JP4290963B2 - Clean room construction method - Google Patents
[go: Go Back, main page]

JP4290963B2 - Clean room construction method - Google Patents

Clean room construction method Download PDF

Info

Publication number
JP4290963B2
JP4290963B2 JP2002329421A JP2002329421A JP4290963B2 JP 4290963 B2 JP4290963 B2 JP 4290963B2 JP 2002329421 A JP2002329421 A JP 2002329421A JP 2002329421 A JP2002329421 A JP 2002329421A JP 4290963 B2 JP4290963 B2 JP 4290963B2
Authority
JP
Japan
Prior art keywords
clean room
construction
dust
work
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002329421A
Other languages
Japanese (ja)
Other versions
JP2004163004A (en
Inventor
憲司 村岡
正泰 三浦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP2002329421A priority Critical patent/JP4290963B2/en
Publication of JP2004163004A publication Critical patent/JP2004163004A/en
Application granted granted Critical
Publication of JP4290963B2 publication Critical patent/JP4290963B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Ventilation (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、半導体製造等に使用されるクリーンルームの施工方法に関する。
【0002】
【従来の技術】
従来、半導体製造工場、手術室等のクリーンルームが知られている。このクリーンルームの施工に際しては、クリーンルームの清浄度を、低コスト,短工期で最終レベルにするために、建物建設段階からクリーン化対策を行なっている。即ち、施工中の毎日の掃除、周毎の掃除を徹底し、また、躯体工事、鉄骨工事完了後は、入室者に対して上履き入室を義務付け、その後、施工が進む毎に、入室者に対して、クリーンスーツの着用、さらにはエアーシャワーを介しての入室を義務付ける等してクリーン施工化を図っている。
【0003】
【発明が解決しようとする課題】
従来のクリーンルームの施工においては、施工中の換気は、所定の換気口を介して外気を入れる自然換気を行なっていたので、特に夏季等においては、施工中のクリーンルーム内に結露が発生し、結露除去作業が大変であるという課題があった。
【0004】
【課題を解決するための手段】
本発明によるクリーンルームの施工方法によれば、クリーンルームの内装工事に入る前においては、クリーンルームの躯体床上にシート材を敷設して躯体床からの発塵による粉塵の浮遊を防止するとともに、施工中のクリーンルーム内に水を噴霧して施工中のクリーンルーム内に浮遊している粉塵を噴霧水に付着させてシート上に落下させ、クリーンルームの内装工事以後においては、施工中のクリーンルーム内にドライエアを供給して内装仕上げ表面における結露を防止したので、クリーンルームの内装工事に入る前においては、施工中のクリーンルーム内での粉塵の浮遊を防止できるとともに、クリーンルームの内装工事以後においては、内装仕上げ表面の結露を防止できる。
【0005】
【発明の実施の形態】
以下、本発明の実施の形態を図1,図2に基づき説明する。まず、本実施の形態における半導体製造工場のクリーンルームの概要を図2に基づいて説明する。一般に、クリーンルームは3つのエリアに区切られた構造となっている。即ち、半導体製造や検査などに必要な精密機器が設置されるプロセスエリア10と、床下エリア20と、天井エリア30とを備える。プロセスエリア10の床は有孔床(グレーチング)11となっており、プロセスエリア10の天井は有孔天井12となっている。天井エリア30には、空調機31と空気洗浄フィルタ32が設けられている。プロセスエリア10の横には空気循環空間10Aが設けられ、これにより、空気が空気洗浄フィルタ32で浄化されて、矢示のように各エリア10,20,30を循環する構造となっている。また、出入口40と外部との間にはエアーシャワーが装備された前室が設けられており、クリーンルームへの入室者は前室で空気洗浄を行なった後にクリーンルーム内に入る。前室は、クリーンルーム側のドア40aと外部側のドアとで密閉空間となる。尚、41は空気循環空間10Aとプロセスエリア10との間の出入口、41aはこの出入口41のドア、42は柱、42aは有孔床11の鉄骨根太、43,44は耐火被覆梁、45は二重窓、46は廊下、47は配線を収納する配線ピットである。
【0006】
次に、実施の形態によるクリーンルームの施工方法を図1を参照して順を追って説明する。ここでは、施工管理を6段階に分けて実施した例を示す。
・ステップ1
躯体工事、鉄骨建方工事等を行なう。このステップ1から入室者の出入口、資材等の搬入口が指定される。そして、日々の作業が終了する毎及び周毎に、掃き掃除を行なう。
ステップ1の躯体工事の完了直後に、図1に示すように、床下エリア20の躯体床21上にシート材1を敷設し、噴霧機2により、施工中のクリーンルーム内に水を噴霧する。
このように、躯体工事の完了直後に、床下エリア20の躯体床21上に、シート材1を敷設することにより、躯体床21からの発塵による粉塵の浮遊を防止でき、さらに、水を噴霧することにより、施工中のクリーンルーム内に浮遊している粉塵は噴霧水2aに付着してシート材1上に落下するので、施工中のクリーンルームの空間に浮遊する粉塵を効率的に除去できる。
尚、粉塵を付着してシート材1上に落下した噴霧水2aは、適宜掃除機で吸い取る。また、噴霧は毎日行ない、シート材1は汚れ具合によって適宜取り替える。
このように躯体床21上にシート材1を敷設して施工中のクリーンルーム内に水を噴霧することによる防塵及び徐塵作業は、ステップ3に移るまで行なう。
・ステップ2
足場組立工事、ALC版等の壁下地コンクリート成形板,壁下地ボード,天井デッキ,耐火被覆ケイカル板の取付工事、建具取付工事、天井デッキ塗装工事等を行なう。このステップ2から入室者に上履きによる入室を義務付ける。また、日々の作業が終了する毎及び周毎に、掃除機等を用いて掃除を行なう。
・ステップ3
足場解体工事、床の塗装工事、クロス貼り工事、シーリング工事、建具,鉄骨の塗装工事等を行なう。このステップ3からは、建具を常時閉鎖するとともに、図1に示すように、仮設の空調機3(例えば防塵機能付きエアコン)を用いて施工中のクリーンルーム内にドライエア3aを送る。これにより、施工中のクリーンルーム内の結露、特に、クロス表面、塗装表面等の内装仕上げ表面における結露を防止できる。尚、この仮設の空調機3によるドライエア3aの供給は、天井エリア30に空調機31が設置され運転されるまで続ける。また、ステップ2と同様な掃除を行なう。
