en) * | 1991-08-09 | 1993-05-07 | Noel E Zeller | Medicinal container |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS59210198A (en) | 1984-11-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101167511B1 (en) | Underpass using precast concrete pile and method for constructing the same | |
| JPH06272495A (en) | Construction method of tunnel | |
| JPH07292783A (en) | Connective structure of prestressed concrete members | |
| JPH0258440B2 (en) | ||
| JPH07103785B2 (en) | Segment that does not require joint bolts | |
| JPH06129189A (en) | Vertical shaft construction method using segments | |
| JPS6332095A (en) | Segment coating construction method and concrete segment also used as mold frame | |
| JPH084033A (en) | Construction method of the pressure barrier against the outer perimeter of the building | |
| JPS5853321Y2 (en) | Element for mountain retainer | |
| JP2733722B2 (en) | Construction method of deep foundation pile type retaining wall | |
| JPH10299003A (en) | Foundation method using precast concrete members | |
| JPS59134228A (en) | Integration work of pile or continuous wall and footing | |
| JPH0353439B2 (en) | ||
| JP7633891B2 (en) | Method for constructing underground structure, underground structure, and precast concrete side or intermediate wall/column therefor | |
| JPS5841227Y2 (en) | Element for mountain retainer | |
| JP2572680B2 (en) | Underground structure by reverse strike method | |
| KR20010035996A (en) | An accessory for concrete block attachment | |
| JP2631066B2 (en) | Underground rectangular body construction method | |
| JP3291544B2 (en) | Split assembling method for box culvert construction | |
| JPS6024249B2 (en) | How to build a basement | |
| JPH02248527A (en) | Constructing foundation structure | |
| JP2000178985A (en) | Basement | |
| JPH0539611A (en) | Method for building underground housing chamber | |
| JPH076204B2 (en) | How to build an underground structure | |
| JPH0754336A (en) | Construction method of composite wall body |