・ステップ4
有孔床(グレーチング)工事、天井エリア工事、動力配管配線工事、空調ダクト配管工事等を行なう。このステップ4から入室者にクリーンスーツ(ラフなもの)の着用を義務付ける。また、日々の作業が終了する毎及び周毎に、水拭き掃除を行なう。
・ステップ5
プロセスエリア10の内壁パネル取付工事、床下設備設置作業、純水配管作業、薬液配管作業等を行なう。このステップ5からは正規入室ルートでの入室、即ち、前室からの入室を義務付ける。また、毎日の掃除、周毎の一斉掃除において、内装材を純水で拭き掃除する。
・ステップ6
空調機31,空気洗浄フィルタ32の取付工事、ガス機器工事、空調機31の試運転(空気循環運転)等を行なう。このステップ6からは正規のクリーンスーツの着用及びエアーシャワーを経た入室を義務付ける。また、ステップ5と同様な掃除を行なう。
【0007】
尚、上記では、ステップ3以降、即ち、内装工事に入った時から、施工中のクリーンルーム内にドライエア3aを供給する例を示したが、クリーンルームの空間がある程度閉じている場合は、ステップ1からドライエア3aを供給するようにしてもよい。
また、上記シート材1として、例えば、液状の防水剤を含浸させたウエットシートを用いれば、このウエットシート上に一旦落下した粉塵が再び空間に舞い上がって浮遊するようなことも防止でき、さらに、防水処理が施されているので、粉塵を付着した噴霧水2aが躯体床21に浸透して躯体床21上を汚してしまうようなことも防止できる。
また、上記各ステップによる工事の区分けは一例であり、これに限るわけではない。
【0008】
【発明の効果】
本発明によれば、クリーンルームの内装工事に入る前においては、施工中のクリーンルーム内での粉塵の浮遊を防止できるとともに、クリーンルームの内装工事以後においては、内装仕上げ表面の結露を防止できる。
【図面の簡単な説明】
【図1】 本発明の実施の形態によるクリーンルームの施工方法を説明するための説明図である。
【図2】 実施の形態による施工方法により施工されたクリーンルームの概要を示す断面図。
【符号の説明】
3 空調機、3a ドライエア。
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method for a clean room used for semiconductor manufacturing or the like.
[0002]
[Prior art]
Conventionally, clean rooms such as semiconductor manufacturing factories and operating rooms are known. In the construction of this clean room, cleanup measures are taken from the building construction stage in order to bring the clean room to the final level with low cost and short construction period. In other words, daily cleaning during construction and cleaning every lap are thorough, and after completion of the frame construction and steelwork construction, it is mandatory for the occupants to enter their shoes and every time the construction proceeds, Clean construction is required by wearing clean suits and requiring entry through an air shower.
[0003]
[Problems to be solved by the invention]
In conventional clean room construction, the ventilation during construction was naturally ventilated with outside air through a predetermined ventilation port, so condensation formed in the clean room under construction, especially in summer, caused condensation. There was a problem that the removal work was difficult.
[0004]
[Means for Solving the Problems]
According to the construction method of the clean room according to the present invention, before entering the interior construction of the clean room, a sheet material is laid on the cabinet floor of the clean room to prevent dust from floating due to dust generation from the cabinet floor, Water is sprayed into the clean room, and the dust floating in the clean room under construction is attached to the spray water and dropped onto the seat.After the interior construction of the clean room, dry air is supplied to the clean room under construction. Having preventing condensation on interior finish surface Te, before entering the interior construction of the clean room, it is possible to prevent floating of dust in a clean room in construction, Oite the interior work after the clean room, the interior finish surfaces Condensation can be prevented.
[0005]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to FIGS. First, an outline of a clean room of a semiconductor manufacturing factory in the present embodiment will be described with reference to FIG. Generally, a clean room has a structure divided into three areas. That is, it includes a process area 10 in which precision equipment necessary for semiconductor manufacturing and inspection is installed, an underfloor area 20, and a ceiling area 30. The floor of the process area 10 is a perforated floor (grating) 11, and the ceiling of the process area 10 is a perforated ceiling 12. In the ceiling area 30, an air conditioner 31 and an air cleaning filter 32 are provided. An air circulation space 10A is provided on the side of the process area 10 so that the air is purified by the air cleaning filter 32 and circulates in the respective areas 10, 20, and 30 as indicated by arrows. A front room equipped with an air shower is provided between the entrance 40 and the outside, and a person entering the clean room enters the clean room after performing air cleaning in the front room. The front room becomes a sealed space with the door 40a on the clean room side and the door on the outside side. Incidentally, 41 is an entrance / exit between the air circulation space 10A and the process area 10, 41a is a door of the entrance / exit 41, 42 is a pillar, 42a is a steel joist of the perforated floor 11, 43 and 44 are fire-resistant coated beams, 45 is A double window, 46 is a corridor, and 47 is a wiring pit for storing wiring.
[0006]
Next, the construction method of the clean room by embodiment is demonstrated in order with reference to FIG. Here, an example is shown in which construction management is performed in six stages.
・ Step 1
Carry out frame construction and steel frame construction. From this step 1, the entrance / exit of the room occupant and the carry-in entrance for the materials are designated. Then, sweeping and cleaning are performed every day and every work.
Immediately after the completion of the frame construction in step 1, as shown in FIG. 1, the sheet material 1 is laid on the frame floor 21 in the underfloor area 20, and the sprayer 2 sprays water into the clean room under construction.
As described above, by laying the sheet material 1 on the cabinet floor 21 in the underfloor area 20 immediately after the completion of the cabinet construction, it is possible to prevent dust from floating due to dust generation from the cabinet floor 21 and to spray water. By doing so, the dust floating in the clean room under construction adheres to the spray water 2a and falls onto the sheet material 1, so that the dust floating in the clean room space under construction can be efficiently removed.
In addition, the spray water 2a which adhered to the dust and fell on the sheet | seat material 1 is sucked up with a vacuum cleaner suitably. Moreover, spraying is performed every day, and the sheet material 1 is appropriately replaced depending on the degree of contamination.
In this way, the dust prevention and gradual dusting work by laying the sheet material 1 on the frame floor 21 and spraying water into the clean room under construction is performed until the process proceeds to step 3.
Step 2
Assembly work of scaffolding, wall foundation concrete molding plate such as ALC plate, wall foundation board, ceiling deck, fireproof coated calcium plate installation work, joinery installation work, ceiling deck painting work, etc. From step 2 onwards, the room entry is required to enter the room. Further, cleaning is performed using a vacuum cleaner or the like every time daily work is completed and every lap.
・ Step 3
Scaffold dismantling work, floor painting work, cloth pasting work, sealing work, joinery and steel frame paint work, etc. From this step 3, the joinery is always closed and, as shown in FIG. 1, dry air 3 a is sent into the clean room under construction using a temporary air conditioner 3 (for example, an air conditioner with a dustproof function). Thereby, the dew condensation in the clean room under construction, especially the dew condensation on the interior finish surface such as the cloth surface and the painted surface can be prevented. The supply of the dry air 3a by the temporary air conditioner 3 is continued until the air conditioner 31 is installed and operated in the ceiling area 30. Further, the same cleaning as in step 2 is performed.
・ Step 4
Perforated floor (grating) construction, ceiling area construction, power piping wiring construction, air conditioning duct piping construction, etc. From step 4 onwards, the room occupants are required to wear clean suits (rough ones). In addition, water wiping and cleaning is performed every day and every cycle.
・ Step 5
Installation of inner wall panel in process area 10, installation work for underfloor equipment, pure water piping work, chemical piping work, etc. From this step 5, it is mandatory to enter the regular entrance route, that is, enter from the previous room. In addition, the interior materials are wiped clean with pure water in daily cleaning and general cleaning every lap.
・ Step 6
Installation work of the air conditioner 31 and air cleaning filter 32, gas equipment work, trial operation (air circulation operation) of the air conditioner 31 and the like are performed. From this step 6, it is mandatory to wear a regular clean suit and enter the room through an air shower. Further, the same cleaning as in step 5 is performed.
[0007]
In the above, the example in which the dry air 3a is supplied into the clean room under construction from Step 3 onward, that is, from the start of the interior work, is shown. You may make it supply the dry air 3a.
Further, as the sheet material 1, for example, if a wet sheet impregnated with a liquid waterproofing agent is used, it is possible to prevent the dust once dropped on the wet sheet from rising again into the space and floating, Since the waterproof treatment is performed, it is possible to prevent the spray water 2a adhering dust from penetrating into the frame floor 21 and contaminating the frame floor 21.
Moreover, the division of the construction by the above steps is an example, and is not limited to this.
[0008]
【The invention's effect】
According to the present onset Akira, in prior to entering the interior construction of the clean room, it is possible to prevent the floating of dust in a clean room in construction, in the interior construction work after the clean room, it is possible to prevent condensation on the interior surface finish.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram for explaining a clean room construction method according to an embodiment of the present invention;
FIG. 2 is a cross-sectional view showing an outline of a clean room constructed by the construction method according to the embodiment.
[Explanation of symbols]
3 Air conditioner, 3a Dry air.

Claims (1)

クリーンルームの内装工事に入る前においては、クリーンルームの躯体床上にシート材を敷設して躯体床からの発塵による粉塵の浮遊を防止するとともに、施工中のクリーンルーム内に水を噴霧して施工中のクリーンルーム内に浮遊している粉塵を噴霧水に付着させてシート上に落下させ、クリーンルームの内装工事以後においては、施工中のクリーンルーム内にドライエアを供給して内装仕上げ表面における結露を防止したことを特徴とするクリーンルームの施工方法 Before starting clean room interior construction, lay sheet material on the floor of the clean room to prevent dust from floating due to dust from the floor, and spray water into the clean room that is being constructed. The dust floating in the clean room was attached to the spray water and dropped on the sheet.After the clean room interior work , dry air was supplied to the clean room under construction to prevent condensation on the interior finish surface. A clean room construction method .
JP2002329421A 2002-11-13 2002-11-13 Clean room construction method Expired - Fee Related JP4290963B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002329421A JP4290963B2 (en) 2002-11-13 2002-11-13 Clean room construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002329421A JP4290963B2 (en) 2002-11-13 2002-11-13 Clean room construction method

Publications (2)

Publication Number Publication Date
JP2004163004A JP2004163004A (en) 2004-06-10
JP4290963B2 true JP4290963B2 (en) 2009-07-08

Family

ID=32807427

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002329421A Expired - Fee Related JP4290963B2 (en) 2002-11-13 2002-11-13 Clean room construction method

Country Status (1)

Country Link
JP (1) JP4290963B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4597769B2 (en) * 2005-05-24 2010-12-15 東洋熱工業株式会社 Clean room and its design and construction method
CN106403133A (en) * 2016-09-23 2017-02-15 安徽丰磊制冷工程有限公司 Dust removal and air exhaust system of GMP solid preparation workshop
CN106369730A (en) * 2016-09-23 2017-02-01 安徽丰磊制冷工程有限公司 Dedusting and exhaust system of good manufacturing practice (GMP) aluminum plastic packaging workshop
KR102333654B1 (en) * 2021-06-22 2021-12-01 정미진 Duct construction method for air conditioning system

Also Published As

Publication number Publication date
JP2004163004A (en) 2004-06-10

Similar Documents

Publication Publication Date Title
JP4290963B2 (en) Clean room construction method
US7818941B2 (en) Plastic sheet barrier enclosure, system, and method
JP4290964B2 (en) Clean room construction method
WO2021186770A1 (en) Connection structure between partition wall and floor and construction method therefor
CN115110720A (en) Putty construction method
JP3958591B2 (en) Clean room
JP4454983B2 (en) Clean room construction method
US11702850B2 (en) Wall structure with horizontal base stud
DE69720418D1 (en) INTERIOR COVERING FOR RENOVATING ROOMS, IN PARTICULAR BATHROOMS, AS WELL AS METHOD FOR RENOVATING SUCH ROOMS
US20030156974A1 (en) Mold prevention system and methods
CN211172651U (en) Assembled furred ceiling
Hallman et al. RG Stokstad Lawrence Berkeley Laboratory
JP3898517B2 (en) Clean room
CN116065847A (en) A low-cost retrofit method for existing buildings with ultra-low energy consumption
JP3867846B2 (en) Clean room joinery structure
JP3155063B2 (en) Manufacturing method of floor sheet and construction method of floor material
US9708827B1 (en) Relocatable corrosion control facility
Benator et al. Case Study: Microbial Abatement of a Moldy Hotel
JP3883873B2 (en) Clean room wall structure
JP7648835B2 (en) How to deodorize a room where a deceased person was left
KR20160141548A (en) Humidification type asbestos stabilization system
ES2109036T3 (en) PROCEDURE FOR THE CLEANING AND SANITATION OF ASBESTOS-CEMENT PLATES.
JP2025128543A (en) Deodorizing method for a room where a deceased person was left
JP3016805U (en) Surface finishing structure of ALC outer wall surface and covering sheet material used for this
JPH06207468A (en) Cleaning methods for paper manufacturing, cardboard factories, and factories with similar conditions

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051020

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080911

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080930

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20081119

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090331

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090402

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120410

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130410

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130410

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140410

Year of fee payment: 5

LAPS Cancellation because of no payment of annual fees